DPRMainReport PDF
DPRMainReport PDF
DPRMainReport PDF
(DECEMBER- 2019)
Preparation of DPR for Rehabilitation and Upgradation to 2-Lane/ Modified Final Detailed Project Report
2-Lane with Paved Shoulders from km 106 to km 136 of Birpur– (Main Report)
Bihpur Section of NH 106 in the State of Bihar
CONTENTS
4.4.5 Investigation for Natural Ground along Widening side & Realignment . 4-13
4.4.6 Axle Load Survey .......................................................................................... 4-14
4.5. SOIL AND MATERIAL INVESTIGATION............................................................ 4-14
4.5.1 General ........................................................................................................... 4-14
4.5.2 Soil for Embankment, Sub base & Shoulder .............................................. 4-14
4.5.3 Granular Material for Sub base ................................................................... 4-14
4.5.4 Stone Aggregates for Pavement Courses and Cement ............................... 4-15
4.5.5 Sand for use in Pavement Course and Cement Concrete .......................... 4-15
4.5.6 Water for Construction Purpose .................................................................. 4-17
4.5.7 Fly ash ............................................................................................................. 4-18
4.5.8 Manufactured Materials ............................................................................... 4-18
4.6. BRIDGE STRUCTURES ............................................................................................ 4-19
4.7.1 Introduction ................................................................................................... 4-19
4.7.2 Inventory of Existing Bridges ....................................................................... 4-20
4.7.3 Condition Survey of Bridges......................................................................... 4-20
4.7. CROSS-DRAINAGE STRUCTURES ....................................................................... 4-23
4.7.1 Introduction ................................................................................................... 4-23
4.7.2 Inventory and Condition survey of Existing CD Structures ..................... 4-23
CHAPTER 5: ENGINEERING DESIGNS ............................................................................. 5-1
5.1 GENERAL ...................................................................................................................... 5-1
5.2 DESIGN STANDARDS AND METHODOLOGY ..................................................... 5-1
5.2.1 Codes and Guidelines ...................................................................................... 5-2
5.2.2 Geometric Design Standards .......................................................................... 5-3
5.3 ELEMENTS OF DESIGN AND PROVISIONS ......................................................... 5-4
5.3.1 Carriageway Widening Principal .................................................................. 5-4
5.3.2 General Arrangement of Proposed New Bridges ....................................... 5-10
5.3.3 Intersection Improvement Proposals ........................................................... 5-26
5.3.4 Pedestrian and Animal Crossing .................................................................. 5-26
5.3.5 Provisions for traffic guidance and safety and Speed Control Measures 5-26
5.3.6 Traffic Control and Safety Measures .......................................................... 5-27
5.3.7 Lighting .......................................................................................................... 5-27
5.3.8 Landscaping and Arboriculture ................................................................... 5-27
5.3.9 Miscellaneous Features ................................................................................. 5-27
8.1.10. Road signs, Pavement marking, Other Traffic Control devices ................. 8-4
8.1.11. Roadside Furniture and Crash barrier ......................................................... 8-4
8.1.12. Guard Rail Crash Barriers ............................................................................. 8-4
8.1.13. Ingress and Egress ........................................................................................... 8-4
8.1.14. Marking of Overtaking Sections, Sight Distance, Night Visibility ............. 8-4
8.1.15. Vehicles ............................................................................................................. 8-5
8.2. SAFETY ISSUES FOR NON MOTORISED TRAFFIC ........................................... 8-5
8.2.1. Pedestrian facilities along the road ................................................................ 8-5
8.2.2. Pedestrian Crossings ....................................................................................... 8-5
8.2.3. Lay-byes/Bus Bays ........................................................................................... 8-6
8.2.4. Bicyclist, Rickshaw and Animal drawn carts ............................................... 8-6
CHAPTER 9: TRAFFIC MANAGEMENT DURING CONSTRUCTION ......................... 9-1
9.1. GENERAL ...................................................................................................................... 9-1
9.2. PLAN OBJECTIVES .................................................................................................... 9-1
9.3. PROJECT SITE ............................................................................................................. 9-2
9.4. PROPOSED TRAFFIC MANAGEMENT .................................................................. 9-2
9.5. TRAFFIC CONTROL DEVICES ................................................................................ 9-4
CHAPTER 10: CONCLUSIONS AND RECOMMENDATIONS ...................................... 10-1
10.1. CONCLUSIONS .......................................................................................................... 10-1
10.2. RECOMMENDATIONS............................................................................................. 10-1
10.3. PROPOSED SALIENT FEATURES ......................................................................... 10-1
LIST OF TABLES
LIST OF FIGURES
EXECUTIVE SUMMARY
1 INTRODUCTION
MORTH has decided for widening and strengthening of Single/Intermediate lane of National
Highways in eight states under Non NHDP category for about 3,800 km. Some of these
stretches are proposed to be improved through the assistance of World Bank. The total
stretches are classified in to four groups namely Group A, Group B, Group C and Group D.
The project corridor i.e. NH 106 falls under Group B. Accordingly, the MORTH had invited
tenders from eligible Consultancy firms for carrying out Feasibility study and preparation of
Detailed Project Report for Rehabilitation and upgradation to 2-lane/2-lane with paved
shoulders and strengthening of the Birpur-Bihpur Section of NH 106 (km 106 to km 136) in
the State of Bihar. M/s Consulting Engineers Group Ltd has been selected as the preferred
bidder for the above said NH Section in the State of Bihar.
1.1 General
The Project Highway from Birpur to Bihpur on NH 106 starts at Udakishanganj at km 106.00
and ends at Bihpur chowk at km 136.00 at junction with NH 31. The NH-106 Highway
traverses through four districts viz Madhepura, Saharsa and Bhagalpur before reaching
Udakishangunj in the state of Bihar. The road traverses through plain terrain with
carriageway width varying mostly from single lane to Intermediate lane.
The Project Highways starts at km 106.00 at Udakishanganj and ends at Bihpur km 136.00 at
junction with NH 31 in Bihpur (km 321 of NH 31). The road traverses through plain terrain
with single/intermediate carriageway with its widths varying from 3 m to 5 m. In general the
existing right of way varies from 20 m to 24 m. There has been a missing link from Km
124.200 to Km 133.400 which majorly covers the stream of the Kosi River.
The horizontal alignment of the road is generally fluent without sharp curves. There is one
Major Junction at the end of the project stretch where the project road meets NH-31 and 20
Nos. of Minor junctions along the existing road. The Project Road passes through major
towns like Madhepura, Udakishanganj and Phulaut.
Area in
94163 94163 2420 2420 1,787 1,787 1,686 1,686 2570 2570
sqm
Population
82878796 10,38,04,637 1,745,069 2,228,815 1,526,646 1,994,618 1,508,182 1,897,102 2,423,172 3,032,226
(millions)
Male 43153964 5,41,85,347 902,207 1,157,185 797,180 1,042,373 789,432 995,502 129,658 1,614,014
Female 39724832 4,96,19,290 830,371 1,070,582 729,460 952,245 718,750 901,600 1,131,514 1,418,212
Population
880 1,102 724 919 854 Project895
1,116 start 1,125 943 1180
Density per
km 0.00
sq. km
Male 60.32 73.39 52.42 71.65 48.8 63.82 51.6 65.22 59.22 72.3
km 26.200
Female 33.57 53.33 20.81 46.63 22.11 42.75 25.27 42.73 38.13 56.49
Population
Growth 21.54 25.01 29.25 28.62 km 27.000
29.45 30.65 33.03 25.79 27.24 25.13
Rate
Per capita
km 45.610
NDDP 6724 5,094 4,950 5,879 7,313
(2004-05) km 45.740
NH
106
3 TRAFFIC STUDIES AND ANALYSIS
NH
107 NH
106
NH
31
Based on the Traffic studies conducted for the project road from km 106.000 to km 136.000
(Birpur – Bihpur Section of NH 106 in the state of Bihar (30 kms), the summary of the major
findings are listed below:
The journey speed of the corridor is about 32 km/h in morning and evening peaks.
The road user willingness to pay toll is 97.14% and 2.86% are not willing.
Traffic demand forecasting: The traffic growth rates have been derived based on the
past traffic data as well secondary data collected on socio economic parameters like
state (NSDP, NNP, GSDP, PCI, Population growth) with this the transport demand
elasticity’s found out and regression analysis have done to derive the final growth
rates.
The traffic in the year 2010 at km 65.000 is 7,523 PCU and at km 106.000 it is 3,210
PCU Before the development of Kosi Bridge (Missing Link not developed). The
above figure shows a clear reduction of 50% of total traffic on the project road after
km 65.000.
After the development of Kosi Bridge the users will use the project road because it is
shorter in length amongst all other alternatives and the traffic is expected to increase
by 50% than the originally projected traffic after the construction of Kosi Bridge and
upgradation of project road, i.e. in the year 2020.
The above table shows the capacity for 4 lane of 10,000 PCU as per ministry vide
circular No. RW/NH-33044/28/2015/S&R (R) exceed in the year 2026 for project
road section of NH-106 from km 106.000 to 136.000. Moreover, the construction of
10 km (including approaches) Kosi Bridge may take more than 3 years for
completion.
By the time the bridge is under operation, the traffic at that section reaches close to its
2 lane capacity and as it is a major structure involving huge investment, time &
complex construction conditions, it is proposed to be 4 lane instead of 2 lane as it
cannot be upgraded frequently.
Detailed Reconnaissance survey, Inventory and Condition Surveys for bridges, cross drainage
structures and drainage provisions, Detailed Topographic Surveys using Total Station,
Pavement Investigations, Sub-grade characteristics and strength-Investigation of required
sub-grade and sub-soil characteristics and strength for road and embankment design and Sub-
soil Investigations, Investigation for bridges including hydrological and geotechnical
Investigations, Identification of sources of construction material and Traffic surveys like
Classified Traffic Volume Count, Origin-Destination & Commodity Movement Surveys,
Turning Movement Surveys at important junctions, Axle Load Survey and Speed-Delay
Survey, Pedestrian and Animal count survey and willingness to pay survey.
The width of roadway including shoulders unless otherwise specified shall be 14.0 m
including earthen shoulders. On horizontal curves with radius upto 300 m, width of
pavement and roadway shall be increased as per IRC SP 73.
The entire road stretch comprises of earthen shoulder(ER) on both sides. The
condition of the shoulder on the entire stretch varies between fair and poor.
The Project Highway traverses mostly through plain terrain, with occasional rolling
terrain. The horizontal alignment of the project stretch is fluent without sharp curves.
The road passes through agricultural lands, settlement areas etc. The settlement area
including the schools, villages and urban area traverses about 8 km along the stretch.
The agricultural land which is both the source of income and chief occupation in the
area accounts to 12 km and rest of the corridor is occupied by shops, bus stops and
which adds up to commercial area of 2 km.
The embankment height along the project stretch varies from 0 to 2.5 m.
The existing drainage pattern along the Project Road is poor due to lack of balancing
culverts. As per inventory done, in most stretches of the Project road there are no
drains, in few stretches there are partially existing drains and in few stretches there are
ponds and nalas. Since the Project Road lies in the Kosi river basin which is a flood
affected region, the improvements of the drainage condition is very much essential.
There is one major intersections and 20 Nos. of minor intersections along the whole
project.
The duct for passing the utility services have not been seen by the side of the road
neither water nor sewer pipeline. The overhead electric poles and telephone cables are
running parallel to the road within the ROW and present outside the earthen shoulder.
Hand pumps to be relocated are 3 nos. The street lights are available on the urban
sections of the road.
The pavement condition varies from fair to very poor. Major flexible pavement
distresses include cracking, raveling, pot holing, patching, ruts and pavement edge
drop. The Pavement investigations carried out on existing pavement condition to
determine the most technically sound and economically feasible pavements design.
Existing Existing
S. From To Length Widening Proposed
Carriageway ROW
No. (km) (km) (km) Scheme Cross Section
Width (m) (m)
1 106.0 114.0 3.05 8.0 17 to 24 LHS 2-lane with PS
2 114.0 116.0 3.05 2.0 24 RHS 2-lane with PS
3 116.0 124.0 3.05 8.0 24 LHS 2-lane with PS
4 124.0 133.5 Four lane bridge having 6.93km length
5 133.5 136.0 3.05 2.5 24 LHS 2-lane with PS
The location, type and features of the at-grade intersections/junctions are given in the tables
below. All intersections/junctions shall be improved as per manual. However, the Contractor
shall improve upon the layout plan and features of the intersections/junctions within the Site
with prior approval of Authority’s Engineer
Existing Design
S. Overall width
Chainage Chainage Remarks
No. (m)
(km) (km)
1 112+757 112+845 16.0 Minor Bridge
2 112+816 112+900 16.0 Minor Bridge
3 117+700 117+020 16.0 Minor Bridge
4 121+246 120+145 16.0 Minor Bridge
5 122+634 121+675 16.0 Minor Bridge
6 123+056 122+092 16.0 Minor Bridge
7 135+587 134+505 16.0 Minor Bridge
The existing culverts at the following location are proposed to be constructed as new
culverts. Size of the culvert are proposed to be designed based on hydraulic parameters but
the size mentioned below is to be followed as a minimum.
Table ES.8: Re-construction of Existing Culverts
Apart from the above additional new culverts are proposed for construction as per
particulars given in the table below:
Table ES.9: Details of Proposed additional Pipe culverts (1x1.2m)
The salient features of the project road are shown in the table below,
S.
Descriptions Features
No.
28.918 km
1 Design Length (km.)
(Ch. 106.000 to Ch. 134.918)
24m to 60m
2 Proposed ROW
150 m at Toll Plaza Section
S.
Descriptions Features
No.
The existing highway shall be upgraded to 2 lane/ 2 lane
paved shoulder with Four lane bridge over Kosi river
3 Configuration
having 6.93km length 120 span of 2x12.5m & 6 span of
2x15.2 carriageway and total 126 Nos. x 55m Span.
4 Bypass NIL
Grade separated
5 NIL
Structure
6 ROB NIL
7 Major Junctions 1 Nos.
8 Minor Junctions 20 Nos.
Slip Roads/ Service
9 NIL
Roads
01 No (km 125+110 to km 132+040) over Kosi river
10 Major Bridges having 6.93 km length and 120 span 2x12.5m & 6 span
2x15.2 carriageway and total 126no. x55m SPAN
7 Nos.
Minor Bridges
11 (Reconstruction of Existing Minor Bridge: 6 Nos.
(with footpath)
Reconstruction of Existing Causeway: 1 No.)
66 Nos.
12 Culverts (Reconstruction: 10 No. New Pipe: 24 No.
New Box: 32 No.)
13 Truck Lay Bye NIL
14 Bus Bays 8 Nos.
15 Toll Plaza 1 No. at Ch.133+450
8 SAFETY MEASURES
In this project the evaluation of Highway Improvement Schemes i.e., imparting safety into
the highway system during design and at the end of construction preferably, before the
scheme is open to traffic is planned to identify potential road safety problems that may affect
many users of the highway and to suggest measures to eliminate or mitigate those problems.
8.1 Safety considerations are incorporated in the design
Design standards for whole project uniformly applied essential from the view point of
road user’s safety and the smooth flow of traffic.
Both horizontal and vertical geometry are given importance at all stages.
The designs are consistent and the standards proposed for the different elements are
compatible with one another and abrupt changes in the design speed were avoided.
“Ruling” standards are followed and “Minimum” standards are followed for safety
considerations only where serious restrictions encountered by technical or economic
considerations.
8.2 Designing for the Users
The road elements and road installations are designed keeping human criteria and behavior in
view. The proposed safe environment contains:
Warnings for drivers of any substandard or unusual features.
Signs to guide the driver through unusual sections.
Markings to control the driver’s passage through conflict points or sections.
8.3 Design Speed
The warning signs are considered wherever reductions in design speed are obligatory
8.4 Horizontal and Vertical curves
In any given section of the project corridor, curves are consistent with safe design criteria to
avoid creation of unexpected situations for the drivers. On horizontal curves with radius upto
300 m, width of pavement and roadway is increased as per standards. Increasing the degree
of horizontal curvature also tends to increase the cause of accidents. So to overcome this,
super elevation is applied according to IRC guidelines with respect to the proposed centerline
and the rate of change of super elevation is kept not steeper than 5%, thus the horizontal
alignment provided blends well with the surrounding topography.
8.5 Intersections
For safer negotiation at intersections the straight priority is expected from the riders
so clear visibility of signs and markings are offered.
So adequate visibility-distance is provided for emerging traffic and obstructions
present if any are removed at intersections
The traffic comprises non-motorized vehicles also, so safe pedestrian and cyclist
passing are provided at sections where the threshold value crossed as indicated in the
code.
The refuges are provided to enhance pedestrian safety, they not only help pedestrian
to maneuver across safely but also helps in channelization of traffic.
8.6 Pedestrian Facilities along the road
Pedestrians and vehicle facilities are done by provision of guard-rails, secured crossing areas,
footpaths, and grade separators. Pedestrian cross-walks are provided at all major intersections
and such other locations where substantial conflict exists between vehicular and pedestrian
movements.
CHAPTER 1
INTRODUCTION
1.1. BACKGROUND
The road transport in India carries 70% of freight and 85% of passengers of total traffic
annually. With the rapid economic development and GDP increasing at an annual rate of 7%
to 8%, the traffic volumes in NH are increasing. The present National Highways are going to
be congested very soon based on the average growth rate over the last five years. Hence, it is
necessary to plan and provide a good road network which will facilitate more economical,
safe and environment friendly movement of passenger and goods vehicles, resulting in better
accessibility to health services, education centers, jobs and transportation of local produces to
the market areas. Good roads would improve socio-economic, industrial, and agricultural
activities and help in economic growth of the nation.
About 19,702 km single lane or intermediate lane National Highways exist in the country.
Substantial length of such National Highways has already been taken up for improvement in
one scheme or the other, but 5,937 km stretches are not covered for improvement under any
scheme. The Ministry of Road Transport and Highways with an aim to improve
interconnectivity has under taken development of about 3,800 km single or intermediate lane
National Highways to 2 lane/2 lane with hard shoulders configuration under National
Highways Interconnectivity Improvement Project (NHIIP) aided by the World Bank. The
total No of Project Roads (non-NHDP roads) under this scheme is 33 across 8 states. State
vise details are as follows:
S No. States No. of Roads Length (km)
1 Andaman & Nikobar Islands 1 277
2 Bihar 7 807
3 Himachal Pradesh 6 640
4 Karnataka 3 663
5 Orissa 8 558
6 Rajasthan 2 216
7 Uttarakhand 4 448
8 West Bengal 2 161
The approximate cost of Projects is about Rs.18,500 crores or 3.70 billion US Dollars. The
MORTH has decided to implement NHIIP in three tranches and target the completion by the
end of year 2014 and accordingly invited tenders from eligible Consultancy firms for
carrying out Feasibility study and preparation of Detailed Project Report for rehabilitation
and up gradation to 2 lane/2 lane with paved shoulders configuration of all the above 33
sections of National Highways under NHIIP and awarded the work to the perspective
Consultants.
For implementation of the Project, the MORTH has opened Project Implementation Cell
(PIC) at its Head Quarters in New Delhi and PWD of respective states are declared as
Executing Agency. The Ministry has also appointed Project Coordinating Consultant (PCC)
to monitor and coordinate implementation of the project.
Ministry of Road Transport & Highways, Government of India has decided to upgrade the
entire single lane/intermediate lane National Highways to at least two lane standards. The
work would be taken up for up gradation on corridor concept. Therefore, corridors include
strengthening (in adjoining reaches) in addition to widening to 2 lane/2 lane with paved
shoulder standards in order to have a better facility in a long continuous stretch.
In view with above, MORTH has invited proposal from eligible Consultancy firms for
carrying out Feasibility study and preparation of Detailed Project Report for Rehabilitation
and upgradation to 2-lane/2-lane with paved shoulders and strengthening of the Birpur-
Bihpur Section of NH-106 from km 0.00 to km 136.00. The project has been divided in to
two packages. Package-1 consists from 0.00 to km 106.00 and package -2 from Km 106.00 to
km 136.00. This report is related to Package-2 from km 106.00 to km 136.00 that includes
Kosi Bridge. M/s Consulting Engineers Group Ltd has been selected as the preferred bidder
for the above said NH Section in the State of Bihar.
1.2. SCOPE OF SERVICES OF THE PROJECT
Scope of Consultancy Services as per TOR is as follows:
1.2.1 The Consultant shall provide the widening/improvement work to 2-lane/2-lane with
paved shoulders within the existing Right of Way, avoiding land acquisition as far as
possible, except for locations having inadequate width and where provisions of short
bypasses, service roads, alignment corrections, improvement of intersections are considered
necessary and practicable and cost effective. However bypass proposals should also be
considered, wherever in urban areas, improvement to 2-lane of the existing road is not
possible. The Consultant shall furnish Land Acquisition details (i.e. all necessary schedules
as per LA Act) as per revenue records/maps.
1.2.2 The Consultant shall study the possible locations and design of Toll plaza. Wayside
amenities required on tolled highway shall also be planned. The local and slow traffic may
need segregation from the main traffic and provision of service roads and fencing may be
considered, wherever necessary to improve efficiency and safety.
1.2.3 The Consultant will also make suitable proposals for widening/improvement of the
existing road to 2-lane/2-lane with paved shoulders, etc, and strengthening of the
carriageways, as required at the appropriate time to maintain the Level of Service over the
design period.
1.2.4 . Environmental Impact Assessment, Environmental Management Plan and
Rehabilitation and Resettlement Studies shall be carried out by the Consultant meeting the
requirements of the World Bank.
1.2.5 Consultant is required to prepare all Land Acquisition papers (i.e. all necessary
schedules as per LA Act) for acquisition of land either under NH Act or State Act.
1.4.4. Climate
The climate of the project area is highly induced by the Himalayan Terrain. Rains are very
frequent here. Bihar experiences four seasons. The average temperature stands for 300C. The
atmospheric pressure comes down up to 980-990. The moisture in the air decreases sharply.
The State has a tropical monsoon climate with three distinct seasons; winters, summer and
rainy and can be divided into three climate zones:-
(a) Sub-Himalayan zone
(b) Ganga plains zone, and
(c) Parts of Chotanagpur plateau zones of south Bihar.
The winter between December and February with a minimum temperature between 4oC and
10o C is followed by summer between March and May with a maximum temperature between
35oC and 40oC, the Monsoon season is between June and September with a average rainfall
of 1384mm and the post- monsoon season from October till December.
1.4.5. Terrain
The Project Road lies in a plain terrain with occasional rolling terrain. The horizontal
alignment of NH 106 is fluent except for some sharp curves from km 106 to 136. There is a
missing link of about 10 km length from km 124 to km 134.
1.4.6. Roadside Development and Villages
There are a total of 16 villages along the Project stretch. The Project Road passes through a
major town Phulaut and few minor settlements. The detailed list of villages along the Project
Highway is given in Table 1.3.
Table 1.3: Name and Location of Towns and Villages along the Road stretch
S. No. Name of the Village/Town From (km) To (km) District
1 Rambagh 106+000 107+000 Madhepura
2 Rahata 107+000 108+000 Madhepura
3 Barteni 108+000 111+000 Madhepura
4 Madheli 111+000 114+200 Madhepura
5 Kursandi 114+200 115+000 Madhepura
6 Karama 115+000 119+000 Madhepura
7 Sapardha 119+000 119+200 Madhepura
8 Bathkariyavasa 119+200 122+000 Madhepura
9 Jagdishpur 122+000 124+000 Madhepura
10 Phulaut 124+000 126+000 Madhepura
11 Barikhalvasa 126+000 127+000 Madhepura
12 Ghagriaghat 127+000 128+000 Bhagalpur
13 Lakhiraivasa 128+000 130+000 Bhagalpur
14 Trimohanghat 130+000 133+000 Bhagalpur
15 Hario 133+000 135+000 Bhagalpur
16 Bihpur 135+000 136+000 Bhagalpur
Existing km
S. No. ROW (m)
From (km) To (km)
1 106.000 107.000 24.0
2 107.000 108.000 24.0
3 108.000 109.000 24.0
4 109.000 113.000 24.0
5 113.000 114.000 24.0
6 114.000 115.000 24.0
7 115.000 115.950 24.0
8 115.950 116.000 24.0
9 116.000 117.000 24.0
10 117.000 119.000 24.0
11 119.000 120.000 24.0
12 120.000 120.370 24.0
13 120.370 121.410 24.0
14 121.410 122.000 24.0
15 122.000 124.200 24.0
16 124.200 133.400 0.0 (Missing Link)
17 133.400 136.000 24.0
Hoping that after improvement of project road and construction of missing link the traffic will
improve on the traffic on project road.
Design of complete drainage system and disposal point for storm water
Strip plans indicating the scheme for widening, location of all existing utilities, trees
and plants and land acquisition requirements.
Climate
Availability of construction-materials
c) Inventory and Condition Surveys for bridges, cross drainage structures and drainage
provisions;
d) Detailed Topographic Surveys using Total Station;
e) Identification of possible improvements in the existing alignment and bypassing
congested locations with alternatives, evaluation of different alternatives, comparison
of techno-economic and other considerations and recommendations regarding most
appropriate option;
f) Pavement Investigations;
g) Sub-grade characteristics and strength-Investigation of required sub-grade and sub-
soil characteristics and strength for road and embankment design and Sub-soil
Investigations;
h) Investigation for bridges including hydrological and geotechnical Investigations
i) Identification of sources of construction material;
The Engineering surveys and Investigations carried out are discussed in Chapter-4 of this
Report.
elasticity of transport. The demand estimate is worked out assuming three scenarios namely,
optimistic, pessimistic and most likely traffic growth. The growth factor is worked out for
five years interval considering Socio economic development plans, land use patterns of the
region, and projection of vehicle manufacturing industry. The detailed Traffic forecasting and
demand is discussed in detail in Chapter-3 of this report.
strata is therefore very essential for safe & economical design of foundations. The
performance of supporting stratum depends upon the physical properties of subsoil, type &
shape of footing & structure, water table depth, etc. It is therefore necessary to have sufficient
information about the arrangement & behavior of the underlying materials and their physical
properties, for adopting and designing the structural foundation. Soil exploration through
field investigation and relevant laboratory testing of the substrata are essential to arrive at the
required parameter for designing of foundations.
Geo-technical investigations are carried out at the sites and locations approved by MORTH
on the Project Stretch for various structure locations and high embankments in accordance
with the requirements spelt out in the TOR. The Project Highway traverses through mostly
flat terrain, and based on secondary data and site reconnaissance during the preparation of the
Inception Report, rocky outcrops may not be expected to be encountered during boring. Most
of the terrain is underlain by the flood plain deposits of the Indo-Gangetic Alluvium. Hence,
the geo-technical investigations were planned accordingly and keeping in mind the site
constraints.
Field investigation at the site were carried out to determine the subsurface conditions and the
required strength characteristics of the underlying soil/rock strata in order to design the
foundation of the proposed structures at various locations. The data obtained from these
investigations conjointly with the laboratory data, are analyzed to arrive at the required
parameters, for the safe design of the foundation of the proposed structures.
The basic „Input Rates‟ to Standard Data Book have been provided from the second resource
document Schedule of Rates and Analysis” (SoR) issued by Engineer-in-Chief, Road
Construction Department (including National Highways Wing), Government of Bihar
effective from 1st April 2017. The SoR, Bihar provides all inputs rates of carriage, materials,
labour, machinery and also provides systematic „input sheets‟ compatible with Standard Data
Book for Analysis of Rates. Thus the unit rates are derived based on the data given in the
Standard Data Book of MORTH .Based on this rate analysis of the various item of the work
has been done and done separate volume.
CHAPTER 2
SOCIO- ECONOMIC PROFILE
2.1. GENERAL
Ministry of Road Transport and Highways (MORTH) has taken up the up gradation of
various single/intermediate/two lane National Highways to 2 lane/ 2 lane with paved
shoulders with the assistance from World Bank for National Highways Inter connectivity
Improvement Project (NHIIP-1). Consulting Engineers Group Ltd has been awarded the
preparation of Detailed Project Report (DPR) including social study for the sub project NH-
106 (SP/B/3) Birpur to Bihpur road in the state of Bihar. The Project Stretch NH-106 from
Birpur to Bihpur traverses through 88 villages and falling in four Districts i.e. Supaul,
Madhepura, Saharsa and Bhagalpur.
The Project Stretch for package-2 of NH 106 starts at Udakishanganj at km 106.00 and ends
at Bihpur chowk at km 136.0 of NH 106 beside Hanumanji Mandir on RHS corner (km 321
of NH 31) .
The road development is confined mostly within 24 m width of ROW. The people who are
most affected are the encroachers and squatters within available ROW and those whose land
is acquired for the development of the road for realignments for geometric improvements.
Table 2.1: Demographic Features of the State and Project Area Districts
Population
880 1,102 854 1,116 943 1180
Density per sq.
Population
21.54 25.01 29.45 30.65 27.24 25.13
Growth Rate
Source: Statistical Abstract, 2001-11, Directorate of Economics and Statistics, Govt of Bihar.
2.3. URBANISATION
Urbanization is both a driver and a consequence of economic growth. The development of an
urban area is also closely linked with the rural economy through exchanges of goods,
services; labor, capital, information - technology and social transactions. In 2001, the level of
urbanization in India as a whole was 27.78%, but in Bihar it is observed that only 10.47%.
The details of level of urbanization in the state of Bihar are given in Table 2.2 and the same
is depicted in Figure 2.1 and Figure 2.2.
Table 2.2: Urban Population by Class of Towns affecting the Project Road
Bhagalpur 1 0 2 2
Madhepura 0 0 3 0
Bihar 19 18 67 18
The comparison of level of Urbanization has been presented for the state of Bihar others for
(1991 & 2001) are given in Figure 2.1 and per capita GSDP of some Indian states are plotted
in Figure 2.2.
Table 2.3: State Domestic Product (NSDP) and Per Capita Income
(at Constant 2004-05 Prices) (Rs. crores)
Product) GSDP as against 23–24% on all India basis and employs less than 10% of the
workforce. Highest contribution comes from food/beverages in districts.Agro-based industry and
petroleum products (primarily, Barauni oil refinery) account for around 85 per cent of the total
industrial output in the state. There are 272 large and medium industries, a majority of which are
located in Patna. Tirhut is the other major industrial centre. Small scale industries, micro and
artisan enterprises play a major role in terms of employment. As on, September 2009, there were
178,863 permanent registered units with total investment of US$ 232.9 million and providing
employment to 0.58 million workers. Figure 2.8 shows the industrial distribution in Bihar State.
There is 3,642 km of National Highways and 3,989 km of State Highways in Bihar. Besides,
there are major district (8,156 km) roads , other district roads (8,156 km) and village roads
(63,262 km).The State Government aims to provide road infrastructure in Bihar, equivalent to
best in the country by 2015. According to the State Plan of the Road Construction Department of
the State, the budgeted outlay for roads and highways was US$ 576 million for 2009-2010, up
from US$ 58.5 million for 2005-06. The major roads in Bihar are shown in Figure 2.9. The
targets achieved under various heads are shown in Figure 2.10. In terms of physical
achievement, compared to construction of 415.5 km of road in 2005-06, 2,417.1 km of road was
constructed in 2008-09.
Table 2.5: On Road vehicles on the Project Road and the Project Road Districts
Agriculture has reportedly registered an unbelievably high growth rate of 9% per annum
average between 2004–05 to 2008–09, with agricultural NSDP increasing from Rs 18,155crore
in 2004–05 to Rs 26,399 crore in 2008–09. This 9% growth rate claim certainly does not tally
with the stagnant and crisis-ridden agricultural scene on the ground. Actually, the agricultural
NSDP in Bihar in 2005–06 at Rs 17,812 crore was lower than Rs 18,735 in 2000–01 and the
intervening years witnessed virtual stagnation in Bihar agriculture. In view of this prolonged
stagnation, recovery in 2006–07 which saw an agricultural NSDP of Rs 23,700 crore marked a
sharp increase in growth rate in 2006–07 over 2005–06, something like 29% in a single year.
This jacked up the overall trend growth rate per annum in the last five years.
The Overall Industrial Sector – Comprising Mining & Quarrying, Manufacturing, construction
and electricity-gas-water supply – NSDP has also clocked a significant 25.4% growth (23.4% in
GSDP) over the five years from a negative growth earlier. The manufacturing sector in Bihar
grew from paltry Rs 3,379 crore in 2004–05 to Rs 4,852 crore in 2008–09.
The secret of high growth in Bihar lies in the exceptionally high growth in construction. The
construction sector in Bihar grew from Rs 3,766 crore in 2004–05 to Rs 12,033 crore in 2008–
09, almost three-and-a-half-fold increase. This jacked up the overall growth rate to some extent.
Actually, the substantial growth in Bihar NSDP is accounted by public investment in which the
Central Plan assistance is a very major component. Central assistance to State Plans as well as
Central Plan projects in Bihar has nearly been around Rs 6,000 crore per annum (Rs 30,000 crore
in the last five years).
2.8.2. Tenth Five Year Plan
The Tenth and Eleventh Plans provide a context with reference of which the efficiency of the
planning process in Bihar can be judged. Bihar still remains a predominantly agrarian economy
with a very small manufacturing base, and the share of agriculture in state income still remains
very high. The share of industry has remained practically constant over the years, while the share
of service sectors has gradually increased over the last decade to about 50 percent in 2003-04.
Despite all these challenges Bihar has emerged as a development-oriented state in last few years.
The government has focused on industrial investments, infrastructural improvement and
agricultural input supply.
Present Five Year Plan (2007-2012) emphasizes investment for women’s socio-economic
empowerment, enhancing livelihood opportunities in the farm and non-farm sectors and
participation of local level institutions such as self-help groups to make service delivery more
accountable. The strategy of the Government of Bihar involves effective targeting of the poor,
especially the most vulnerable groups of Scheduled Castes (SCs) and Scheduled Tribes (STs) in
order to make growth inclusive. Table 2.6 shows the targeted growth rate of state as per annual
plan.
Agriculture
To maximize the use of vast untapped potential and natural endowments of the state there by
ensuring food and nutritional security and better farm incomes through environmentally
sustainable agronomic practices.
Education
Bihar will develop itself as an Innovation Hub by evolving an ecosystem of industries and
education systems to encourage Research and Development (R&D) and entrepreneurship. Bihar
will achieve universal secondary education. 50% of the students will enroll for colleges.
Education will be accessible for all and not denied to any one. The education System should be
able to nurture a minimum of one Noble laureate by 2022.
Role of Stakeholders
Towards realizing the vision 2022 the substantive roles of concerted efforts by the various key
stakeholder’s viz., the state government, the industry, the organized bodies/ groups and
individuals.
Role of government:
Facilitate development in the state through appropriate policy initiatives in various key sectors
and taking steps to usher in administrative reforms and facilitate capacity building.
To create world classes infrastructure that facilitated logistics and enables cost competitiveness.
Market the capabilities and potential of the state to the external world.
Role of Industry:
Focus on growth, operate efficiently and be globally competitive. Exhibit drive, ambition and
capabilities to go global and be world leaders.
ambassador for the state & promote its growth.
Role of media/organized bodies/NGOs
Media in Bihar is well entrenched has a wide spread reach and acknowledged capability in
shaping public opinion. The media has a responsibility in ensuring the overall development of
the state. The media should play positive role in the vision exercise in creating awareness about
the vision for the state, mobilizing public opinion and providing a forum for people to discuss the
vision. It should assist in mobilizing public opinion on the vision and act as a watch dog and
monitor stake holder’s action on implementation of the vision .Organized bodies and civil
movements have a long history of shaping government policy in Bihar. Their presence should be
positively canalized to realize the vision.
Role of individuals:
Individuals have a key role to help in the realization of the vision as they are the primary
beneficiary of the development envisaged. Individuals need to involve themselves in the
visioning exercise by providing feedback to the government during the initial stage when the
vision is being discussed in the public forum. They should utilize the opportunities to voice their
concern, if any, and suggest appropriate modification to the vision themes and the
implementation plan.
Consulting Engineers Group Ltd. Jaipur 2-14
Preparation of DPR for Rehabilitation and Upgradation to 2-Lane/ Modified Final Detailed Project Report
2-Lane with Paved Shoulders from km 106 to km 136 of Birpur– (Main Report)
Bihpur Section of NH 106 in the State of Bihar
Bihar under various components for rural development during the current financial year 2009-10
include Rs. 258.99 crores for Swarnjayanti Gram Swarojgar Yojana (SGSY), Rs. 2240.39 Crores
for Indira Awaas Yojana (IAY) and Rs. 17.57 crores for District Rural Development Agency
(DRDA). The allocation of funds under the rural development schemes is done on the basis of
pre-determined criteria framed by the Planning Commission, which include poverty ratio
reflecting the backwardness of the States.
2.8.3. Perspective Growth Rate
The medium term growth rate of NSDP at constant prices, taking the period 1999-00 to 2008-09,
is estimated to be 5.57 percent. Although this growth rate is lower than the national growth rate
of about 6 to7%, it indicates an improved growth performance compared to the recent past when
the state economy had managed to grow at barely 3 to 4 %. The GDDP and NDDP of the project
influenced districts are given in Table 2.7.
Table 2.7: District wise GSDP & NSDP at 1999-2000 Prices (Rs. in Lakh)
District NSDP of Bihar at
Sl
Year Constant Prices (99-00)
No. Bhagalpur Saharsa Supaul Madhepura (Rs in Cr)
1 2000-01 148,876 93,962 76,990 81,145 60045
2 2001-02 154,647 81738 78221 67582 60817
3 2002-03 167846 89551 92293 75503 75439
4 2003-04 175751 86887 77368 73097 82069
5 2004-05 188,334 95,891 94,358 80,933 96,422
Source: State domestic product 1999-2000 to 2006-2007 (Quick) & District Domestic product 1999-2000
to 2004-2005 (Page 50 to 54).
The Per capita GDDP and Per capita NDDP of the project influenced districts are given in Table 2.8.
Table 2.8: District wise per capita GSDP & Per Capita NSDP at 1999-2000 Prices (Rs.)
Bhagalpur Saharsa Supaul Madhepura
Sl Per Per Per Per Per Per Per Per
Year
No. capita capita capita capita capita capita capita capita
GDDP NDDP GDDP NDDP GDDP NDDP GDDP NDDP
1 2000-01 7,042 6,225 6,887 6,325 4,856 4,505 5,779 5,390
2 2001-02 7,139 6,282 5,887 5,320 4,849 4,440 4,754 4,352
3 2002-03 7,573 6,734 6,297 5,728 5,593 5,165 5,193 4,792
4 2003-04 7,899 6,934 6,082 5,439 4,692 4,251 5,008 4,552
5 2004-05 8,268 7,313 6,521 5,879 5,572 5,094 5,417 4,950
Source: State domestic product 1999-2000 to 2006-2007 (Quick) & District Domestic product
1999-2000 to 2004-2005 (Page 50 to 54).
Table 2.9 gives NSDP growth rate for the State. The state had a robust average annual growth of
16.7 per cent between March 2006 and March 2010.
Where,
Gp – Growth rate of Population Gpci – Growth rate of per capita NSDP
NSDP – Net State Domestic Product NNP – Net National Product
CHAPTER 3
TRAFFIC STUDIES AND ANALYSIS
3.1 GENERAL
The objective of conducting traffic surveys is to understand the traffic flow pattern on the
project highway. The Consultants have carried out a reconnaissance survey of the project
corridor to understand the general traffic and travel characteristics on the Project road. The
following traffic studies have been carried out for the project road.
a) Traffic volume count (for 7 days 24 hours duration)
b) Origin – Destination study
c) Intersection Turning movement count survey
d) Speed and Delay Survey
e) Axle load survey
f) Pedestrian movement Survey
g) Animal Crossing Survey
Traffic data is one of the important inputs required for a highway project. The main
objectives of the surveys are to:
a) Establish Base year traffic demand
b) Identification of travel pattern and influence area of the project stretch
c) Pattern of Commodity Movement
d) Deriving Growth Factor for Traffic Demand Forecasting
e) Estimation of corridor traffic including traffic diversion if any
f) Identify traffic bottlenecks and the need for service roads and bypasses to congested
locations.
g) Determine spectrum of traffic loads and vehicle damage factor for different types of
commercial vehicles.
3.2 TRAFFIC SURVEYS
A map study was taken up for the project road and all the possible diversions identified for
the traffic in the project stretch of NH 106. The team members of the study team visited the
site and carried out a reconnaissance survey to identify the proposed locations of the surveys
in conjunction with the network of roads. Traffic survey stations for carrying out Traffic
Volume Count and Origin-Destination survey were selected considering the following
parameters:
The station should be located in a reasonably level terrain with good visibility
Sl. Location
Survey Date Remarks
No. (km)
Traffic volume 31.07.10 to
1 106 Near UdaKishanganj
count 06.08.10
Origin –
2 103 04.08.10 Near UdaKishanganj
Destination Survey
Turning At Udakishanganj (SH 58
105.7 16.7.10
Movement count & NH 106 Crossing)
3
Survey at At Bihpur (NH 31 & NH
Intersections 136 14.7.10
106 Crossing)
All along the Project
Corridor at 2 Trips in each
4 Speed and Delay Whole Stretch 05.08.10
direction by Moving
Observer Method
5 Axle Load Survey 103 04.08.10 Near Udakishanganj
Pedestrian
6 Movement Count 112.1 03.11.10 Near Madheli
Survey
Pedestrian and
8 Animal crossing 111.1 03.11.10 Near Madheli
survey
Truck Terminal
9 105.2 28.11.10 Near Kishanganj
Survey
10 Willingness to Pay 105.2 15.11.10 Near Kishnaganj
Project start
km 0.00
NH
106
km 26.200
km 27.000
km 45.610
km 45.740
NH
106
km 65.000
km 65.900
km 70.000
km 73.000
km 76.200 NH
107
NH
106
NH
107 km 103.000
km 105.700
km 106.000
NH
107 NH
106
NH
31
turning movements from each approach as per guidelines given in IRC: SP: 41. The survey
was conducted recording traffic for each successive 15 minute intervals, for 24 hours with the
help of trained enumerators. Each turning movement at the intersection was recorded by
deploying enumerators in sufficient numbers at suitable locations. The data on peak hour volume
with turning movement flows is used to analyze and design the intersection.
Since the data collected from the site for the various vehicle types having different sizes and
characteristics are to be converted into a standard equivalent unit called Passenger Car Unit
(PCU). The Passenger Car Unit Values (Rural Roads) as suggested in the IRC 64: 1990
“Guideline for Capacity of Roads on Highway” has been adopted are shown in Table 3.3.
Table 3.3: Adopted PCU Values
Motorized Traffic Non-Motorized Traffic
Car, Jeep, Van, Taxi and Utility Vehicles 1.0 Bicycle 0.5
Auto Rickshaw / Tempo / 3 Wheeler 1.0 Cycle Rickshaw 2.0
2 Wheelers 0.5 Animal Drawn 6.0
Mini Bus 1.5 Hand Drawn 3.0
Other Slow Moving
Standard Bus 3.0 1.0
Vehicles
Light Commercial Vehicle (LCV) 1.5
2 – Axle Truck 3.0
3 – Axle Truck 3.0
Multi Axle Truck (Semi Articulated &
4.5
Articulated) /HCM/EME
Agriculture Tractor without Trailer 1.5
Agriculture Tractor with Trailer 4.5
Exempted Vehicles 1.0
At km 106.000 the variation in daily traffic is from 0.85% to -13% of the ADT. Percentage
traffic composition vehicle wise at location km 106 is shown in Table 3.5.
Table 3.5: Percentage Traffic Composition at all stations
km 106.000
Vehicle AADT (No.) AADT (No.)
PCU PCU
in year 2010 in year 2016*
Two - wheeler 1291 646 1730 865
Three-wheeler/Auto rickshaw 72 72 96 96
Car/Jeep/Van/Taxi 432 432 579 579
Mini Bus 18 27 24 36
Standard Bus 48 144 64 192
LCV 31 47 42 63
km 106.000
Vehicle AADT (No.) AADT (No.)
PCU PCU
in year 2010 in year 2016*
Multi-Axle Truck 4 18 5 23
Agri. Tractor With Trailer 155 698 208 936
Cycle-Rickshaw 40 80 54 108
Hand Drawn 2 6 3 9
200
150
Traffic (ADT)
100
50
0
15:00 - 16:00
16:00 - 17:00
17:00 - 18:00
18:00 - 19:00
19:00 - 20:00
20:00 - 21:00
21:00 - 22:00
22:00 - 23:00
23:00 - 00:00
00:00 - 01:00
01:00 - 02:00
02:00 - 03:00
03:00 - 04:00
04:00 - 05:00
05:00 - 06:00
06:00 - 07:00
08:00 - 9:00
09:00 - 10:00
10:00 - 11:00
11:00 - 12:00
12:00 - 13:00
07.00 - 08.00
Time
31.07.10 01.08.10 02.08.10 03.08.10 04.08.10 05.08.10 06.08.10
Truckload (TL) carriers generally move full loads of freight, usually from one firm to one
receiver without having to make an intermittent stop to sort the load.
Less-than-truck load (LTL) carriers generally deliver smaller loads from more than one firm
to be delivered to more than one receiver.
Parcel express carriers make door-to-door deliveries of small packages (usually less than
100 kgs). Parcel express carriers are Federal Express (FedEx) and DHL, their business is a
specific delivery timeframe that ensures on-time delivery based on the customer’s
specifications.
With respect to goods vehicles, the types of goods carried were broadly grouped into 8
categories, plus empty trucks.
2. Perishable Goods
3. Petroleum/Chemical products
4. Building Materials
5. Engineering Goods
6. Garments
7. Parcel Lorries
8. Others
9. Empty
The Origin - Destination survey was carried out at km 103/000 along the project stretch. Data
collected from the site were fed to the computer and compiled for the base year (2010), using
the Zoning system adopted for the study. Mode wise OD matrices for at km 103.000
locations were prepared from the data collected to find the travel characteristics of the traffic.
Zoning Systems
For analysis of O-D data collected from the field, it is required to code it for origin and
Destination of trip. The zoning was done in three levels. In first level, all-important towns
(traffic generators) lying on the project road have been assigned a separate zone code. Next
immediate influence areas of project road were considered and nearby districts were
delineated as separate zones. Finally, states beyond the influence area were aggregated
broadly in the eastern and southern direction of project highway. The details of the traffic
zones adopted for the study are given in Table 3.8.
O-D zoning Map showing immediate and intermediate zone is given in Fig. 3.3(a) and Broad
influence zone in Fig. 3.3(b).
PASHCHIM
NEPAL
34
CHAMPARAN
PURBA
34 SITAMARHI
GOPALGANJ 34 15
23
CHAMPARAN MADHUBANI 1 1 BIRPUR
BHIMNAGAR 1BASANTPUR
2
SIMHARA 30
4
34 GHANPATGANJ RAGHOPUR
3
22 KISHANGANJ
SIWAN KISANPUR ARARIA
BANGLADESH
5
6
PIPRA
24 16
34 MUZAFFARPUR DARBHANGA
SARAN 7
UTTAR SINGHESWAR
8 21
PRADESH 25 MADHEPURA
PURNIA
VAISHALI 26 9 GWALPARA
SAMSTIPUR SAHARSA 10BIHARIGANJ
17 11 UDA
12 KISHANGANJ
35 27 18
31 BEGUSARAI KHAGARIA 20
BUXAR 35 ALAMNAGAR
PATNA KATIHAR
BHOJPUR 13PHALUT
14 BIHPUR 38
32
NALANDA 33 28 WEST BENGAL
33 LAKHISARAI MUNGER 19
35 36
JEHANABAD SHIEKHPURA BHAGALPUR
BHABHUA
35
ROHTAS 36 36
GAYA 33 33
AURANGABAD NAWADA
JAMUI 29 37
BANKA
JHARKHAND
JHARKHAND
Himachal Pradesh
43
43
Punjab
Uttarakhand
43
Haryana
43 New Delhi
Arunachal Pradesh
42 42
Sikkim
Uttar Pradesh
Rajasthan 39
Assam 42
44 Nagaland
Bihar 42
1-36 42 Meghalya
Mijoram
42
Jharkhand Tripura 42
Madhya Pradesh' 37 42 Manipur
Gujrat 45 West Bengal
38
44
Chhatisgarh
40
Maharashtra Orissa
41
45
Andhra Pradesh
Goa 46
45
Karnataka
46
46 Tamilnadu
Kerala 46
Commodity details
Different commodities recorded during the O-D survey were classified into 18 categories as
given in below. Due consideration has been given to include all possible commodities moving
along the project road. Classification of commodities is given in Table 3.9.
Table 3.9: Classification of Commodities
Commodity
Commodity Type Description
Code
1 Empty No Load
2 Perishable Products Vegetables, Fruits, Meat, Milk Products, etc.
3 Food Crops Rice, Wheat, Pulses, Bajra, Jowar
4 Cash Crops Cotton, Jute, Sugarcane, Tea, Tobacco, Silk
Manufacturing
5 Electronic & Electrical Goods, Vehicles, Medicines
Products
6 Consumer Products Parchun, Soap, Shampoo, etc (Daily usable Items)
7 Chemical Products Powder, DOC, Fertilizers, Acids, liquor
8 Petroleum Products Oil, Gas, Lubricant, Petrol & Diesel
9 Textile Products Threads, Clothes
10 Building Materials Sand, Pipe, Bricks, Stones, Flyash
11 Cement Cement, Lime stone,
Parcel & Paper
12 Parcel, Courier, Postal Services, Cartoons, Paper, etc.
Products
Wood and Forest
13 Timber, Furniture, & Ply Wood
Products
Machine and
14 Auto Parts, Machinery, Parts, etc
Machine parts
15 Metals Iron Items, pipes, Iron Plates, etc.
16 Minerals & Ores Gypsum, Zinc
Rubber & Plastic
17 Rubber, Tyres, Plastic, etc
Products
18 Miscellaneous Animals, Glass, Bottles, Scrap, etc
km 103.000
Vehicle Type No. Total Lead Average Lead No. Total Load Average Load
km 103.000
Lead Analysis
The survey data was analyzed to assess the lead and load distribution for commercial vehicles.
Trip length frequency distribution at km 103 for goods vehicles giving lead analysis are
shown in Table 3.12 respectively.
Table 3.12: Trip Length Frequency Distribution of Goods vehicle (%) at km 103.000
Graphical representation of trip length frequency distribution for goods vehicles for three
locations is given in Figure 3.6.
80.00%
3- Axle
70.00%
60.00%
% Share
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
0 - 20 20- 50 50 - 100 100 - 250 250 - 500 500 - 1000 1000-1500 1500-2000 more than
2000
Trip Length (KM)
Load Analysis
Load analysis of goods vehicles at one location is given in Table 3.13.
Table 3.13: Load Distribution of Goods vehicles (%) at km 103.000
70.00%
LCV
60.00%
2-Axle
50.00%
3-Axle
40.00%
% Share
30.00%
20.00%
10.00%
0.00%
Empty upto 2.5 2.5 - 5.0 5.0 - 7.5 7.5 - 10.0 10.0 - 15.0 15.0 - 20.0 20.0 - 25.0 25.0 - 30.0 > 30
Load (T)
Table 3.14: Percent Commodity Distribution on the Project road (excluding empty vehicles)
Commodity 103.000
Perishable Products 14.37%
Food Crops 5.91%
Cash Crops 1.90%
Manufacturing Products 0.00%
Consumer Products 0.00%
Chemical Products 0.45%
Petroleum Products 0.00%
Textile Products 0.00%
Building Materials 28.26%
Cement 0.00%
Parcel & Paper Products 0.00%
Wood and Forest Products 0.00%
Machine and Machine parts 24.05%
Metals 0.00%
Minerals & Ores 0.00%
Rubber & Plastic Products 0.00%
Miscellaneous 7.98%
Total 82.91%
60.00%
50.00%
%
40.00%
30.00%
20.00%
10.00%
0.00%
Chemical
Cement
Empty
Food Crops
Rubber &
Metals
Products
Products
Wood and
Manufacturing
Textile
Plastic
Forest
Products
50.00%
40.00%
%
30.00%
20.00%
10.00%
0.00%
Chemical
Cement
Empty
Food Crops
Rubber &
Metals
Products
Products
Wood and
Manufacturing
Textile
Plastic
Forest
Products
50.0%
40.0%
%
30.0%
20.0%
10.0%
0.0%
Chemical
Cement
Empty
Food Crops
Rubber &
Metals
Products
Products
Wood and
Manufacturing
Textile
Plastic
Forest
Products
The journey speed of the test vehicles along the corridor is ranging from 31.40 to 31.70 km/h
in morning peak and 31.10 to 31.86 km/h in evening peak respectively. The running speed is
low at km 106 to km 124 is single lane.
Distribution of Truck types at various stations are presented in Table 3.16.
Table 3.16: Distribution of Truck Types at km 106.000
Sl. No. Truck Types vehicles Year 2010
1 LCV 30
2 2-Axle Truck 69
3 3-Axle Truck 37
4 Multi Axle 4
5 Agriculture Tractor with Trailer 155
6 Agriculture Tractor without Trailer 43
Total 338
Toll Rates
The toll rates have been derived from the study of willingness to pay survey conducted on the
project road and the road users acceptable toll rates are worked out and given in Table 3.17.
Table 3.17: Acceptable toll rates - Percentage of Road users willing to pay
Toll and amount acceptable
% of road users Willingness to pay toll
Sl. No. Locations (km)
Rs. 10 to 20 Not willing to pay
1 120.000 96.43 3.57
Peak hour traffic characteristics at various stations are given in Table 3.19.
Table 3.19: Peak Hour Traffic Characteristics at various stations
Vehicle Type km 103.000
Peak Hour 18:00 - 19:00
Two Wheeler 37.1%
Three Wheeler 1.9%
Car/Jeep/Van/Taxi 17.1%
Mini Bus 0.7%
Standard Bus 1.4%
LCV 1.5%
2-Axle Truck 2.0%
3-Axle Truck 0.5%
Multi Axle 0.1%
Agriculture Tractor with Trailor 3.7%
Agriculture Tractor without Trailor 2.4%
Bicycle 29.6%
Cycle Rickshaw 1.1%
Bullock Cart 0.5%
Hand Drawn Cart 0.2%
Others 0.1%
Total 100.0%
1 111.100 7 4
1 2008 23
2 2009 27
3 2010 24
It is presumed that accidents must have taken place at sharp curves in km 11, km 33, km 44
and km 64.
3.5 CORRIDOR TRAFFIC
The Classified volume count has been conducted at km 106.000. The corridor traffic for the
project road is given in the table below:
Total
Year Truck Bus Car Taxi Jeep 3W 2W Tractor Trailer Other
Vehicles
2000 46636 14493 50376 16067 29498 26009 538337 89438 52399 5106 944,863
2001 47650 15092 54657 20163 31014 28345 585987 99413 59244 3298 1,032,594
2002 48060 15365 58335 20703 32560 38707 644477 107049 63855 3483 1,001,043
2003 48180 15472 61354 20962 33388 31915 608899 110147 65764 4962 1,179,190
2004 48592 15820 64939 21641 35731 34554 767480 116090 67584 6759 1,348,711
2005 49437 16158 71834 22271 39542 39823 903261 125968 73154 7263 1,429,074
2006 50016 16271 76896 22698 41863 43096 964594 129477 75594 8569 1,576,383
2007 52005 17192 84305 24024 46293 48123 1077579 135637 80875 10350 1,738,140
2008 54414 18533 92528 27066 50522 54153 1197875 143801 86233 13015 1,958,553
2009 58012 19654 103077 30857 56270 62576 1364757 155004 93743 14603 1,958,553
Growth Trend (%)
2000-
2.13 3.97 7.83 20.31 4.89 8.24 8.13 10.03 11.55 -54.82 8.50
2001
2001-
0.85 1.78 6.30 2.61 4.75 26.77 9.08 7.13 7.22 5.31 -3.15
2002
2002-
0.25 0.69 4.92 1.24 2.48 -21.28 -5.84 2.81 2.90 29.81 15.11
2003
2003-
0.85 2.20 5.52 3.14 6.56 7.64 20.66 5.12 2.69 26.59 12.57
2004
2004-
1.71 2.09 9.60 2.83 9.64 13.23 15.03 7.84 7.61 6.94 5.62
2005
2005-
1.16 0.69 6.58 1.88 5.54 7.59 6.36 2.71 3.23 15.24 9.34
2006
2006-
3.82 5.36 8.79 5.52 9.57 10.45 10.49 4.54 6.53 17.21 9.31
2007
2007-
4.43 7.24 8.89 11.24 8.37 11.14 10.04 5.68 6.21 20.48 11.25
2008
2008-
6.20 5.70 10.23 12.29 10.22 13.46 12.23 7.23 8.01 10.87 0.00
2009
Average Growth (%)
2001 to
1.16 2.15 6.84 6.02 5.66 6.92 9.41 6.59 6.40 2.76 7.73
2005
2006 to
3.90 4.75 8.62 7.73 8.42 10.66 9.78 5.04 6.00 15.95 7.48
2009
Source: http://www.adb.org/Documents/RRPs/IND/41629/41629-01-ind-ea.pdf
Truck Bus
60000 20000
y = 1065.5x + 44440
R2 = 0.8288 18000
55000
16000
45000 12000
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2W Tractor & Trailor
260000
y = 91451x + 362346
1400000 y = 10865x + 133287
R2 = 0.9511 240000
2
1250000 R = 0.9858
220000
1100000
200000
950000
180000
800000
160000
650000
500000 140000
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Others 2000000
Total
15000
1800000
12000
y = 1207x + 1102.4
R2 = 0.8829 1600000
9000 1400000
y = 124620x + 731299
1200000
6000 R2 = 0.9705
1000000
3000
800000
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
3.6.3 Economic Perspective
State Domestic Product and PCI reflect the overall performance of economy of the state. The
estimates of State Domestic Product are prepared both at current and constant prices for each
year. However, we adopt the NSDP and NNP at constant prices for calculating of elasticity of
Goods vehicles. The perspective growth rate of state NSDP is presented in Table 3.25.
Sl,
Year Gp Gpci NSDP NNP
No.
* The adopted growth rate for NSDP and NNP are considered at lower side which may
increase in future.
Where,
Gp – Growth rate of Population
Gpci – Growth rate of per capita NSDP
NSDP – Net State Domestic Product
NNP – Net National Product
Car/
Year Jeep/ Bus Truck 2W 3W Tractors Trailers
Taxi
2019-2023 1.22 0.81 0.81 1.62 1.62 0.81 0.81
2024-2028 1.09 0.73 0.73 1.46 1.46 0.73 0.73
2029-2033 0.98 0.66 0.66 1.31 1.31 0.66 0.66
2034-2038 0.89 0.59 0.59 1.18 1.18 0.59 0.59
Car/
Year Jeep/ Bus Truck* 2W 3W Tractors Trailers
Taxi
Car/
Year Jeep/ Bus Truck 2 W* 3 W* Tractors Trailers
Taxi
* Assumed
3.6.5 Projected Traffic Growth Rates
Based on the elasticity values calculated for various scenarios as mentioned in clause 5.7
above, the growth rate calculated are mentioned in Table 3.27(a) to Table 3.27 (d).
Table 3.27(a) Traffic Growth (%) rate Calculated as per Elasticity values Suggested by
World Bank
Sl. Car/ 2 3
Year Bus Truck Tractors Trailers
No. Jeep/Taxi Wheeler Wheeler
Table 3.27(b) Traffic Growth rates (%) calculated by reducing Elasticity values by 10%
in slab of five years
Sl. Car/ 2 3
Year Bus Truck Tractors Trailers
No. Jeep/Taxi Wheeler Wheeler
Table 3.27(c) Traffic Growth rates (%) calculated as per Elasticity values suggested by
IRC SP: 19
Sl. Car/ 2 3
Year Bus Truck Tractors Trailers
No. Jeep/Taxi Wheeler Wheeler
Sl. Car/ 2 3
Year Bus Truck Tractors Trailers
No. Jeep/Taxi Wheeler Wheeler
Table 3.27(d) Traffic Growth rates (%) calculated as per Elasticity values suggested by
Vision 2021
Sl. Car/ 2 3
Year Bus Truck Tractors Trailers
No. Jeep/Taxi Wheeler Wheeler
From the growth rates calculated, it is observed the growth rates are not appropriate. Based on
consultants experience and observing growth trend on other National Highway projects the
following most likely growth rates are adopted as given in Table 3.28. Growth rates for
pessimistic and Optimistic scenarios are given in Table 3.29 (a) & Table 3.29 (b).
Table 3.28: Traffic Growth (%) rates adopted for NH 106 for Most Likely Scenario
Sl. Car/
2 3
No. Year Jeep/ Bus Truck Tractors Trailers Others
Wheeler Wheeler
Taxi
Table 3.29(a) Traffic Growth (%) rates adopted for NH 106 for Optimistic Scenario
Car/
Sl. 2 3
Year Jeep/ Bus Truck Tractors Trailers Others
No. Wheeler Wheeler
Taxi
Table 3.29(b) Traffic Growth (%) rates adopted for NH 106 for Pessimistic Scenario
Car/
Sl. 2 3
Year Jeep/ Bus Truck Tractors Trailers Others
No. Wheeler Wheeler
Taxi
Table 3.30: Traffic Projection in Cardinal Years & Total Projected Traffic along the Project road (AADT)
km 106.0
Year AADT PCU
Total Fast Moving Total Slow Moving Tollable Traffic Total Total Fast Moving Total Slow Moving Tollable Traffic Total
Most Likely Scenario
2010 2200 1078 639 3278 2467 743 986 3210
2014 3121 1309 875 4430 3334 810 1318 4145
2019 4464 1671 1199 6135 4552 1034 1769 5586
2024 5938 2132 1552 8070 5946 1320 2279 7265
2029 7579 2722 1980 10300 7588 1684 2908 9273
2034 9673 3473 2527 13146 9685 2150 3712 11834
2039 12345 4433 3226 16778 12360 2744 4737 15104
Optimistic Scenario
2010 2200 1078 639 3278 2467 743 986 3210
2014 3738 1309 1054 5047 4009 810 1599 4819
2019 6691 1671 1816 8362 6803 1034 2695 7837
2024 10981 2132 2863 13114 10603 1320 4158 11923
2029 16515 2722 4128 19236 15220 1684 5874 16904
2034 22837 3473 5498 26311 20459 2150 7727 22609
2039 29645 4433 7017 34078 26374 2744 9862 29118
Pessimistic Scenario
2010 2200 1078 639 3278 2467 743 986 3210
2014 2673 1309 776 3982 2995 810 1197 3805
2019 3412 1671 991 5083 3822 1034 1528 4856
2024 4355 2132 1265 6487 4878 1320 1950 6198
2029 5558 2722 1614 8279 6226 1684 2489 7910
2034 7114 3473 2060 10588 7957 2150 3177 10107
2039 9215 4433 2629 13648 10227 2744 4054 12971
Missing Link
(Due to kosi River)
as "Silk City", the thermal power plant at NTPC Kahalgaon in Kahalgaon falls under
Bhagalpur district. The industrialization in Bhagalpur district will influence the traffic
movement on the project road of trucks and MAV for transportation of silk handlooms and
other raw materials.
The total traffic traversing the road section at km 106.000 is projected to be 4521 PCU @ 5%
growth rate in the year 2017. The construction is expected to start in 2018 and considering
the construction period of 3 years, the traffic will thus open in the year 2021. Considering all
the factors in the adjacent areas of the project road, the traffic is expected to increase by 50%
than the originally projected traffic after the construction of Kosi Bridge and upgradation of
project road, i.e. in the year 2020. The projected traffic for a period of 30 years @ 5% growth
rate is shown below.
Table 3.31: Projected Induced Traffic on Kosi Bridge
Road Section from
S. No. Year (km 106 to km 136)
PCU/day
1 2010 3210
2 2016 4303
3 2017 4521
4 2018 4746
5 2019 4981
6 2020 5230
Increase in traffic by 50%
8 2021 7845
9 2022 8237
10 2023 8649
11 2024 9082
12 2025 9536
13 2026 10013
14 2027 10513
15 2028 11039
16 2029 11591
17 2030 12170
18 2031 12779
19 2032 13418
3.8 CONCLUSION
Before the development of Kosi bridge (Missing Link not developed) the traffic in the
year 2010 at km 65.000 is 7523 PCU and at km 106.000 it is 3210 PCU which shows
a reduction of 50% of total traffic on the project road after km 65.000.
After the development of Kosi Bridge the users will use the project road because it is
shorter in length amongst all other alternatives and the traffic is expected to increase
by 50% than the originally projected traffic after the construction of Kosi Bridge and
upgradation of project road, i.e. in the year 2020.
The above table shows the capacity for 4 lane of 10,000 PCU as per ministry vide
circular No. RW/NH-33044/28/2015/S&R (R) exceed in the year 2026 for project
road section of NH-106 from km 106.000 to 136.000. Moreover, the construction of
10 km Kosi Bridge may take more than 3 years for completion.
By the time the bridge is under operation, the traffic at that section reaches close to its
2 lane capacity and as it is a major structure involving huge investment, time &
complex construction conditions, it is proposed to be 4 lane instead of 2 lane as it
cannot be upgraded frequently.
CHAPTER 4
ENGINEERING SURVEYS AND INVESTIGATIONS
4.1. GENERAL
Primary consideration for feasibility study of a road is an overall cost of transportation (i.e.
the cost of initial construction, traffic operation and maintenance) it is low without adversely
affecting the environment and social impact. All operations need advance planning of
methodology in a logical sequence.
General Scope of Survey & Investigation covered is:
a) Traffic surveys like Classified Traffic Volume Count, Origin-Destination &
Commodity Movement Surveys, Turning Movement Surveys at important junctions,
Axle Load Survey and Speed-Delay Survey, Pedestrian and Animal count survey and
willingness to pay survey.
b) Detailed Reconnaissance survey
c) Inventory and Condition Surveys for bridges, cross drainage structures and drainage
provisions
d) Detailed Topographic Surveys using Total Station
e) Identification of possible improvements in the existing alignment and bypassing
congested locations with alternatives, evaluation of different alternatives, comparison
of techno-economic and other considerations and recommendations regarding most
appropriate option
f) Pavement Investigations
g) Sub-grade characteristics and strength-Investigation of required sub-grade and sub-
soil characteristics and strength for road and embankment design and Sub-soil
Investigations
h) Investigation for bridges including hydrological and geotechnical Investigations
i) Identification of sources of construction material
4.2. INVENTORY AND CONDITION SURVEY OF ROAD AND PAVEMENT
4.2.1 Road Inventory
Detailed road inventory surveys were carried out to collect details of all existing road &
pavement features along the existing road sections. The data collected through road inventory
surveys was found sufficient to meet the requirements.
The data is presented in the format given as “Road Inventory Data Sheet” (IRC-SP: 19-2001).
Under the following headings:
area accounts to 85 km and rest of the corridor is occupied by shops, bus stops and petrol
bunks which adds up to commercial area of 10 km.
4.2.1.5 Drains
Road Side Drains
There are no road side drains as such. However natural drains of 20m to 40mm wide run
parallel to the existing road. The details of natural drains running parallel to road are as
follows:
Embankment Condition
Chainage Pavement Condition Shoulder
(Good/Fair/Poor)
Overall
(NE/PF/F)****
Condition of
Unpaved G/F/P
Potholing (%)
Cracking (%)
Raveling (%)
Patching (%)
Paved G/F/P
FROM (km)
(mm)
Pavement
TO (km)
(Excellent/
Good/Fair/
Poor)
106.0 110.0 0 to 40 0 to 25 0 to 20 Nil Nil 0 to 100 Fair to Poor NE Nil Fair to Poor Fair
110.0 115.0 0 to 40 0 to 20 0 to 20 Nil Nil 0 to 100 Fair to Poor NE Nil Fair to Poor Fair
Good to Very
115.0 120.0 0 to 2 0 to 5 0 to 2 Nil Nil Nil Good to Poor PF/ POND Nil Good to Poor
Poor
Canal / Fair to Very
120.0 124.0 0 to 10 0 to 10 0 to 10 Nil 0 to 2 Nil Poor Nil Poor
Nala Poor
Poor to Very
133.4 136.0 0 to 5 0 to 10 5 Nil 0 to 2 0 to 80 Poor NE/PF Nil Fair to Poor
Poor
LHS RHS
From Existing (km)
Calculation of IRI
Considered BI for
To Existing (km)
Corre-cted BI (mm/
Obser-ved BI (mm/
Road Road
Corre-
Surface Obser- Surface
cted IRI
Condition ved BI Condition
km)
km)
BI
(mm/ (IRC:
(IRC: (mm/
SP:16- km) SP:16-
km) 2004)
2004)
After this temperature & seasonal corrections were applied to get final
Step 3 (corrected) deflection from which, mean, standard deviation and characteristic
deflection are obtained.
Characteristic Deflection
The statistical analysis of all the measurements done in the field and corrections applied as
required was done as under:
Mean deflection= X=ΣX
n
Characteristic deflection Dc in mm= X + 2σ for major arterial roads (like NH and SH)
Dc = X + σ could be considered for all other roads but for this project it is not
applicable.
Here, X = Individual deflection in mm
X= Mean deflection in mm
n= Number of deflection measurements
In the formula for standard deviation, division is done by n-1 and not n which follows the
established statistical theorems.
Every km of the road, readings were staggered with respect to 50 m on either side, Left Hand
(LHS) and Right Hand (RHS). The observations of LHS were taken while going and RHS
while returning, involving a difference of several days. Hence, calculated characteristic
deflection for LHS is bound to be different for RHS on the same km. The representative
characteristic deflection for the same km is the maximum of the two and not the average for
the obvious reasons. The average characteristic deflection values as per the data indicate
structural capacity of the pavement is low and the average value varies between 1.2 mm to
1.8 mm. The adversely affected stretch is km 4 to km 19, having values higher than average
while the optimum values being 0.55 mm and 2.84 mm respectively. The summary of
Characteristic deflection data is given in Table 4.5.
Table 4.5: Summary of Characteristic Deflection Data
Existing Existing
Characteristic Characteristic
Chainage (km) Chainage (km)
Deflection (mm) Deflection (mm)
From To From To
106 107 1.51 118 119 2.61
107 108 1.49 119 120 1.51
108 109 1.4 120 121 1.77
109 110 1.43 121 122 2.11
110 111 1.35 122 123 1.53
111 112 2.11
112 113 3.01
113 114 1.44
114 115 2.17
115 116 1.34
116 117 1.5
117 118 1.55
Water Old
Bituminous Total
LHS / Bound GSB/ Pavement
Chainage layer Thickness
RHS Macadam Brick (mm) (BT+WBM+
(mm) (mm)
(mm) GSB)
113+010 LHS 100 60 150 - 310
113+500 LHS 125 80 150 - 355
114+000 RHS 100 70 145 - 315
114+500 RHS 115 160 80 - 355
115+010 LHS 125 200 120 - 445
115+500 LHS 130 190 130 - 450
116+080 RHS 125 185 105 - 415
116+500 RHS 125 150 85 - 360
117+005 LHS 125 125 80 - 330
117+500 LHS 125 130 80 - 335
118+000 RHS 105 95 90 - 290
118+500 RHS 115 130 80 - 325
119+000 LHS 125 65 140 - 330
119+500 LHS 110 160 80 - 350
120+000 RHS 100 80 170 - 350
120+500 RHS 100 150 80 - 330
121+000 LHS 100 80 160 - 340
121+350 LHS 100 160 80 - 340
121+750 RHS 100 160 70 - 330
122+200 RHS 80 140 - 220 440
122+700 LHS 60 100 - 265 425
123+250 LHS 75 150 - 220 445
123+800 RHS 50 160 - 200 410
123+800 to 133+800 No existing road (missing link)
134+000 RHS 40 95 100 - 235
134+500 LHS 50 95 80 - 225
135+000 LHS 40 80 70 - 190
135+400 RHS 65 110 75 - 250
135+800 RHS 60 100 70 - 230
The soaked CBR corresponding to 97% MDD varies from 5 to 12 in Package II (km 106 to 136).
4.4.5 Investigation for Natural Ground along Widening side & Realignment
The sub grade samples for natural ground have not been collected as there are no new
alignments and bypasses proposed which are outside the existing ROW.
metal, crushed stone or combinations thereof meeting the prescribed grading and physical
requirements. The sub-base material should have a minimum CBR of 20 % and 30 % for
traffic upto 2 msa and traffic exceeding 2 msa respectively. Sub-base usually consist of
granular or WBM and the thickness should not be less than 150 mm for design traffic less
than 10 msa and 200 mm for design traffic of 10 msa and above.
4.5.4 Stone Aggregates for Pavement Courses and Cement
The survey was carried out to locate potential sources of sound stone aggregates required for
the construction of:
Wet Mix Macadam
Deus Bituminous Macadam
Bituminous Concrete
Cement Concrete
Consequent upon the detailed survey of the project influence area, discussions with the PWD
officers & Construction Agencies working in the vicinity of project road, it was revealed that
the stone quarries located at Itari, Fathepur and Madhepura are the only potential & nearest
source for the required stone aggregates & that in this area stone aggregates metal from these
quarries were being used.
Control on particle shape to get the product within flakiness and elongation limits will have
to be ensured during production with appropriate selection of crushing plant. The laboratory
tests for these properties have hardly any significance at this stage.
Therefore, in summary if the physical/ mechanical properties of a stone aggregate source
comply the requirements shown above, then the source should be deemed to comply with
requirements for concrete and any of the pavement courses i.e., GSB, WMM, DBM and BC
envisaged in the project. Sufficient quantities of materials are available at quarries to serve
the requirements of this project and those to follow in near future.
4.5.5 Sand for use in Pavement Course and Cement Concrete
The constituent parts of a fine-grained soil are silt and clay fractions. Silts are finer than
sands in texture and lighter in colour. Silts and clay particles are microscopic in size; physical
properties other than grain size must be used as criteria for field identification. The
classification tests used in the field for preliminary identification are:
Dry strength test
Shaking test
Plasticity test
Dispersion test
Stain test
Dry strength test: The strength of a soil in a dry state is an indication of its cohesion and
hence of its nature. It can be estimated by crushing a 3-mm size of dried fragment between
thumb and forefinger. A clay fragment can be broken with great effort whereas silt fragment
crushes easily.
Shaking test: Shaking test is also called dilatancy test. It helps to distinguish silt from clay
since silt is more permeable than clay. In this test a part of soil mixed with water to a very
soft consistency is placed in the palm of the hand. The surface of the soil is smoothened out
with a knife and the soil pat is shaken by tapping the back of the hand. If the soil is silt, the
water will rise quickly to the surface and will give it a shiny glistening appearance. If the pat
is the deformed either by squeezing or by stretching, the water will flow back into the soil
and leave the surface with a dull appearance. Since clayey soils contain much smaller voids
than silts, the appearance of the surface of pat does not change during the shaking test. An
estimate of the relative proportion of silt and clay in an unknown soil mixture can be made b
y nothing whether the reaction is rapid, slow or nonexistent.
Plasticity test: If a sample of moist soil can be manipulated between the palms of the hands
and fingers and rolled into a long thread of about 3 mm diameter, the soil then contains a
significant amount of clay, where as silts cannot be rolled into thread of 3mm diameter
without severe cracking.
Dispersion test: This test is useful for making a rough estimate of sand, silt and clay present
in a material. The procedure consists in depressing a small quantity of soil water taken in a
glass cylinder and allowing the particles to settle. The coarse particles settle within about 30
seconds if the depth of water is about 10 cm. Silt particles settle in about 30 seconds to 240
minutes, where as clay particles remain in suspension for at least several hours and
sometimes several days. Colloidal particles finer than 0.0002 mm generally will not settle
because of Brownian movement.
Stain test: A paste of clayey with water when rubbed in between fingers leaves stain, which
is not observed in case of silts.
On the basis of information gathered through conducts with local people and applying visual
and field identification guides, it could safely be concluded that sufficient quantity of soil
from borrow areas will be available on either side of the project road within reasonable on
either side of the project road within reasonable distance (lead).
Suitable sources of soil required for the construction of embankment and sub-grade was
identified at 2 locations at Madhepura.
The soil sample about 40 kg in weight was collected from each pit in a gunny bag, and after
allotting identification marks was sent to the field laboratory for detailed testing. The Particle
size distribution, Atterberg limits, Modified AASHTO Compaction test, Cohesion, angle of
internal friction (unconsolidated, un- drained triaxial shear test) and laboratory CBR after 4
days soaking as per normal practice at 55 blows of Modified Proctor Rammer are done on
aggregates. In normal practice of testing the CBR values of the soil samples are more than
7% and also the soils are non expansive as evident from swell values. Hence the soils are
quite suitable for embankment.
Recommendation
Water quality was found satisfactory for concreting, R.C.C & prestressed concrete work
confirming to IS 456.
During actual execution of work chemical tests for each source of ground water shall
be carried out and approval shall be in according with IS 456 – 2000
4.5.7 Fly ash
Nearly 73% of India‟s total installed power generation capacity is thermal, of which coal-
based generation is about 90%. Power generation in India consumes about 70% of country‟s
coal production. Bulk utilization of fly ash is possible in the field of civil engineering
especially in the construction of road embankments. Natural borrow areas are either scarce or
expensive and the environmental degradation caused due to use of top soil for embankment
construction is very high. Fly ash is proved to be environmentally preferable alternative to
natural borrow soil. Fly ash possesses various desirable characteristics like lightweight, ease
of compaction, faster rate of consolidation etc. Also spreading and compaction of fly ash can
be started much earlier in comparison to soil after a rainfall. Fly ash would be a preferred
material for construction of embankments over weak soil.
4.5.8 Manufactured Materials
Cement
Cement to be used in the works shall be any of the following types with the prior approval of
the Engineer:
a) Ordinary Portland cement, 33 Grade, conforming to IS 269.
b) Rapid Hardening Portland cement, conforming to IS 8041.
c) Ordinary Portland cement, 43 Grade, conforming to IS 8112.
d) Ordinary Portland cement, 53 Grade, conforming to IS 12269.
e) Sulphate Resistant Portland cement, conforming to IS 12330.
Cement conforming to IS 269 shall be used only after ensuring that the minimum required
design strength can be achieved without exceeding the maximum permissible cement content
of 540 kg/cum of concrete.
Cement conforming to IS 8112 and IS 12269 may be used provided the minimum cement
content from durability considerations is not reduced.
Cement conforming to IS 12330 shall be used when sodium sulphate and magnesium
sulphate are present in large concentration to be aggressive to concrete.
Cement conforming to IS: 8041 shall be used only for precast concrete products after specific
approval of the Engineer.
Total chloride content in cement shall not exceed 0.05 percent by mass of cement. Also total
sulphur content calculated as sulphuric anhydride shall in no case exceed 2.5 percent and 3.0
percent when tri-calcium aluminate percent by mass is upto 5 or greater than 5 respectively.
Bitumen
Bitumen is a thermoplastic material and its stiffness is dependent on temperature. The
temperature vs. stiffness relationship of bitumen is dependent on source of crude oil and
method of refining.
As per revised code IS: 73-2006, bitumen is classified based on Viscosity (viscosity at 60˚C
& 135˚C) and as specified there are four grades namely VG-10, VG-20, and VG-30 & VG-
40. According to viscosity grading, higher the grade stiffer is the bitumen. The penetration at
25˚C, which is the annual average pavement temperature, is retained.
VG-10 BITUMEN: VG-10 is widely used in spraying applications such as surface-dressing
and paving in very cold climate in lieu of old 80/100 Penetration grade. It is also used to
manufacture Bitumen Emulsion and Modified Bitumen products.
VG-20 BITUMEN: VG-20 is used for paving in cold climates and high altitude regions.
VG-30 BITUMEN: VG-30 is primarily used to construct extra heavy duty Bitumen
pavements that need to endure substantial traffic loads. It can be used in lieu of 60/70
Penetration grade.
VG-40 BITUMEN: VG-40 is used in highly stressed areas such as intersections, near toll
booths and truck parking lots in lieu of old 30/40 Penetration grade. Due to its higher
viscosity, stiffer Bitumen mixes can be produced to improve resistance to shoving and other
problems associated with higher temperature and heavy traffic loads.
Bricks
Burnt clay bricks shall confirm to the requirements of IS: 1077 except that the minimum
compressive strength when tested flat shall not be less than 8.4 MPa for individual bricks and
10.5 MPa for average of 5specimen. They shall be free from cracks and flaws and nodules of
free lime. The brick shall have smooth rectangular falls with sharp corners and emit a clear
ringing sound when struck. The site may be according to local practice with a tolerance of ±5
percent.
4.6. BRIDGE STRUCTURES
4.7.1 Introduction
A project team (comprised of a Bridge Engineer, a Hydrologist, a Geotechnical Engineer &
supporting staff) carried out the bridge inventory surveys and visual condition survey of
existing bridges as per guidelines stipulated in applicable codal provisions (IRC-SP: 19, 35 &
40). The project team inspected the existing Bridges & other cross Drainage Structures lying
on the project road and recorded the data using Performa prepared for carrying out the
detailed condition survey. The deficiencies in the existing structures were noted to ascertain
the measures required for strengthening of the structure.
All the details stipulated in IRC codes for efficient detailed inventory & condition survey of
structures has been tabulated in a convenient format enabling easy analysis. The cross
drainage structures were identified based on the material of construction, carriageway width,
total length, and type of structure.
As per detailed Inventory & condition Survey of the Stretch, there are 06 Minor Bridges, 1
Vented Causeway & 9 Slab and 1 Box Culverts lying along the Project Stretch.
4.7.2 Inventory of Existing Bridges
Out of 6 existing bridges, no major bridge falls within the project stretch. The project road
has a missing link across Kosi River between km 124.0 to km 132.0 which requires
construction of bridge/bridges to connect NH 106 and NH 31.
There are 06 minor bridges, 1 submersible causeway on existing Project Road. These bridges
consist of simply supported RCC solid slab with PCC Abutment and Wall type Pier as
substructure elements. Most of the bridges are narrower with carriageway width less than
8.4m.
Note: All Bridges are reconstructed due to Geometrical constraints of Road Embankment as
per IRC SP: 73 (2015) clause 4.2.1 (ii)
The inventory and general conditions of existing bridges are presented in Clause 4.7.3.
4.7.3 Condition Survey of Bridges
Major Bridges
Table 4.10: Inventory and Condition of Major Bridges
C way Total
Sl Chainage Existing Condition of the
Crossing Width Length
No. (km) Spans Existing Bridge
(m) (m)
NIL
Minor Bridges
There are 06 existing Minor Bridges lying on the project stretch. The types of superstructures
for the Minor Bridges were found to be RCC Solid Slab resting on PCC Sub-Structure.
Details of existing structures are shown in Figure 4.1.
The following table shows the Condition survey of Minor bridges along the project stretch.
Table 4.11: Report on Condition Survey for Minor Bridges
C way Total
Sl Chainage Existing Condition of the
Crossing Width Length
No. (km) Spans Existing Bridge
(m) (m)
Structure is in sound
condition with smaller
1 112+757 Stream 7.6 2 x 5.5 11.0 span configuration of
2x5.5 m with brick
masonry substructure.
Structure is in sound
condition with smaller
2 112+816 Stream 6.6 2 x 3.4 6.8 span configuration of
2x3.4 m with brick
masonry substructure.
Structure is in sound
condition with smaller
2 x 3.5
3 121+246 Stream 7.2 7.0 span configuration of
m
2x3.5 m with brick
masonry substructure.
Structure is in sound
condition with smaller
2 x 3.5
4 122+634 Stream 7.2 7.0 span configuration of
m
2x3.5 m with brick
masonry substructure.
Structure is in sound
condition with smaller
2 x 3.5
5 123+056 Stream 7.3 7.0 span configuration of
m
2x3.5 m with brick
masonry substructure.
Structure is in sound
condition with smaller
2 x 3.5
6 135+587 Stream 9.2 7.0 span configuration of
m
2x3.5 m with brick
masonry substructure
Causeways
A vented causeway having 10 nos of Pipe of 1000mm dia was observed to be situated at Km
117+700 on the project road. This causeway was found to exist in low lying & submersible
Location Carriageway
S. No. No. Vents x Size (m) Condition
(km) width (m)
1 107 + 000 6.5 1 x 1.0 Fair
2 107 + 200 6.5 1 x 1.0 Fair
3 108 + 000 6.5 1 x 1.2 Poor
4 109 + 600 6.5 1 x 1.3 Fair
5 110 + 800 6.6 1 x 2.5 Fair
6 112 + 300 6.5 1 x 1.2 Fair
7 113 + 100 6.5 1x 3.1 Fair
8 114 + 200 6.5 1 x 3.0 Poor
9 115 + 500 6.6 1 x 1.3 Fair
Carriageway
S. No. Location (km) No. Vents x Size (m) Condition
width (m)
CHAPTER 5
ENGINEERING DESIGNS
5.1 GENERAL
The Project Highway National Highway No.106 starts at Udakishanganj (km 106) and
terminates at Bihpur (km 136.0 at junction of NH 31 at km 321). The entire Project Highway
passes through plain terrain. The existing project highway is made of single lane width.
About a length of 10 km is missing link which is due to washout of existing road and bridges
in the past during floods in Kosi River.
The Project highway lacks safety due to inadequate Road Signs and other road
appurtenances.
The safe, efficient and economic operation of highway is governed to a large extent by the
care with which, the improvement proposals and design has been worked out. These
improvements will consists widening, realignment and strengthening of pavement with all
ancillaries such as the improvements of geometries; widening and reconstruction of culverts
and bridges; providing drainage; junction improvements; providing road marking signs and
other safety devices, road over bridges etc to enable all road users (motor vehicles, animal
drawn vehicles, cyclists, pedestrians and animals) to use the facility without degrading the
environment.
Latest editions published by IRC/IS codes of practices & standards specifications and
guidelines of Ministry of Surface Transport are followed for design. Additional technical
references are used wherever the provisions of IRC/IS codes are found inadequate.
5.2 DESIGN STANDARDS AND METHODOLOGY
The design standards for widening and upgradation has been done as per the Manual of
Standards and Specifications for 2-laning of State Highways IRC SP 73: 2015 published by
Indian Roads Congress. The other relevant IRC codes have also been considered as required.
Additional technical references are used wherever the provisions of IRC/IS codes are found
inadequate. As far as possible eccentric widening is proposed in rural areas to take care of
traffic diversion during construction and also to minimize utility relocation and cutting of
trees. Concentric widening is proposed in urban areas to have minimum utility relocation and
R&R issues.
The existing carriageway is proposed to be improved to 2-lane with paved shoulders in urban
areas and 2-lane with earthen shoulders in rural areas. The horizontal curves which are
deficient either in radius or in transition lengths and curve length have been improved to the
extent possible with existing ROW to avoid land acquisition. The vertical curves which are
deficient in curve length and gradients have also been improved.
The various standards followed in design for various elements is given in Table 5.1 and
Table 5.2 of this chapter.
For items not covered in the above specifications, provisions in IS codes, Sound Engineering
practice, Technical Literatures/Papers & provision of relevant codes of other countries have
been considered. In addition to the above standards the MORTH suggestions are also
followed.
5.2.2 Geometric Design Standards
The improvement of geometrics is necessary on National Highways for safety and comfort of
road users, even for low traffic volumes. The Geometric Design standards adopted have been
listed in Table 5.2.
Table 5.2: Proposed Geometric Design Standards
Description Criteria Remarks
Design Service Volume 18000 PCU (Two-Lane with The Project road is Proposed
in Plain Terrain 1.5 m Paved Shoulders) two lane with paved shoulder
Ruling 100
Design Speed (km/h)
Minimum 80
Bituminous - 2.5%
Camber
Earthen - 3.0 %
Existing
Sl. From To Length Widening Proposed
Carriageway
No (km) (km) (km) Scheme Cross Section
Width (m)
1 106.000 114.000 3 to 5 8 LHS 2-lane with PS
2 114.000 116.000 3 to 5 2 RHS 2-lane with PS
3 116.000 124.000 3 to 5 8 LHS 2-lane with PS
4 124.000 133.500 Missing Link 2-lane with PS
5 133.500 136.000 3 to 5 2.5 LHS 2-lane with PS
S. No. Existing km
ROW (m)
From (km) To (km)
1 106.000 107.000 24.0
2 107.000 108.000 24.0
3 108.000 109.000 24.0
4 109.000 113.000 24.0
5 113.000 114.000 24.0
6 114.000 115.000 24.0
7 115.000 115.950 24.0
8 115.950 116.000 24.0
9 116.000 117.000 24.0
10 117.000 119.000 24.0
11 119.000 120.000 24.0
12 120.000 120.370 24.0
13 120.370 121.410 24.0
14 121.410 122.000 24.0
15 122.000 124.200 24.0
16 124.200 133.400 00.0 (Missing Link)
17 133.400 136.000 24.0
Design Chainage
S. No. Length (Km) Row
From To
1 106+000 123+300 17,300 24.0
2 123+300 125+110 1,810 60.0
3 125+110 132+040 6,930 30.0
4 132+040 132+900 860 60.0
5 132+900 133+280 380 24.0
6 133+280 133+620 340 150.0
7 133+620 134+918 1,298 24.0
Existing Chainage
S. No. Design Chaniage Side Type of Junction
(km)
1 107.624 106+800 BHS +
2 109.550 108+900 BHS +
3 112.190 111+113 RHS T
4 112.560 111+481 RHS Y
5 112.634 111+553 LHS T
6 113.154 112+250 RHS T
7 113.323 112+414 LHS T
8 113.662 112+752 RHS T
9 115.269 114+422 LHS T
10 115.650 114+800 LHS T
11 115.750 114+900 RHS Y
12 117.656 116+728 LHS T
13 118.800 117+890 LHS T
14 118.810 117+900 RHS Y
15 119.035 118+100 LHS T
16 119.570 118+532 LHS T
17 119.870 118+939 LHS T
18 120.650 119+700 RHS T
19 121.235 120+280 LHS T
20 124.095 123+131 BHS +
TCS Drawings
One toll plaza proposed is proposed at Ch. 133+450 with (2+1) lane configuration on both
sides. It shall be designed as per the guidelines of the manual.
The widening and new construction of structures is based on the requirement laid down in
IRC: SP: 73: 2015. All new bridges have been constructed to accommodate for 2-lane traffic.
Width of immediate approaches has been adjusted to provide smooth transition from
approaches to bridge.
Major Bridge of 6.93 km length having 120 span of 2x12.5m carriageway, 6 span of 2x15.2m
carriageway Total 126 no span of 55m with Pile and well foundation. Pile foundation has
been proposed in central 2km portion. Bridge Health Monitoring System (BHMS) has been
proposed in the major bridge to monitor the bridge from safety and durability aspect during
its construction and complete life span
Reinforced concrete pipe for new culverts are of NP 4 type, conforming to the requirements
of IS: 458 with minimum diameter 1200 mm (Internal diameter). The Pipe / Slab / Box
culverts have been provided the same overall width as of the approach road. Overall width of
these structures is such that the outer face of railing/parapet will be in line with the outer edge
of the shoulder. All Bridges are reconstructed due to Geometrical constraints of Road
Embankment as per IRC SP: 73 (2015) clause 4.2.1 (ii)
The details of proposals for existing and additional culverts are given below.
Table 5.11: Proposals for Existing and Additional Culverts
Details of Existing Pipe Culverts
1 - 108.640 1 x 2.0
2 - 109.340 1 x 2.0
3 - 111.640 1 x 2.0
4 - 112.660 1 x 2.0
5 - 113.260 1 x 2.0
6 - 116.200 1 x 2.0
7 - 117.780 1 x 2.0
8 - 118.940 1 x 2.0
S. No. Existing Chainage (m) Design Chainage Proposed No. Vents x Size (m)
9 - 120.940 1 x 2.0
10 - 121.140 1 x 2.0
11 - 123.080 1 x 2.0
12 - 133.260 1 x 2.0
13 - 133.800 1 x 2.0
14 - 134.180 1 x 2.0
Details of Proposed Additional Box Culverts (1 x 3.0m)
SI. No Existing Chainage (m) Design Chainage Proposed Span/Opening (m)
1 - 110.360 1 x 3.0
2 - 110.580 1 x 3.0
3 - 117.460 1 x 3.0
4 - 118.280 1 x 3.0
5 - 119.700 1 x 3.0
6 - 123.307 1 x 3.0
7 - 123.337 1 x 3.0
8 - 123.367 1 x 3.0
9 - 123.400 1 x 3.0
10 - 123.430 1 x 3.0
11 - 123.500 1 x 3.0
12 - 123.530 1 x 3.0
13 - 123.575 1 x 3.0
14 - 132.840 1 x 3.0
15 - 133.010 1 x 3.0
16 - 133.470 1 x 3.0
17 - 134.600 1 x 3.0
18 - 134.870 1 x 3.0
Superimposed Load
Superimposed Dead load consists of load due to Wearing coat (surfacing coat), crash barrier
and foot path with hand rails. Unit weight for superimposed dead load is in conformity with
IRC: 6-2014. Loads corresponding to the dimensions given for bridge furniture details in
IRC: 5 are also considered as SIDL for design of structure.
Live Loads
Live Load Combinations specified as per IRC: 6-2014 are considered for New Structures.
Single Lane of Class 70R/ 2 Lane of Class A with Footpath/ 3 Lanes of Class A/ Single Lane
of Class 70R + Class A loading (whichever producing severe effect) are considered in design
with an appropriate Impact Factor. Reduction in longitudinal effect for three lane loading is
also considered as per Clause 211 of IRC: 6-2014
Also, as per Amendment released for IRC: 6-2014 in January 2014, IRC class Special
Vehicle (SV) loading (used for stator units, turbines, heavy equipment & machinery) shall
also be considered for analysis.
Differential settlements:
If the riding quality permits, clause 706.3.2 of IRC: 78 -2014 specify that the calculated
differential settlement between the foundations of simply supported span shall not exceed L /
400 of the distance between the foundations, where L is distance between two foundations. In
case of structure sensitive to differential settlement such as continuous structures the value of
differential settlement is taken as 10 mm.
Temperature Gradient
Temperature forces for calculation of bearing movement and for the design of expansion joint
are considered as per clause 215 of IRC: 6-2014. The design will be based on the range of
effective bridge temperature at the site location of the structure. The temperature gradient for
stress calculation of all structure members is considered as per the clause 215.3 of IRC 6-
2014. In context, following parameters shall be used in line with the mentioned clause:
Coefficient of thermal expansion: 12 x10-6/C.
Highest Maximum Temperature = 45.0C
Lowest Minimum Temperature = - 7.50 C.
Total Variation in temperature = +45.0 – (-7.5) = 52.5° C
Mean Variation in of temperature = 52.5/2 = 26.25° C
Thus, as per clause 215 of IRC: 6-2014, the structures (when effectively restrained) are
designed for a temperature range considering Mean of minimum or maximum air shade
temperature ± 10° C, whichever is critical
An effect of distribution of temperature across the deck depth is considered in design of
superstructure. The temperature has influence on the movement of expansion joints as well as
on bearings. The temperature variation and effect of rise and fall takes place over a season
and hence the long-term value of Modulus of Elasticity is considered in the analysis.
Other Loads
The loads which are not mentioned in above Clause (like Vehicle collision loads etc) are as
per IRC: 6-2014.
Bearings
All bearings are detailed and designed in such a way that they are easily accessible for
inspection, maintenance and replacement. Design and specifications of bearings are as per
IRC: 83 (Part I, II & III).
For slab type superstructures no bearings have been provided, rather Tar paper bearings are
proposed. For bridges with RCC girder type superstructure POT/ PTFE bearings have been
proposed. Design loads and movements coming on to the bearings are provided to the
manufacturer to enable him to design and supply.
Expansion joints
For solid slab super structures up to 11.0 m span, the “Filler Type Expansion Joints” (20 mm
thick joint filler) have been proposed. „Single Strip Seal Expansion Joints‟ have been
provided for other type of superstructures with movement up to 80 mm. Rubberized
components of all the expansion joints older than 15 years of existing structures shall be
replaced.
5.3.2.2 Structural Analysis/ Design Methodology
Structural Analysis shall be clearly identified and explained for evolving a comprehensive
design methodology, which covers all aspects of design for various parts of the
bridges/structures (viz. superstructure, substructure, foundations & bearings).
Method of Analysis/ Design for Super Structure
Cast-in-situ/ Pre-cast RCC Box type of Structure
Analysis of Non-Skew RCC Box type structures considering a slice of unit width (for
loads & forces) & modeling the geometry of structure in STAAD Pro. Subsequently,
design of section for critical values of loads & combination (applied on the structure)
from the output of the analysis. Reinforcement Calculations & Check for Stresses
(ULS & SLS case for various combinations) based on acquired results & standard
codes of practice.
Stresses also checked for SLS condition under rare load combination & crack width
check for quasi permanent load combination.
Precast & Cast-in-situ RCC Girder type of Superstructure
The Structure having RCC Girder type of Structure (Precast or cast-in-situ) behaves as
composite section for all loads since the staging is released after the Slab gains strength. Such
Superstructure is analyzed for dead loads, SIDL, Live Loads & other loads using a two
dimensional grillage analogy method.
Skew effect is directly accounted in the grillage model to simulate the actual behavior.
The analysis of the RCC Girder for longitudinal flexure is carried out as below:
Calculation of effective Flange Width for determination of sectional properties for the
longitudinal girders (in accordance with IRC: 112).
The Longitudinal members of the superstructure (other than skew & curved
superstructure) is assigned as torsion less members that are able to resist the loads
applied in a plane perpendicular to the plane of assemblage, through bending shear of
the members.
Generation of Grillage Model with longitudinal members along the C/L of the Girder
and along the outer edges, along with the Suitable transverse members along the cross
beams.
Separate Calculations of Moments & Shear Forces for Inner & Outer Girders by
keeping the load train at a distance of minimum eccentricity from Crash Barrier.
Reinforcement Calculations & Check for Stresses (ULS & SLS case for various
combinations) based on acquired results & standard codes of practice.
Stresses checked for SLS condition under rare load combination & crack width check
for quasi permanent load combination.
Secondary effects due to shrinkage & creep of concrete for composite structures shall
be accounted as per IRC method.
The Design therefore, is done with only the girder section being effective upto the stage of
casting of deck slab. Diaphragm & Composite Section are considered for all subsequent loads
(i.e. for SIDL & Live Loads).
Such Superstructure is analyzed for dead loads, SIDL, Live Loads & other loads using a two
dimensional grillage analogy method. Self weight of Girder & Dead Weight Load of Slab is
applicable on girder section alone & hence, the design forces for Dead Loads are calculated
separately & results are superimposed.
The analysis of the PSC Girder for longitudinal flexure is carried out as below:
Calculation of effective Flange Width for determination of sectional properties for the
longitudinal girders (in accordance with IRC: 112).
The Longitudinal members of the superstructure (other than skew & curved
superstructure) are assigned as torsion less members that are able to resist the loads
applied in a plane perpendicular to the plane of assemblage, through bending shear of
the members.
Fixation of Cable length at various sections along the length based on which gross &
net section properties along with resultant centroid of strands is calculated at various
sections along the length of girder.
Generation of Grillage Model with longitudinal members along the C/L of the Girder
and along the outer edges, along with the Suitable transverse members along the cross
beams.
Separate Calculations of Moments & Shear Forces for Inner & Outer Girders by
keeping the load train at a distance of minimum eccentricity from Crash Barrier.
Reinforcement Calculations & Check for Stresses (ULS & SLS case for various
combination) based on acquired results & standard codes of practice.
Effect of Differential shrinkage & creep between pre-cast girder & cast-in-situ slab
shall also be considered.
Design of Cross Girder (i.e. calculation of Bending Moment & required reinforcement) for
critical load case is calculated considering both, Jacking condition as well as service
condition. Reinforcement Calculations & Check for Stresses (ULS & SLS case for various
combinations) are based on acquired results & standard codes of practice. For lifting of span
for replacement/maintenance of bearing in any future, it is needful to use jacks located as per
design consideration.
STAAD Pro is used to analyze the Deck Slab transversely as a continuous one-way slab
(supported on longitudinal girders) with cantilever overhang (on either side) by considering
unit width of deck slab along span. Global analysis of Deck slab is also done due to unequal
deflection in Girder. The analysis is carried out for various loads (i.e. DL, SIDL & LL).
Various design sections are identified & designed for the worst combinations of the loads
mentioned earlier. Stresses are then checked for SLS condition under rare load combination
& crack width is checked for quasi permanent load combination.
The Bending moment and Shear Forces due to Dead Load, Super Imposed Dead Load
and Live Loads worked out based on Simple Beam Theory, considering center to
center of bearing as span length.
To account for torsion, distortion and warping the Live Load bending moments and
shear forces increased by 10%.
In the transverse direction the box is analyzed as R.C.C. section. The box is idealised
as a plane frame considering unit width of box. The load intensities due to Live Load
are applied on the frame considering the width over which they are dispersed as per
I.R.C. codes.
The concrete stresses at extreme fibres under various stages of loading are checked at
all the design sections. Capacities of the sections are also checked for the ultimate
moment condition as per provisions of IRC:112.
For obtaining maximum shear stress, the section at a distance equal to effective depth
from the face of the support is checked for ultimate loads and the shear reinforcement
calculated at the section is continued up to the support.
For PSC Box Girders, section cracked or un-cracked in flexure has been decided
based on whether the maximum ultimate shear capacity of the sections governs by
cracked or un-cracked capacity. At locations where un-cracked capacity governs the
relief due to vertical component of pre-stress has been considered.
Design of RCC Voided Slab
The Structure having RCC Voided slab type of Structure is analyzed and designed for loads
and forces by modeling the structures in STAAD.pro. Dimensions to be provided conform to
IRC: SP-64-2005
The Bending moment and Shear Forces due to Dead Load, Super Imposed Dead Load
and Live Loads is worked out based on Simple Beam Theory, considering center to
center of bearing as span length.
Capacities of the sections is checked for the ultimate moment condition as per
provisions of IRC: 112.
The concrete stresses at extreme fibers and tensile stresses in reinforcement for
bending moment/loading under SLS combination are checked at all the design
sections as per provision in IRC:112. Stresses of flanges/webs are checked confirming
to IRC: SP-64.
In the transverse direction the voided analyzed as R.C.C. section. The RCC voided is
idealized as a plane frame considering unit width of voided slab.
For obtaining maximum shear stress, the section at a distance equal to effective depth
from the face of the support is checked for ultimate loads and the shear reinforcement
calculated at the section is continued up to the support.
Shear check is checked for all critical locations for ultimate loads.
Seismic Design
The Project Corridor falls under the seismic Zone-III. Seismic Analysis is carried out in 2
Steps:
Carrying out single mode of analysis to obtain the fundamental vibration period of the
structure in two orthogonal directions (i.e. Longitudinal & Transverse direction).
Estimation of seismic forces using the spectrum response, as per IRC: 6-2014.
The calculation for fundamental period is done either by using the simplified expression
given in Appendix – D of IRC: 6-2014 or else by modeling the structure in STAAD/Pro and
carrying out dynamic analysis.
Vertical seismic coefficient is taken as “two third” of the horizontal seismic coefficient. The
vertical seismic is combined with the horizontal seismic in any one direction. The seismic
combination to be considered is as follows:
o +SX+0.3SY+0.3SZ
o +SY+0.3SX+0.3SZ
o +SZ+0.3SX+0.3SY
Where SX & SZ are seismic forces in longitudinal & transverse direction respectively, while
SY is the seismic force in vertical direction.
Method of Analysis/ Design for Sub-Structure & Foundation
The Sub-structure (Abutment/ Pier) is designed to withstand the vertical forces transferring
from Superstructure. IRC: 78-2014 Codal provisions is followed in this regard.
The scour to be considered for design is based on mean design flood. In the absence of
detailed data, the scour to be considered for design is 0.9 times the maximum design scour
depth.
In loose sands or poorly graded sands with little or no fines, vibrations due to earthquake may
cause liquefaction or excessive total and differential settlements. Since this project is located
in critical seismic zone & hilly region, hence liquefaction effect is not required to be
considered.
The dimension of the member & reinforcement are provided as per design requirement &
minimum criteria as per latest codal provision.
Open Foundation
Considering the project in hilly & rocky terrain, open Foundation is expected as feasible &
shall be proposed in view of rock & safe bearing capacity available at shallow depth. Open
Foundation shall be analyzed as per load combinations mentioned in IRC: 6-2014 & shall be
designed & checked for bending as per the provisions of IRC: 112 & IRC: 78-2014.
Factor Safety against overturning and sliding for unfactored load combination are given
below.
Stresses are checked for SLS condition under rare load combination & crack width is
checked for quasi permanent load combination.
Seismic forces are increased by 25% for design of Foundation as per IRC:6-2014.
Piers & Pier Cap
The piers are designed for as per the provisions of IRC: 112 & IRC: 78-2014. The design is
checked for both, cracked & un-cracked condition.
Pier cap is checked either as a flexural member or as a bracket, depending upon the span /
depth ratio. In case it is a flexural member, the bending moments are checked at the face of
pier support. Shear force is checked at a distance deff away from the face of support. In case
the pier cap acts as a bracket, the design conforms to provisions of IS: 456 in absence of any
specific provision in IRC code for bracket design.
Pier Cap is also checked for bending & shear arising from vertical forces acting on bearings
& torsion due to unbalanced vertical loads on bearings.
Analysis, design and detailing will in general conform to the stipulations of relevant IRC
codes and good engineering practice.
Reinforcement Detailing
The bar sizes and distance between bars and pre-stressing cable ducts/tendons in
accordance with section 15 of IRC: 112-2011.
Curtailment of bars as per clause 16.5.1.3 of IRC: 112-2011,
Minimum Reinforcement and Distribution reinforcement in slabs as per IRC: 112
Minimum shear reinforcement as per IRC: 112-2011.
Minimum diameter of any reinforcement not less 10mm for open foundation,
transverse ties, stirrups and all secondary reinforcement for girder and slab.
Minimum diameter of any reinforcement not less than 12 mm for pier vertical bar,
pier cap main bar, and longitudinal bar in girder.
Ductile detailing as per chapter 17 of IRC:112.
Box culverts shall be constructed with individual precast inverted U-shaped sections
connected by in-situ base and stitch concrete at deck.
Permissible Stresses
The Permissible Stresses in the RCC & PSC members are as per IRC: 112.
The Permissible Stresses in the Composite members & Steel structures considered in design
are as per IRC: 22-2008 & IRC: 24-2010, respectively.
Increase in Permissible Stress in steel and concrete due to various load combinations are as
per IRC: 6-2014.
Software for Analysis and Design
In house developed programs and spread sheets for checking stresses and capacity of
structural element.
Structural Analysis: STAAD.pro.
5.3.2.3 Construction Methodology
As per geotechnical and hydrological investigations wall type/circular RCC piers with
raft/pile foundations are considered. Standardization of spans and type of structures has been
done in view of faster construction. MORTH specifications for road and bridge works shall
be followed for construction methodology.
Clauses which are applicable for relevant parts of structures are as below.
Open foundation ------- Section 2100
Sub-structure ------- Section 2200
Super Structure ------- Section 2300
Protection Work ------- Section 2500
Bearing ------- Section 2000
CHAPTER 6
ENVIRONMENTAL IMPACT ASSESSMENT AND EMP
Ministry of Road Transport & Highways has decided for Rehabilitation and upgrading to 2-
lane/2-lane with paved shoulders configuration and Major Bridge over kosi river for package-
2 section from (km 106+00 to km 136.00) of NH 106 in the state of Bihar.
(b) Widening/ reconstruction to two-lane paved shoulder from the existing single
lane/intermediate lane width,
Certain road stretches may also require the provision of drains, pedestrian, crossings, etc.
In package –I, the project road (NH-106) starts at Udakishanganj at km 106.000 district
Madhepura, and end at Km 136.00 at Bihpur chowk of Bhagal Pur district Bihar. The project
road traverses through two Districts viz, Madhepura and Bhagalpur.
Total 30
Birpur is close to international Nepal boundary at a distance of about 1.5 Km. The entire
stretch of the study road falls under multi-hazardous zone and runs along river Kosi. Further
stretch of this road beyond Udakishangang (106 Km) goes to Bihpur (136 Km) in Bhagalpur
district. The length from 106 Km to 136 Km is included in Package II as river Kosi flows
across the road and is a major hurdle. Similar but separate EIA, EMP studies are being
carried out for this Phase II. The major benefit of this widening and construction of missing
link over kosi bridge improve connectivity of the surrounding areas and also with other
National Highways and State Highways. Map is given in Fig. 6.1.
The project road passes through plain terrain. Nearly 10% area is under flood plain and is
prone to natural flood disasters.
The corridor of impact (COI) is the direct area of influence. The COI is defined on the basis
of road design, speed and the distance needed (the clear zone) for a vehicle leaving the road
to come to a safe stop or to swerve back on to the carriageway. The existing ROW is varying
from 22 m to 24 m. Project stretch has single/intermediate (SL/IL) wide bituminous
carriageway with 1 m to 2 m wide shoulders on both sides. Embankment height varies from 1
m to 8.0 m for most of the stretch. However, for various other environmental components,
which are likely to have a broader area of influence, a distance of 10 km on either side of the
road has been used to define the indirect area of influence.
For a design-speed of 80-100 km/h, the clear zone should extend 4.5 m beyond the standard
of 2.5 m road shoulder, thus creating a 7 m wide cleared area beyond the edge of the
carriageway. For this design speed the COI would be 21m (4.5 m clear zone plus 2.5 m
shoulder on either side plus two 3.5 m carriageways). However, in certain cases, the COI is
wider than the available ROW (such as where land beyond the ROW is required for
geometric realignment of highway, etc) and in these cases the direct area of influence has
been taken as the “edge of permanent works”.
In urban areas, with design speed of 50-60 km/h, the minimum COI would be about 16 m.
However, because of the need for on-street parking, and similar facilities, the COI has been
set as 18 m. These COI boundaries, when drawn onto the strip maps, yield much lower and
hopefully more realistic impacts, for example, reduced number of affected assets and persons.
The COI concept has not been applied as an absolute measure but, rather, as a guideline. The
COI is extended to include, the ROW boundary and beyond, for example, when schools or
hospitals border the ROW. The design decisions also play a part where, the pavement is
deliberately constricted or has been designed as narrow sections.
Table 6.2: Present Traffic Volumes by Vehicle Types along the Project Road
Ruling Minimum
Plain Less than 10%
100 80
In general, the ruling design speed shall be adopted for the various geometric design features
of the road. Minimum design speed shall be adopted where site conditions are restrictive and
adequate land width is not available. However the minimum design speed at a few locations
could be lowered to 50 to 60 km/h due to site constraints and to minimize the acquisition of
land and structures.
6.2.3 Improvement proposal
The improvement proposal includes up gradation of existing carriageway.
The main elements of the up gradation - widening and strengthening are:
(i) Widening is done along the existing alignment eccentrically in rural areas and
concentrically in urban areas.
(ii) Wherever adequate ROW is not available, the deficient curves are improved to design
speed of 60 km per hour in open area and 50 km per hour in built up area as per
guidelines of MORTH.
(iii) As far as possible the widening is accommodated within the existing ROW and
additional land acquisition is kept to absolutely minimum.
(iv) Numbers of realignments are kept to minimum extent.
In built up area, the widening has been proposed in the entire existing ROW to restrict future
encroachments.
6.2.4 Road Construction Materials
The sources of construction materials such as fine and coarse aggregates, granular sub-base
material, sub-grade soil and borrow area soil have been carried out in respect of their
availability and suitability. Information on existing quarries and other sources of potential
road construction materials have been collected during field visits and from local officers of
the Road Construction Department of the project area.
Details of road construction materials and their locations for the proposed sub-project road
are given below:
6.2.4.1 Rocks/Aggregates
Coarse aggregates from different quarries were collected and tested to assess their suitability.
It will be ensured that these quarries have proper valid consent to operate from State
Pollution Control Board. The locations of quarries are listed below:
1) ITARI Source in Nepal, 140 km from 0.000 of Project Corridor.
2) Sahabganj, 225 km from Madhepura (km 73.000 of Project Corridor).
3) Pakur, 320 km from Madhepura
6.2.4.2 Gravel
Murrum and residual gravel are useful as sub-base, sub grade and shoulder material. The
locations of gravel quarries are listed below:
6.2.9 Junctions
10 bus stops are exist along the project road. 10 more bus bays have been proposed along the
project road. Bus bays for village or built up locations have been positioned in straight and
level sections of the road and visible from a long distance in both directions and as per the
recommendations in IRC: 80-1981.
Road markings, mandatory, informatory and cautionary sign boards; delineators, object
markers; reflective pavement markers; guard posts and crash barriers; road humps and rumble
strips have been proposed at appropriate locations for the safety of road users as per the IRC
guidelines keeping in view the site requirements.
There are three major bridges at km 2.20, km 74.227 and km 92.424. Out of three major
bridges, one is proposed to be realigned as a Major Bridge & remaining two are retained.
Also two existing Minor Bridges has been proposed as Major Bridges.
There are 22 minor bridges, out of which 3 are retained. 1 is proposed to be retained with
widening as per two-laning manual and superseding manual while 1 is realigned. Also, 15
Minor Bridges are proposed for reconstruction. Remaining two Minor Bridges are proposed
as Major Bridge as discussed above.
Four additional minor bridges are also proposed after discussion with State RCD and
MORTH Regional Officer at Patna to improve the hydrology of the area.
There are 64 existing culverts, out of which one is retained, 36 are proposed for widening and
remaining 27 are to be reconstructed.
188 additional culverts are proposed to improve the hydrology of the project area from km 0
to km 106.
EIRR should be based on final cost estimate. An analysis for a period of 30 years including
construction period is carried out to assess economic viability of the project.
HDM-4
Base Case NPV Undiscounted NPV Discounted
EIRR (in %)
(in million Rs.) (in million Rs.)
5% Growth Rate 37856.96 3214.20 17.5%
Mitigation Measures
Selected borrow areas have been identified during the design stage of the project. Most of
these borrow areas are local borrow areas, and agricultural fields not in productive use, and
where farmers desired lowering of the level of the land (reduction of energy requirement for
the watering and reduce loss of water, nutrients, and fertilizer through the seepage).
The borrow area should not be located in cultivable land unless unavoidable i.e. no
suitable uncultivable land in the vicinity for borrowing or private landowners are
willing to allow borrowing in their fields.
Along the roadside, borrow pits should be located 5 m away from the toe line.
Impact on Soil
Only 20.329 ha land is required for widening of the project road. Loss of fertile soil may
occur during construction stage, if construction plant, offices, workers camps, stockyards,
borrow areas, etc, are located on fertile areas, and if, haul roads and traffic detours during
construction are routed through agricultural lands. Top soil will be scrapped and stacked
separately. It shall be used for plantation growth on slopes of embankment.
Soil Erosion
Erosion of top-soil can be considered a moderate, direct and long-term negative impact
resulting from the construction phase. The potential for soil erosion is high and pervasive
during the construction stage. Starting with clearing and grubbing of trees vegetation is
stripped away, exposing raw soil. The construction of new fill slopes for grading and bridge-
end fills also exposes large areas to erosion, if protection methods are not implemented.
Compaction of soil
Compaction of soil may occur, particularly on haul roads during site clearance due to
movement of heavy machinery and vehicles and during setting up of construction camps and
stockyards. During construction, there is a possibility of compaction beyond the COI, due to
the movement of vehicles and heavy machinery.
Mitigation Measures
Soil erosion could cause sever negative impact if, not dealt with in time. It may harm the
environment in two ways, firstly it erodes the top soil and secondly it spoils the resource
where it settles, mostly water course. The following measures shall be taken during
construction stage:
Loss of Land
As far as possible the land acquisition has been kept to the minimum, by restricting the
geometric improvement within the existing right of way. However the land acquisition will
be done at sections having width, insufficient to accommodate the approved cross-sections &
geometric improvements.
Due to the removal of structures (Residential), pavement scarification and cross drainage
structures debris will be generated, which shall be disposed properly at designated sites to
avoid contamination of land and water.
The locations of disposal sites have to be selected such that:
Disposal sites to be located at least l000 m away from sensitive locations like
Settlements, Water body, notified forest areas, sanctuaries or any other sensitive
locations.
Disposal sites do not contaminate any water sources, rivers, etc, for this, site should
be located away from water body, and disposal site should be lined properly to
prevent infiltration of water.
Purpose Cum/day
Dust Suppression at work zone 80
Curing 36
Laboratory 20
Haul roads 60
Crusher 40
Plant Cleaning and workshop washing 36
Domestic purpose 20
Permanent works (Total requirement nearly 32000 m3) Average daily 80
requirement
Total Requirement 372 (say 380)
& oxide and carbon based emissions from the hot mix plants. The air pollution during the
construction phase may be considerable locally, particularly near the working zones,
construction plant sites, quarries and from construction machinery and construction vehicles.
The list of activities which generate air pollutants are:
Dust generation from the construction zone during different stages of the construction
such as clearing and grubbing, materials dumping, drying of materials, brushing of the
surface, etc.
Dust generation from the access roads to the borrow-areas, aggregate quarries
construction plants and construction camp sites.
Operation of the construction plants such as hot mix plants, Crushers, WMM plants
and Concrete Batching Plants.
Mitigation Measures
During the construction stage, there are two major sources: the first one is construction
activities at working zones, which cause primarily dust emission and second are from
operation of the construction plant, equipments and machinery, which causes gaseous
pollutants. The specific measures include:
Vehicles delivering fine materials like soil and fine aggregates shall be covered to
reduce spills on existing roads.
Hot mix plants fitted with the bag filter/cyclone and scrubber will be installed for the
reduction of the air pollution.
Pollution control systems like water sprinkling and dust extractors and cover on
conveyors will be installed for the crushers.
All vehicles, equipment and machinery used for construction are regularly maintained
to ensure that the emission levels conform to the SPCB/CPCB norms. Air pollution
monitoring plan has been delineated for construction phase separately for checking
the effectiveness of the mitigation measures adopted during the construction phase of
the contract.
Noise Impacts
The impacts of noise due to the project will be of temporary significance locally in the
construction phase and slight increase may occur during the operation stages. Although the
baseline day & night time noise levels monitored at various locations along the project roads
are within permissible limit specified by the MOEF for residential and rural areas, still, noise
is a major area of concern, especially since sensitive receptors (Schools, Colleges and
Hospitals) have been located quite close to the road.
To assess the noise levels at the various sensitive receptors located along the roads,
consultant carried out the noise survey through noise integrator both at inside and outside the
sensitive receptor. As such no direct impact is envisaged at all the noise sensitive locations
along the project corridor.
All schools, hospitals and cultural properties have been identified and those that are close to
the project roads within 100 m distance will require noise barrier to accommodate the long
term impact of the improved road. The following migration measures will be taken during
construction stage:
Noise standards will be strictly enforced for all vehicles, plants, equipment, and
construction machinery. All construction equipment used for an 8-hour shift should
conform to a standard of less than 75 dB (A). High noise producing generators such as
concrete mixers, generators, graders, etc, must be provided with noise shields.
Workers in the vicinity of high noise levels will be provided earplugs, helmets and
will be engaged in diversified activities to prevent prolonged exposure to noise levels
of more than 90dB(A) per 8 hour shift.
During construction vibratory compactors will be used sparingly within the urban
areas. In case of complaints from roadside residents, the engineer will ask the site
engineer to take suitable steps of restricting the work hours even further or use an
alternative roller.
Proposed tree and shrub plantations planned for avenue plantation especially close to
settlements, may form an effective sound buffer during the operation stage.
Tree cutting
Trees located within the toe line (bottom of formation) need to be removed for proper
embankment compaction, efficient construction workmanship and more importantly to
prevent collision with the trees, in case of accident. Roadside trees with strong and rigid
stems can pose safety hazards. Some trees obstruct clear sight distances. Others have a
propensity to overturn when old and are potential safety hazards depending upon age and
decay condition. All such trees that are safety hazards need to be cleared.
There will be a significant, direct impact on cutting of the roadside trees, it includes:
Removal of roadside trees will also reduce comfort levels for slow moving traffic and
pedestrians.
The removal of trees would lead to erosion and contribute to the loss of the micro-
ecosystems developed on the roadside.
Besides this, trees act as noise barrier, dust absorption, air purifier, etc.
A detailed tree inventory was carried out of all the existing trees with the corridor of impact;
due care had been given in alignment design to reduce/minimize the loss of flora and green
tunnels. About 9014 trees are required to be felled for the proposed project. No tree will be
cut beyond the proposed toe line. Efforts will be made to transplant the young trees.
There is no recorded wild life habitat in near vicinity of the project corridor.
The trees felled will be replaced and compensated according to the Compensatory
Afforestation Policy under the Forest Conservation Act, 1980. Apart from trees earmarked
for feeling, no additional tree clearing within the ROW will be carried out.
Construction vehicles, machinery and equipment will move or be stationed in the designated
area only (ROW or COI, as applicable), to prevent compaction of vegetation. While operating
on temporarily acquired land for traffic detour, storage, material handling or any other
construction related or incidental activities, it will be ensured that the trampling of soil will be
avoided.
Construction of road will involve removal of topsoil and cutting resulting in clearing of
vegetation cover and felling of trees. However such impacts will primarily occur at the
project site during initial period of the construction phase and will be minimized through
adoption of mitigation measures. 27042 (9014x 3) trees will be planted as compensatory
afforestation.
Water sprinkling on haul roads should be regularly done so that dust pollution is
minimized.
Resettlement of People
Economic Impacts
The overall local and regional impacts on the socio-economics will be positive because of
policies of the project on the improvement of the roads. Such strengthened infrastructure is
expected to contribute to the economic growth of the State and socioeconomic well being of
the people.
The major sources of noise pollution are movement of construction vehicles, the haulage of
construction materials to the construction site and the noise generating activities at the site.
Ambient noise levels may slightly increase due to uninterrupted movement of heavy and light
vehicles at higher speeds along roadway during operational stage.
6.4.1.7.3 Fauna
Biotic components such as flora, fauna and biodiversity conservation are important
considerations in assessing environmental impacts of any infrastructure development project.
Construction will involve some site clearance activities. The adjoining areas comprise mainly
of common shrubs, weeds and grasses.
Selection of Air and noise All the vehicles, machinery and Contractor,
construction pollution equipments to be engaged for the PIU
vehicles, construction work should be
machinery and attached with the latest, advanced
equipments pollution control measures
available in the country and those
should conform to the relevant
Indian standards.
Haul roads Air and noise During the inception of the Contractor,
maintenance project, Contractor should identify
pollution CSC, PIU
the network of roads (especially
the village roads) to be used for
haulage of construction materials.
Strategy for the maintenance of
identified haul road stretches is to
be prepared so that regular
maintenance is carried out to those
stretches by the Contractor for
easy plying of construction
vehicles as well as the regular
local commuters.
Selection of Air, water and Compliance to all the State norms Contractor
Borrow areas noise pollution, towards operation and and CSC
loss of environmental protection of
productive borrow areas is the sole
lands responsibility of the Contractor.
CSC will inspect locations
intended for operation and
mitigation measures will be
instructed towards satisfactory
redevelopment. Inspection to the
borrow areas will be carried out by
raising Request for Inspection
(RFI) by the Contractor for each of
the borrow areas and obtain
subsequent approval from CSC.
Selection of Air and noise Contractor will identify the stone Contractor
Stone Quarries pollution, loss quarries in consultation with the
of productive Mining Department. A
lands comprehensive Quarry
Management Plan need to be
prepared incorporating
Environmental and Safety
Management Plan with special
emphasis to Quarry redevelopment
for approval from CSC.
Construction Phase:
Noise generated Since the noise The main noise producing sources Contractor
from generating such as the concrete mixers, and CSC
construction activities are generators, grader etc should be
vehicles, asphalt localized and provided with noise shields around
plants and intermittent, no them. The noise shields can be any
equipments serious impact physical barriers, which is
on human effective in adequate attenuation
CHAPTER 7
RESETTLEMENT ACTION PLAN
7.1 INTRODUCTION
The Project study corridor starts at km 106+000 near Udakishanganj in Birpur and ends at km
136+000 situated near village Bihpur Chowk in Bihpur traversing via Madhepura and
Bhagalpur Districts. The improvement works will consist mainly in raising the formation
level, upgrading/improvement of road geometrics, widening to two-lane/two–lane with paved
shoulders from the existing, single/intermediate-lane and construction of mission link over
kosi river that is the major component of the project. The Project road is shown in Fig. 7.1.
Udaikishanganj to Bihpur (km106. 0 to km 136.0).
Udakishanganj to Hut-549
6 25 11
Bihpur NH-106 House-60
The impacts involve loss of assets, including land and house; loss of livelihood and income
opportunities; collective impacts on groups, such as common property resources. The total
extent of land to be acquired for NH 106 is 50.8 Hectares as per the approved alignment. Due
to land acquisition and clearing of existing ROW from encroachments, 650 structures are
impacted, such as residential, commercial, community assets, religious structures and
government buildings. The impacted structures and the loss of assets and livelihood and the
details shall be assessed and estimated for preparation of resettlement action plan.
To address the resettlement impacts, an action plan to implement the various provisions shall
be worked out and includes the following: institutional mechanisms, grievance redress
mechanisms, procedures for disbursements of entitlements and livelihood restoration
mechanisms, involvement of NGO in implementation, monitoring of effectiveness of RAP
implementation etc, costs towards these have been worked out and are included in the project
costs.
One of the most important aspects of road improvement planning under the present project is
to provide safer road to the users. Generally road accidents are related to (i) the road user
behavior, including pedestrians, drivers and passengers of motorized and non -motorized
vehicles; (ii) the road environment, including physical condition of the road infrastructure
and the traffic control devices, e. g. traffic signs and road markings; and (iii) lack of traffic
law enforcement of motorized and non-motorized vehicles driving on the roads. To predict
road users behaviors accurately is a difficult proposition. However with different
stakeholder‘s involvement in road safety awareness programme, broad road users and people
linkages could be established.
Road safety strategy for community awareness has been formulated based on information
collected from secondary sources from concerned department and to ensure participation.
Major junctions and important curves have been considered as hot spots for road design.
These locations will be considered to generate road safety awareness.
the project, its components, and the R&R policy. Public consultation and disclosure plan is
given in Table 7.2.
Table 7.2: Public Consultations and Disclosure Plan
Activity Task Timing Remarks
(Date/Period)
Stakeholder Mapping of the Project 2015
Identification area
Project Information Distribution of Detailed survey
dissemination information leaflets to in process
displaced persons (DP)
Consultative Discuss potential impacts 13-18 Sept
meetings with DP of the project 2015
during scoping phase
Public Notification Publish list of affected In process
lands/sites in a local Public consultation
newspaper; establish is done
eligibility cut-off date
Socio-economic Collect socioeconomic Baseline survey
survey information on DP is done
perception on the project
Consultative Discuss entitlements,
meetings on compensation rates,
resettlement grievance redress
mitigation measures mechanisms
Publicize the Distribute leaflets or
resettlement plan booklets in local LA in Process
(RP) language
Full disclosure of the Distribute RP in local
RP to DP language to DP
Internet disclosure of RP posted on World
In process
the RP Bank and/or EA website
Consultative Face to face meetings
meetings during with DP
detailed measurement
survey
Disclosures Disclose updated RP to
DP
Internet disclosure of Updated RP posted on
the updated RP World Bank and/ or
website
Disclosure of Information
The project preparation Support team while conducting structure survey has conducted
information dissemination along the project route in following manner.
Potential project affected families were consulted and canvassed them about proposed
road
improvement program,
Pictorial Methods to explain road improvement proposals in the concerned settlement
Information dissemination among the villagers explaining proposed road
improvement
The project related information would be made available in the following offices and public
places.
Office of the Deputy Commissioner,
Office of the Revenue Circle officer, Office of the Executive Engineer,
Office of the Assistant Executive Engineer,
Office of the Assistant Engineer,
District Central Library
Village Panchayat Offices.
Other Government libraries
RAP document of the project road would be hosted in the official web sites such as:
Government of Bihar,
PWD ( Roads) Government of Bihar
The RAP will be disclosed to the project affected persons and other stakeholders for review
and comments on various mechanisms and entitlement suggested for the implementation.
Intention of this procedure was to receive comments from the project affected persons in
particular so as to incorporate the appropriate suggestions albeit technically feasible.
Concerns raised, would be addressed appropriately by modifying the road designs, provision
of adequate compensation and assistance etc.
For the benefit of the community in general and PDPs in particular, RAP and R&R policy
shall be translated in local language and will be disclosed to PDPs at important locations by
BSPWD and would be kept in local public offices (at least one document in each Tehsil) for
easy access to PDPs.
Key features of the entitlements will be displayed in billboards on the project corridor
at important locations in local language (BSPWD offices and community centers).
The consultant and PIU will conduct information dissemination sessions in major
intersections, congested location and solicit the help of the local community/business
leaders and encourage the participation of the PDPs.
Through public meeting attempt would be made to ensure that vulnerable groups such
as ST households understand the process of project preparation and their needs are
specifically taken into consideration.
The consultant will organize public meetings to inform the community about the
payment and assistance paid to the community as per their category of loss. Regular
update of the program of resettlement component of the project would be placed for
public display at Divisional offices of PWD project offices.
A district level meeting will be organized at the Deputy Commissioner office in a
fixed date at least once in a month with PDPs and line departments.
Continued Consultation
The consultation would be continued as the project enters in the implementation stage.
Several additional rounds of consultations with PDPs will be done through NGO involvement
during RAP implementation. These consultations during RAP implementation will involve
agreements on compensation and assistance options and entitlement package. The other
round of consultation will occur when compensation and R&R assistance are provided and
actual resettlement begins. The following set of activities will be pursued for effective
implementation of RAP.
For the benefit of the community in general and PAP in particular, RAP will be
translated in Hindi will be made available at local public offices for easy access to
RAP related information.
Key features of the R&R entitlements will be displayed in billboards along the project
corridor.
Together with the NGO, Social Management Cell (SMC) of PIU will conduct
information dissemination sessions in major intersections and solicit the help of the
local community business leaders and encourage the participation of the PDPs in RAP
Implementation.
Focus attention will be made for vulnerable groups to understand the Implementation
process and ensure that their needs are specifically taken into consideration.
The NGOs Involved In the implementation of RAP will organize Public meetings,
and will appraise the communities about the progress in the implementation of project
works.
The NGO will organize public meetings to inform the community about the payment
and assistance paid to the community. Regular update of the program of resettlement
component of the project will be placed for public display at Work Department
package offices.
Participation of PDPs will also be ensured through their involvements in various local
committees such as, Village Level Committees, District committees, and Grievance
Redress Committee.
Acts,
Sl.
Notifications Relevance to this project Applicability
No.
and policies
1 National Land required for the project shall be Applicable to
Highways acquired as per the provisions of this act. all sub-
Act, 1956 projects.
2 National Provides limited benefits to affected family Applicable
Rehabilitation and (an ex-gratia payment of not less than Rs.
Resettlement 20,000/- and in case land-holder becoming
Policy (NRRP), landless or small or marginal farmer in such
2007 cases other rehabilitation benefits as
applicable.
Acts,
Sl.
Notifications Relevance to this project Applicability
No.
and policies
3 Bihar Land Government has decided to fix the cost of Applicable
Acquisition the land to be acquired after adding 50% of specifically
Resettlement and registration cost of similar type of land. The for this project
Rehabilitation land shall be acquired after paying 30%
Policy, solatium on the rates as fixed above, but
2007 (BLARRP- wherever the landowner agrees to give his
2007) land voluntarily in that case the solatium to
be paid shall be 60%.
4 World Bank OP The project entails land acquisition though, Applicable to
4.12 – at a low scale for widening, realignments, all sub-
Involuntary junction improvements, bypasses etc. It projects.
Resettlement would also adversely affect structures used
for various purposes, livelihood of people
(mainly earning their livelihood by means of
petty shops and providing various services).
Many of them have been operating from the
government land. Thus both title holders and
non-title holders alike would be affected as a
consequence of the project.
5 The Right to The Act provides for setting out the Applicable
Information Act, practical regime of right to information for
2005 citizens to secure access to information
under the control of public authorities, in
order to promote transparency and
accountability in the working of every
public authority, the constitution of a Central
Information Commission and State
Information Commissions and for matters
connected therewith or incidental thereto.
Where homestead land is being acquired the land owner shall be entitled for same
area of land being acquired (Maximum 5 Decimal) which shall be acquired for the
purpose and shall be handed over to the entitled person.
Every land owner, whose homestead land has been acquired, shall be paid an amount
equal to Rs 10,000 (Rupees Ten thousand) as one time assistance for temporary
accommodation.
Every Land Owner whose homestead land is being acquired shall be entitled for a
onetime payment of Rs 5,000.00 (Rupees five thousand only) as assistance for
transportation of his household goods.
Displaced agricultural laborer who has been working for a period of minimum three
years and who used to earn his livelihood by working on the land which is now under
acquisition and who has become jobless because of the acquisition, shall be entitled
for onetime payment of two hundred days wages as fixed by the govt. under minimum
wages act and shall also be entitled for National/State level job card under National
Rural Employment Guarantee Program.
The policy specifies that the entire cost for resettlement and rehabilitation, in addition to the
cost of acquisition of land shall be borne by the respective requisitioning authorities. The
Requisitioning Authority shall deposit an amount equivalent to 0.5% of the estimated cost of
land under acquisition for the project to the Collector-cum-Administrator, Resettlement and
Rehabilitation through a bank draft subject to maximum of Rs 2.0 (Two lakh) only. This
amount shall be over and above the amount paid for establishment expenditure under LAA.
This additional amount shall be paid for outsourcing the work of survey for Resettlement,
Monitoring, Stationeries, POL and other incidentals like vehicle, Computer, Computer
Operator, Administration, Drafts man, Chainman etc. The better part of the BLARRP-2007 is
that the rate of land offered under it is near to replacement value. The rate of land according
to this policy is 85% more than the rate of land being provided by LA A-1894. Additionally
the policies also ensure transitional assistance, transportation assistance and assistance for
income loss by the DPs.
The National Highways (NH) Act, 1956
For the purpose of development, maintenance, and management of national highways, a
special law, The National Highways Act (NH Act), 1956 has been promulgated. This Act
provides for acquiring land through a ―competent authority‖, which means any person or
authority authorized by the Central Government by notification in the official Gazette to
perform functions of the competent authority for such areas as may be specified in the
notifications. For land acquisition (LA), the Act defines the various procedures as (i) section
3A—intention of Central Government to acquire land, (ii) 3B—power to enter for survey,
(iii) 3C—hearing of objections, (iv) 3D—declaration of acquisition, (v) 3E—power to take
possession, (vi) 3F—power to enter into the land where land has vested in the central
government, (vii) 3G—determination of compensation, and (viii) 3H—deposit and payment
of the amount. The Act requires that the processes must be completed within a year from 3A
to 3D. The Act covers only legal titleholders and provides for compensation based on (i)
market value of the land; (ii) additional payments for trees, crops, houses, or other
immovable properties; and (iii) payments for damage due to severing of land, residence, or
place of business.
Land acquisition in this project will be carried out under the NH Act, 1956. This Act provides
for acquiring the land through "competent authority" which means any person or authority
authorized by the Central Govt. by notification in the official Gazette to perform functions of
the competent authority for such areas as may be specified in the notifications.
Comparison between LA and R&R Policies in the State, NPRR and WB
For this Road stretch the Bihar State has Land acquisition, R&R policy (BLARRP act of
2007) shall be adopted. The advantage of Land acquisition as per NH Act of 1956 is that
within a year the land is acquired and development works can start soon, a comparison of
different policies as shown in Table 7.3.
Table 7.3: Comparison of Gaps in Various Acts and Policies with the World Bank
Resettlement Site
Following procedure will be adopted for selection and development of the resettlement site.
The PDPs will be resettled preferably in a place close to the area where they were residing
prior to the project. The resettlement plan will address the requirement for residential plots of
all squatters. This will be implemented on the basis of providing options for relocation, which
include:
Option 1. Squatters may choose self- relocation with compensation for their structures and
related assistance and,
Option 2. For squatters, who are unable to self-relocate, PIU/NGO will examine on a case by
case basis each household‘s access and ability to find appropriate replacement land for
dwelling and if they are unable to find or afford land themselves, then project will provide the
required suitable land for this purpose.
R&R Requirements of World Bank
Operational Policy 4.12 Involuntary Resettlement provides procedures and responsibilities
towards displaced persons involved in involuntary resettlement. It aims at avoiding or
minimizing forced displacement due to its disruptive and improvising effects
Operational Policy 4.10 ensures that indigenous population benefits from development
projects and those projects' potentially adverse effects are avoided or mitigated.
Operational Policy 4.20 draws on Integrating Gender aspects into the World Bank's Work.
The objective of the Bank's gender and development policy is to assist member countries to
reduce poverty and enhance economic growth, human well-being, and development
effectiveness by addressing the gender disparities and inequalities that are barriers to
development, and by assisting member countries in formulating and implementing their
gender and development goals
Operational Policy 4.11 Make provisions about the impacts on physical cultural resources
resulting from project activities, including mitigating measures, may not contravene either the
borrower's national legislation, or its obligations under relevant international environmental
treaties and agreements.
Definitions
Following definitions that will be applicable unless otherwise stated specifically.
Agricultural labourer: means a person primarily resident in the affected area for a
period of not less than five years immediately before the declaration of the affected area,
who does not hold any land in the affected area but who earns his livelihood mainly by
manual labour on agricultural land therein immediately before such declaration and who
has been deprived of his livelihood;
Agricultural land: Denotes land used or capable of being used for the purpose of
agriculture or horticulture, dairy farming, poultry farming, pisciculture, sericulture,
breeding of livestock or nursery growing medicinal herbs, raising of crops, grass or
garden produce and land used by an agriculturist for the grazing of cattle, but does not
include land used for cutting of wood only;
Below poverty line (BPL) or BPL family: means below poverty line families as defined
by the Planning Commission of India, from time to time and those included in the BPL
list for the time-being in force.
Corridor of impact (COI): Refers to the minimum land width required for construction
including embankments, facilities and features such as approach roads, drains, utility
ducts and lines, fences, green belts, safety zone, working spaces etc. Additional land
width would be acquired/purchased or taken on temporary lease if the Corridor of Impact
extends beyond the available Right of Way.
Cut-off date: Refers to the date on which the census survey of PDPs starts in that road
section/stretch. For entitlement purpose, the PDPs would be those who have been in
possession of the immovable or movable property within the affected area/zone on or
prior to cut off date. However, the cut-off date for land acquisition purpose is the date on
which the notification under section 3A will be issued under the NH Act, 1956.
Encroacher: A person who has extended their building, agricultural lands, business
premises or work places into public/government land without authority.
Entitled person (EP): A person who is adversely impacted by the project and is entitled
to assistance as per the project entitlement framework is considered to be an Entitled
Person.
Holding: means the total land held by a person as an occupant or tenant or as both;
Kiosk: A kiosk is a booth/stall/cabin/cubicle made of wood or iron or any other building
material which could be shifted to another location as a single unit without much damage
and is used for carrying out petty business/ commercial activities and has been in
operation/existence prior to cut off date.
Land acquisition" or "acquisition of land": means acquisition of land under the NH
Act, 1956 for the time being in force;
Landowner: A person who is an allottee or a grantee of any land under any scheme of
the Government under which such allotment or grant is to mature into ownership, who
has mortgaged his land (or any portion thereof) or who has permanent rights and interest
in land.
Marginal farmer: Refers to a cultivator with an un-irrigated land holding upto one
hectare or irrigated land holding up to half hectare.
Non-agricultural labourer: means a person who is not an agricultural labourer but is
primarily residing in the affected area for a period of not less than five years immediately
before the declaration of the affected area and who does not hold any land under the
affected area but who earns his livelihood mainly by manual labour or as a rural artisan
immediately before such declaration and who has been deprived of earning his livelihood
mainly by manual labour or as such artisan in the affected area;
Non-titleholder: Affected persons/families/ households with no legal title to the land,
structures and other assets adversely affected by the project. Non-titleholders include
encroachers, squatters, etc.
Notification: means a notification published in the Gazette of India.
Occupier: means a member of a Scheduled Tribes community in possession of forest
land prior to the 13th day of December, 2005;
Project: Refers to the National Highways Interconnectivity Improvement Project
(NHIIP).
Project affected area: Refers to the area of village or locality under a project for which
land will be acquired under NH Act 1956 through declaration by Notification in the
Official Gazette by the appropriate Government or for which land belonging to the
Government will be cleared from obstructions.
Project affected family: includes a person, his or her spouse, minor sons, unmarried
daughters, minor brothers, unmarried sisters, father, mother and other relatives residing
with him or her and dependent on him or her for their livelihood; and includes "nuclear
family" consisting of a person, his or her spouse and minor children;
Project affected person (PAP): Any tenure holder, tenant, Government lessee or owner
of other property, or non-titleholder who on account of the project has been affected from
such land including plot in the abadi or other property in the affected area will be
considered as PAP.
Project displaced person (PDP): Any tenure holder, tenant, Government lessee or
owner of other property, or non-titleholder who on account of the project has been
involuntarily displaced from such land including plot in the abadi or other property will
be considered as PDP. A displaced will always be a PAP but all PAP may not be PDP.
Project affected household (PAH): A household that may comprise of one family or
several families.
Replacement cost: A replacement cost/value of any land or other asset is the cost/value
equivalent to or sufficient to replace/purchase the same land or other asset.
Small farmer: Refers to a cultivator with an un-irrigated land holding up to two (2)
hectares or with an irrigated land holding up to one (1) hectare.
Squatter: A person who has settled on public/government land, land belonging to
institutions, trust, etc and or someone else‘s land illegally for residential, business and or
other purposes and/or has been occupying land and building/asset without authority.
Tenant: A person who holds / occupies land / structure of another person and is or (but
for a special contract) would be liable to pay rent for that land / structure to other person
and includes the predecessor and successor-in-interest of such person but does not include
mortgage of the rights of a landowner or a person to whom holding has been transferred
or an estate or holding has been let in farm for the recovery of an arrear of land revenue
or of a sum recoverable as such an arrear or a person who takes from Government a lease
of unoccupied land for the purpose of subletting it.
Titleholder: A PAP/PAF/PAH who has legal title to land, structures and other assets in
the affected zone.
Vulnerable group: This includes Scheduled Caste. ST, family/household headed by
women/ female, disabled, handicapped, orphans, destitute, BPL, abandoned woman;
unmarried girls; widows; and persons above the age of 65 years irrespective of their
status of title (ownership). Vulnerable groups would also include those farmers who
(after acquisition of land) become small/marginal farmers and also qualify for inclusion in
BPL. For such cases, total land holding of the landowner in that particular revenue village
will be considered in which land has been acquired.
Wage earner: Wage earners are those whose livelihood would be affected due to the
displacement of the employer. The person must be in continuous employment for at least
six months prior to the cut-off date with the said employer and must have reliable
documentary evidence to prove his/her employment.
Based on the above analysis of government provisions and requirements as per World Bank
IR policy the broad resettlement principle for this project shall be the following:
Proposed highway improvement and strengthening work will take place mostly on the
existing alignment and within the available ROW except at locations where bypass is
proposed or at locations were realignment is necessary to incorporate required safety
measures;
The involuntary resettlement and adverse impacts on persons affected by the project
would be avoided or minimized as much as possible exploring viable alternative project
design;
Where it is not feasible to avoid resettlement, resettlement activities should be conceived
and executed as sustainable development programs, providing sufficient investment
resources to enable the persons displaced by the project to share in project benefits;
Efforts should be made to improve their livelihoods and standards of living or at least to
restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the
beginning of project implementation, whichever is higher;
Displaced persons should be meaningfully consulted and should have opportunities to
participate in planning and implementing resettlement programs;
Replacement land shall be an option for compensation in the case of loss of land. In case
of unavailability of replacement land, cash-for-land with compensation on replacement
cost option will be made available to the PAPs;
Compensation for loss of land, structures and other assets will be based on full
replacement cost and will be paid before physical displacement of PAPs including
transaction costs;
In the event of necessary relocation, PAPs shall be assisted to integrate into host
communities;
All land acquisition for the project would be done as per the National Highways Act,
1956.
Additional assistance would be provided to the PAPs for meeting the replacement cost of
the property;
The uneconomic residual land remaining after land acquisition will be acquired by the
project.
The owner of such land/property will have the option to seek acquisition of his entire
contiguous holding/ property provided the residual land is less than the average land
holding of the district;
Any structure/asset rendered unviable/unsafe because of the project shall also be
considered as affected and entitlements shall be extended accordingly;
The affected persons who does not own land or other properties, but have economic
interests or lose their livelihoods will be assisted as per the policy principles described in
this document;
Cut-off date for titleholders will be the date of publication of notification under Section
3A of the National Highways Act, 1956. For non-titleholders who has not any legal
holding of the occupied land such as squatters and encroachers the date of project census
survey or a similar designated date declared by the executing agency will be considered
as cut-off date;
An entitlement matrix for different categories of people affected by the project has been
prepared and provisions will be kept in the budget for those who were not present at the
time of census survey. However, people moving in the project area after the cut-off date
will not be entitled to any compensation or assistance;
Vulnerable groups (PAPs below poverty line (BPL), the landless, disabled, elderly
persons, women and children, indigenous peoples) will be identified and given additional
support and assistance under the project;
All common property resources (CPR) lost due to the project will be reconstructed
or compensated by the project;
Information related to the preparation and implementation of resettlement plan will be
disclosed to
all stakeholders and people‘s participation will be ensured in planning and
implementation;
Appropriate grievance redressal mechanism will be established at sub-project, state and
central levels to ensure speedy resolution of disputes;
An effective monitoring and evaluation mechanism will be established to ensure
consistent implementation of resettlement activities planned under the project including
third party monitoring.
Entitlement Matrix
This entitlement matrix has been developed in accordance with the basic principles adopted
in the RPF and analysis of initial identification of project impacts. In case State Government
through any Act or Gazette Notification or as approved by any authority of State Government
(duly authorized for the purpose) as per their approved procedure has fixed a rate for
compensation of land and is higher than the provisions under the project, the same may be
adopted by the Competent Authority in determining the compensation for land.
Similarly, in case State Government through any Act or Gazette Notification or as approved
by any authority of State Government (duly authorized for the purpose) as per their approved
procedure has fixed a rate for resettlement and rehabilitation assistance and is higher than the
provisions under the project, the same may be adopted by the Executing Authority.The
developed entitlement matrix is presented in Table below.
The Entitlement Matrix provides category-wise details regarding the entitlements in relation
to the R&R principles enumerated above. Table 7.4 presents the entitlement matrix for the
project:
E. Loss of Livelihood
6 Families Title
Resettlement a) Monthly subsistence/transitional
living Holders/ & allowance equivalent to twenty-five
within the Non-Title Rehabilitation days minimum agricultural wages per
Corridor of holders/ month for a period of one year from the
Assistance
Impact sharecroppe date of displacement (para 7.16 of NRRP-
(CoI) rs, 2007).(PAPs covered under 1(f), 2(f) and
agricultural 5(e) (i) above would not be eligible for
labourers this assistance).
and b) Training Assistance of Rs 10,000/- for
employees income generation per family
c) Temporary employment in the project
construction work to project affected
persons with particular attention to
vulnerable groups by the project
contractor during construction, to the
extent possible
Suggestion
Sl Location/ Public Mitigation
Issues Raised from Remarks
No. Date Consultation Measures
Participants
People
perceived that Employment to
the proposed local skilled and
project road unskilled
Shankarpur Locals should Farmers stay
will provide laborers will be
1 Madheli be given idle between
quicker preferred during
13/9/15 Employment two crops
transport road construction
facility and and operation
generate phase
employment
Proper
The
relocation of
loss of compensation Relocation
the displaced
Karma agricultural money of of common
2 persons &
16/9/15 land and agricultural land property
compensation
structures should be resources
against loss
properly invested
of land
Suitable
resettlement All the
Self options will be grievances
Fulaut problem in relocation offered to them will be
3
18/9/15 relocation and adequate to maintain their resolved by
compensation pre project living mutual
standards , even consultation
better
Major findings (arising out of the consultations) related to key issues such as general
perception about the project; suggestions to mitigate hardships resulting from dislocation and
loss of livelihood, the details are given below:
People were convinced about the importance of good highways in their region since it
will reduce the incidence of accidents and enhance economic opportunities
Most people preferred to resettle near their previous place of business and residence
and preferred self-resettlement
Cultivators preferred cash compensation at market rate. Land for land option was least
preferred
Requests were made by the affected people for providing facilities and amenities like
rain shelter and safer accessibility at points of congestion and intersections
On site relocation for small business enterprise (SBE) within the ROW at the edges of
the carriageway were suggested. Small Business Enterprisers were not interested to
relocate at far-off locations. They perceived low business growth at such locations
People suggested that adequate safety measures should be provided such as speed
breakers, signages, etc, near inhabited areas, school, hospitals, etc.
To speed up the land acquisition process, the negotiation with the land acquisition is
proposed to be used for fixing up the land price. The compensation for the land to be
acquired will be paid through private negotiation with the concerned landowners. The PIU
will examine the possibilities of the implementation and will take the necessary initiatives
as described below. The LA Act procedures will be adopted in case of negotiation fails with
the land owners.
A time period of 45 days would be available for carrying out negotiations with the
Landowners
After every round of negotiation, record (Documentation) would be sent to the DC and
RCD, Bihar.
The RCD will hand over the final list along with Land records map duly verified by the
Revenue Department to the concerning NGO.
Land
Circle rate Compensation
Sl Acquisitio
Existing (km) Village per unit (Based on
No. n Area
Rs/sqm Circle Rate), Rs
(sqm)
Hario
Tulsipur
Madwa
9 132.200 to 132.900 Tulsipur 15695.580 500 7847790
10 133.250 to 133.800 Tulsipur 37462.389 500 18731194.5
11 134.200 to 134.900 Madwa 1890.560 500 945280
Total 254175903
Cost In ( Cr) 25.417 cr
Cost with
50% Additional as registration cost (B) 12.708 cr
60% solatium if owners agree to give land voluntarily ( C ) 15.250 cr
Interest @ 12%/Year for one year 3.05 cr
Departmental Charges 2% of B 0.508 cr
Contingency Charges 0.5% on B 0.127 cr
Total 57.060 cr
Negotiations of Land Rates
The negotiation shall begin by offering a minimum of basic land rate/value. According to
R&R policy, the following formulae can be adopted to achieve basic rate/value i.e,,10% of
circle rate (If the circle rate is more than one year old at the time of negotiation, additional of
10% per year will be to added) +1.5 times + 30% .
Cost and Budget
The format for unit cost for resettlement and rehabilitation is presented in Table 7.8.
Table 7.8: Unit Cost for R& R
Administrative and Financial Responsibilities of officials and Agencies are given in Table 7.10.
Table 7.10: Administrative and Financial Responsibilities of officials and Agencies
PIU Chief Project • In charge of the overall project activities. • Will be authorized to
Officer • To decide on all policy matters regarding LA and R & R. make any additional
changes without
• Participate as a member secretary in the State level Committees to facilitate
having to refer to the
land acquisition, pre-construction activities, and implementation of R & R
Steering committee,
activities.
provided the amount
• Authorized to take decision in financial matters within the provided budget. is within the budget
Project Director • Overall in charge of day to day activities of LA and R & R. • To approve awards
• Participate in State and District level meetings to facilitate LA and R & R above Rs.50 lakhs to
activities. Rs. One Crore.
• Responsible for contracting NGOs and Monitoring consultants. • To approve of Rand R
assistance above One
• Periodic appraisal of progress and reporting to the World Bank and the
lakh.
Government on monthly basis.
Assistant Director • Assist CAO in the implementation of R & R activities. • No financial powers
Social Welfare • Coordinate training for PIU and NGOs for capacity building to implement R &
R.
• Facilitate development of resettlement sites and agriculture land.
• Participate in the allotment of residential and commercial plots to the DPs.
• Liaison with district administration and line departments for dovetailing
government schemes for income generating activities to DPs.
• Participate in the meetings of Grievance Redressal Committee.
Manager R & R • Coordinate implementation of R & R activities with PIU and field staff. • No financial powers
• Facilitate the appointment of external agency for monitoring activities to be
taken up by the implementing NGO.
• Assist CAO to perform R & R activities.
• Review the work in finalization of resettlement site development.
• Prepare monthly progress report for the SDRC and Land Acquisition.
• Monitor the R & R report and submit to CAO and PD.
LA Special DC Land • Coordinate Land acquisition process with Tehsildar at field. • To approve awards
Acquisition • Prepare guidelines and procedures to be adopted for land acquisition. upto Rs.50 lakhs,
• Interact with District officials and other stakeholders to speed up the land
acquisition process.
Asstt. Comm- • Assist CAO and Sp. DC LA to perform R & R and Land Acquisition activities. • No financial powers
issioner -LAO • Make budgetary provisions
Tehsildar • Overall responsible for land acquisition as land acquisition officer. • No financial powers
• Coordinate the preparation of Land Plan Schedules with Consultants and
monitor the same.
• Prepare progress report on physical and financial monitoring of LA and submit
to DC LA.
FIELD UNIT Executive • Participate in District level meetings. • No financial powers
Engineer • Oversee the process of implementation of RP in the field.
• Ensure the preconstruction work is done before handing over site to contractor.
• Oversee the process of land acquisition, shifting of CPRs and other assets in
the field.
• Scrutinize and certify the structures valuation report submitted by the
valuators.
• Coordinate selection of resettlement site. • Conduct periodic review with staff
• Submit monthly progress reports to PD on R & R activities.
Assistant • Responsible for pre construction work in his jurisdiction. • No financial powers
Executive • Finalization and demarcation of COI.
Engineer • Coordinate with NGO/Monitoring consultants and SDO to carry out R & R
activities.
Social Welfare • Responsible for maintaining the R & R work at division wise. • No financial powers
Inspectors • Assist NGO for selection of resettlement site.
• Assist Monitoring Consultants /NGO to conduct training for DP on IGA
• Coordinate with SDO/EE at field level for disbursement of R & R assistance.
• Ensure all eligible DPs are awarded compensation.
Grievance • Support DPs in resolving issues related to R & R and LA. • No financial powers
Redressal • Record grievance and resolve them within stipulated time.
Committee.
• Inform PIU about any serious cases.
• Report to the aggrieved parties about the decisions of the PIU.
judge of the area. Other members would include a retired revenue officer from the locality, a
retired PWD engineer, and a representative of NGO. The broad functions of the GRC are the
following:
Record the grievances of PAF, categories and priorities them and provide solution to
their grievances related to land and property acquisition.
If required, the GRC would undertake site visit, ask for relevant information from the
project authorities, other government and non-government agencies, etc.
Fix a time frame within the stipulated time period of 60 days to resolve the
grievances.
Inform the aggrieved parties through the NGO about the development of their
respective cases and their decision to the project authorities and the aggrieved parties
as well.
Table 7.12 illustrates the sequential steps for the grievance redress mechanism.
Table 7.12: Monitoring of GRC (Grievance Redressal)
6 No. of DP moved to
court
Response Time
The GRC will hear grievances once in a month. However, as the entire resettlement and
rehabilitation process has to be completed before road construction work starts, the GRC may
meet frequently and more than once every month, depending upon the number of such cases.
The GRC will inform the concerned Entitled Person/PDP of their decision within 60 days of
the hearing of the grievances. It is, however, noted that the decision of the GRC will not be
binding on the PAF, who may approach the civil courts for redress of his grievances
7.12 MONITORING AND EVALUATION
Monitoring and Evaluation (M&E) are critical activities in involuntary resettlement in order
to ameliorate problems faced by the PDP and develop solutions immediately. Monitoring is a
periodic assessment of planned activities providing midway inputs, facilitates changes and
gives necessary feedback of activities and the directions on which they are going, whereas
evaluation is a summing up activity at the end of the project assessing whether the activities
have actually achieved their intended goals and purposes. The M&E mechanism will
measure project performance and fulfillment of the project objectives.
RP implementation for the Project Highway will be closely monitored by PIU through its
R&R Cell and will be at the helm of all activities related to the RP implementation.
Components of monitoring will include performance monitoring, impact monitoring and
external evaluation. Two broad categories of indicators will be monitored during the project
are: 1) input and output indicators and ii) outcome and impact indicators.
Input and output indicators related to physical progress of the work will include items as:
Training of PIU, RO and other staff completed
Public meetings held
Census, assets inventories, assessments and socio-economic studies completed
NGO recruited and trained
Meeting of DLC
Meeting of GRC
Grievance redress procedures in-place & functioning
Compensation payments disbursed
Shops space allotted
Relocation of PDP completed
Employment provided to PDP
Community development activities completed
Infrastructure repaired, bus stands, water & sanitation facilities provided
Village roads repaired
Total Progress
Sl Monitoring Indicators for Implementation Unit
Cost this
No. Physical Progress Target Cost
(Rs.) Month
1 Land Acquired-private
Land transferred –
2
Government
Allowance for those losing
3
land
4 Commercial site (owner)
Pucca housing (Area in
5
(sqm)
6 Semi Pucca (Area in sqm)
Total Progress
Sl Monitoring Indicators for Implementation Unit
Cost this
No. Physical Progress Target Cost
(Rs.) Month
7 Kutcha (Area in sqm)
8 Commercial site (squatter)
EWS House construction
9
(Non Titleholder)
10 House construction (owners)
Shifting Allowance (Non
11
titleholders)
Subsistence Allowance (Non
12
titleholders)
Subsistence Allowance
13
(Owners)
Shifting
14
Allowance(Titleholders)
Economic generating asset
15
(owner/tenant)
Economic generating asset
16
(squatter)
Rental Value for
17
Commercial tenant
Rental Value for Residential
18
tenant.
Training for DP (commercial
19
owner, employee)
20 Vulnerable groups
21 Group Entitlement (kms)
CHAPTER 8
SAFETY CONSIDERATIONS
8.1. GENERAL
As part of the ongoing process of building safety into highway improvement schemes and
other developments affecting the public highway, a procedure for auditing designs and newly
completed works is implemented. In this project the evaluation of Highway Improvement
Schemes i.e., imparting safety into the highway system during design and at the end of
construction (preferably before the scheme is open to traffic) is planned to identify potential
road safety problems that may affect many users of the highway and to suggest measures to
eliminate or mitigate those problems. Here the audit process includes the accident monitoring
of Highway Improvement Schemes to identify any road safety problems that may occur after
opening.
8.1.1. Basic Safety Considerations Related to Designs
The two main strategies in designing the road safety work are accident reduction and accident
prevention. In the former we generally use the previous accident data on existing roads to
influence the designs of behavior of the road user. In the latter we apply expertise for safe
design including both geometric design and material design. Hence the following safety
considerations are incorporated in the design:
Design standards for whole project uniformly applied essential from the view point of
road user’s safety and the smooth flow of traffic.
Both horizontal and vertical geometry are given importance at all stages.
The designs are consistent and the standards proposed for the different elements are
compatible with one another and abrupt changes in the design speed were avoided.
“Ruling” standards are followed and “Minimum” standards are followed for safety
considerations only where serious restrictions encountered by technical or economic
considerations.
Table 8.1: Safety Considerations Related to Design
maintain a speed of 80 km/h, the design speed of 100 km/h is adopted with minor changes to
the alignment. The warning signs are considered wherever reductions in design speed are
obligatory.
Existing horizontal curves, which are found deficient in radius, transition lengths or super
elevation, are corrected to the extent possible within the available ROW. Uniformity of
design standards of curves is one of the essential requirements of any road alignment. Hence
in any given section of the project corridor, curves are consistent with safe design criteria to
avoid creation of unexpected situations for the drivers. On horizontal curves with radius upto
300 m, width of pavement and roadway is increased as per standards. Increasing the degree
of horizontal curvature also tends to increase the cause of accidents. So to overcome this,
super elevation is applied according to IRC guidelines with respect to the proposed centerline
and the rate of change of super elevation is kept not steeper than 5%, thus the horizontal
alignment provided blends well with the surrounding topography.
8.1.5. Intersections
While planning the intersections, maneuvering should be simple for the approaching vehicles.
For safer negotiation at intersections the straight priority is expected from the riders so clear
visibility of signs and markings are offered. Roundabouts are a form of intersection control
with their own set of priority rules. So adequate visibility-distance is provided for emerging
traffic and obstructions present if any are removed at intersections. All the junctions on the
project road are atgrade intersections and developed as per IRC-SP-41.
8.1.6. Visibility
Providing adequate visibility for all the users is a necessity for safer travel. All the control
features are so designed that they do not cause hindrance as such to drivers view in the sight
triangle yet they are visible in decision making. Here the road markings and signs are
provided with precision as per IRC with definite angle and height to enhance the visibility
and to improve driver’s safety.
The traffic comprises non-motorized vehicles also, so safe pedestrian and cyclist passing are
provided at sections where the threshold value crossed as indicated in the code. The refuges
are provided to enhance pedestrian safety, they not only help pedestrian to maneuver across
safely but also helps in channelization of traffic.
Since the project highway is being developed as a 2-lane road with Earthen/paved shoulders,
access management is done through properly designed intersections, segregations of
pedestrian traffic in habituated areas.
urban areas and in the rural sections delineators and crash barriers with reflectors are
provided. Raised Pavement Markers (RPM) are installed at curves, near bridges and
intersections to improve the night time visibility.
8.1.15. Vehicles
Parking on streets side to busy arterial roads is hazards, especially in urban areas near the
intersections, petrol bunks etc cause hindrance to through traffic. For parked vehicles designs
are planned to avoid/remove/relocate parking in traffic lanes for efficient usage of road width,
uninterrupted traffic movement and also safety of the commuters.
8.2. SAFETY ISSUES FOR NON MOTORISED TRAFFIC
The mixed traffic conditions create a safety challenge of significant magnitude. They are
vulnerable when they travel along with motorized traffic which travel with high speeds,
hence special consideration is given for non motorized traffic.
Table 8.2: Safety Issue for Non-motorized Traffic
obstructions and sufficient space for waiting are given importance for location of pedestrian
crossings. Controlled form of crossing normally through provision of zebra crossings is
provided at intersections and required locations. Once a pedestrian is on a zebra crossing, he
gains priority of movement with respect to vehicular traffic. Pedestrian crossings are
inevitably integrated with the overall design of the intersection.
8.2.3. Lay-byes/Bus Bays
Truck Lay byes and bus bays are designed to provide access as they separate stopping traffic
from main carriageway. Although there are considerable through bus traffic movements, the
numbers of buses stopping at existing bus stops are few. There are no existing facilities
available for truck parking along the corridor hence this situation makes drivers park their
vehicles haphazardly inviting danger for other riders. Hence specific locations where there is
an need for bus bays in specific villages are identified and provided considering all necessary
safety issues.
8.2.4. Bicyclist, Rickshaw and Animal drawn carts
The provision of paved shoulders in habituated sections provides additional space for
overtaking, slow moving and non-motorized traffic. A wide cross-section (7.0 m carriageway
+ 1.5 m paved shoulder) is used to increase safety, by allowing separation of slower traffic,
which can travel on the relatively wide paved shoulder, rather than completely on the main
carriageway, which is now the case. This further helps to reduce accidents and increase road
capacity.
Table 8.3: Check List
S. No. Element Question Check
Horizontal
Are horizontal and vertical alignments
1 Curves, Vertical √
consistent?
Curves
Are all lanes curved and speed reduced
2 Roundabouts adequately? √
Will the central island visible?
Are all conflict areas clearly visible from entry
points?
3 Intersections √
Is there sufficient space for all types of vehicle
maneuvers?
Visibility, Sight Is the visibility acceptable?
4 √
Distances Are the sight lines obstructed?
Whether access to road furniture, bus bays is
5 Access Control √
safe?
Are camber, lane widths, shoulders, drains are
Cross section as per design standards?
6 √
Elements Are cross falls appropriate, suitable gutter
gradient and shoulder gradient?
CHAPTER 9
TRAFFIC MANAGEMENT DURING CONSTRUCTION
9.1. GENERAL
Traffic management is the control of pedestrians, vehicles and plant that are present on
construction sites. The arrangement of Traffic during construction shall conform to the
requirements of IRC: SP: 55 and clause 112 of MORTH Specifications.
Controlling vehicles - Each site should have a traffic management plan, this is a visual layout
of the site that shows structures, roads, site storage, compound, pedestrian routes, etc.
(depending on what's on site).
This Chapter sets out the traffic management measures that may be necessary during the
construction of the road works, and outlines the process which will ensure that affected
residents, businesses and others are informed.
The planning of the works will include consideration of the access and servicing
requirements of affected residential and commercial premises. The contractor will work
together with the nominated person to ensure regular communication with parties affected by
the works. Local residents and businesses will be informed in advance of the dates and
durations of closures and will be provided with details of diversion routes at least two weeks
in advance or when final details are available. Access and servicing will be maintained as for
as reasonably possible, within the constraints of the works and the need to ensure the safety
of the public.
Some traffic management proposals may require Traffic Regulation Orders under the Motor
Vehicles Act 1988 to cover measures such as the introduction of one-way streets, banned
turns, temporary speed limits and the suspension of parking places. These will be discussed
at the liaison meetings and applications for these Orders will be made to the relevant traffic
police authority.
The majority of the works on the route are within existing road corridors, with works limited
to improvement including upgradation and widening of NH 106 from single/intermediate
lane as well reconstruction of weak bridges and culverts.
The bulk of the works in the section will be Reconstruction of roads and the reconstruction of
bridges and culverts. It is therefore, in the section that road works will have the most impact
on the highway in terms of traffic delay, pedestrian movement and loss of parking.
In addition, local diversions and lane closures will be necessary for utilities diversion works
many of which will be undertaken prior to the commencement of the main works.
c) Buses – diversion of bus routes; suspension and relocation of bus stops and Bus
stands;
d) Taxis – relocation of pick up and getting down points;
e) Traffic – Road closures with signed diversions;
- Lane closures; Local shuttle working under traffic signal control;
Contractor and Employee, have a responsibility to minimise the risk of injury and death to
their staff as well as to road users. The Contractor should follow the Guidelines in Road
Construction Zones (IRC SP 55) and maintain the various Road Signs given in the guidelines
in good order till the work is completed.
CHAPTER 10
CONCLUSIONS AND RECOMMENDATIONS
10.1. CONCLUSIONS
(i) The road passes through major habitations like Madhepura, Kishanganj and Phulaut
and Bihpur. There is missing link due to Kosi river. Four lane single Bridge having
length 6.93km has been finalized after various meetings with MORTH considering
Induced traffic after construction of Missing link over Kosi bridge.
(ii) The following would be the benefits of improving the project road:
Development of Tourism
(iii) The existing ROW along the project road generally varies from 22 m to 24 m. In most
of the stretches the proposed widening can be accommodated within existing ROW.
As there are no proposed bypasses in the project road Land Acquisition is minimum
and will be required only at realignment for Kosi bridge and Toll plaza Hence the
project will be having minimum social impact in terms of Rehabilitation and
Resettlements.
(v) Total number of trees and plants to be cut in forest areas are 2,550 and 12,876
respectively. In addition to this, 297 Nos. of trees to be cut in in non-forest area.
10.2. RECOMMENDATIONS
The road stretch from km 0.0 to 106.0 is economically viable but the project stretch is not
financially viable due to high cost bridge over Kosi River. Hence the project is recommended
to be implemented on EPC mode.
The salient features of the project road are shown in the table below,
S.
Descriptions Features
No.
28.918 km
1 Design Length (km.)
(Ch. 106.000 to Ch. 134.918)
24m to 60m
2 Proposed ROW
150 m at Toll Plaza Section
The existing highway shall be upgraded to 2 lane/ 2 lane
paved shoulder with Four lane bridge over Kosi river
3 Configuration
having 6.93km length 120 span of 2x12.5m & 6 span of
2x15.2 carriageway and total 126 Nos. x 55m Span.
4 Bypass NIL
Grade separated
5 NIL
Structure
6 ROB NIL