Technology Park Development Project, Islamabad Electrical Load Estimation (Phase-1-1)
Technology Park Development Project, Islamabad Electrical Load Estimation (Phase-1-1)
Technology Park Development Project, Islamabad Electrical Load Estimation (Phase-1-1)
Estimation(Phase-1-1)
Area Type Area (Sq meter) Watts/sq meter Load (watts) Load (KW) Load (KVA)
HVAC 45501 86.11 3,918,091.1 3918.1 4124.3 KVA
Lighting & 67410 53.81 3,627,332.1 3627.3 3818.2 KVA
others
TOTAL= 7545.4 KW 7942.5 KVA if
PF=0.95
If Demand factor is 0.5 or 50% 7942.5 * 0.503 = 3995 KVA 3995 + 505.26 = 4500.26 KVA
If Demand factor is 0.6 or 60% 7942.5 * 0.60 = 4765.5 KVA 4765.5 +505.26= 5270.76KVA
If Demand factor is 0.7 or 70% 7942.5 * 0.70 = 5559.75 KVA 5559.75+505.26=6065 KVA
If Demand factor is 0.8 or 80% 7942.5 * 0.80 = 6354 KVA 6354 + 505.26 = 6859.26 KVA
NOTE: The Recommended practice of considering Demand Factor in Pakistan is 0.8 or 80%.