Trans1 2020 05
Trans1 2020 05
Trans1 2020 05
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
DAMODAR VALLEY CORPORATION(DVC)
1 LILO of Mejia-Kalyaneswari at Burnpur S/S D/C 220 37 79 55 0 0
2 LILO of Parulia - Dtps at Durgapur steel TPS D/C 220 13 17 17 16 9 MAY-20 JUL-20
3 MTPS - Ramgarh (Bypassing Gola SS) S/C 220 207 681 678 670 191 OCT-20 OCT-20
4 MTPS- Ranchi (PG) (Bypassing Gola SS) S/C 220 228 778 775 752 152 OCT-20 OCT-20
5 Parulia - Burdwan line D/C 220 188 299 213 165 45 JUN-19 DEC-20
6 Ramgarh - Ranchi (PG) (Bypassing Gola SS) S/C 220 95 355 355 340 44 AUG-20 OCT-20
(Balance portion)
NHPC LIMITED(NHPC)
1 LILO of Lakhwar HEP- Muzaffarnagar at D/C 220 JAN-17
Vyasi HEP
POWERGRID (Consultancy Work)(PGCONSULTANCY)
1 (J&K) LILO of Leh - Kharu line S/C 66 16 97 55 16 1 MAY-17 MAY-17
10 Medinipur - Jeerat (New) (PM-JTL-TBCB) D/C 765 338 461 446 426 227 JUL-20 JUL-20
11 Ranchi - Medinipur line (PM-JTL-TBCB) D/C 765 538 717 717 708 518 OCT-20 JUL-20
18 Banaskantha PS - Banaskantha (PG) line D/C 400 132 183 183 183 122 DEC-19 JUN-20
24 Hiriyur - Mysore line (Ckt.-II) D/C 400 206 565 565 565 206 DEC-19 MAY-20
28 Jigmeling - Alipurdauar line (Q) (India Side) D/C 400 324 466 413 396 176 JAN-21 MAY-20
31 LILO of both Ckt. Kishanganj - Patna (Q) D/C 400 150 211 143 134 48 MAR-21 MAR-21
line Saharsa (ERSS XXITL - TBCB)
32 LILO of Both Ckt of Bawana - Mandola at D/C 400 116 89 79 73 68 MAY-17 JUN-20
Rajghat
40 LILO of North Trichur - Cochin line at North D/C 400 1 4 4 4 1 SEP-20 APR-20
Trichur HDVC Station (Q)
41 LILO of one circuit of Dulhasti - Kishenpur D/C 400
at Ratle HEP.
42 LILOof one Ckt. of Agra South-Fatehabad D/C 400 0
(765kV) D/C line at 400kV at Firozabad (J-
FTL-TBCB)
43 LILO of One Ckt of Bamnauli - Jhattikara at D/C 400 17 41 27 12 0 MAY-17 JUN-20
Dwarka-I
44 LILO of Sagardighi - Subhasgram line at S/C 400 2 8 6 5 0 FEB-20
Jeerat
45 LILO OUT of Teesta-III - Kishanganj at D/C 400 15 35 20 7 2 JUN-20 JUN-20
Rangpo
46 Lower Subhansiri - Biswanath Chariyali line D/C 400 335 444 329 228 64 AUG-13 MAR-22
-I
47 Lower Subhansiri - Biswanath Chariyali line D/C 400 348 465 327 196 35 AUG-13 MAR-22
-II
48 Mohindergarh - Bhiwani line D/C 400 122 181 152 81 8 OCT-20 JUL-20
49 New Neyveli TPP - Ariyalur (Villupuram) D/C 400 156 213 213 213 138 JUL-19 MAY-20
52 Pugalur HVDC - Arasur line (Q) D/C 400 118 162 142 134 23 JUN-20 MAY-20
54 Pugalur HVDC - Pugalur line (Q) D/C 400 100 138 138 138 100 JUN-20 MAY-20
55 Pugalur HVDC - Thiruvalam line (Q) D/C 400 780 1107 890 785 134 FEB-20 SEP-20
56 Rajarhat - Purnea (excl. Farakka-Gokarna D/C 400 645 1219 1218 1217 877 APR-16 MAR-20
portion)
59 Sitamarhi (New) - Motihari line (Triple D/C 400 187 229 215 200 103 MAR-21 JAN-21
Snowbird) (ERSS XXITL-TBCB)
60 Tehri Gen. - Tehri Pooling Station (Q) D/C 400 14 38 35 34 12 NOV-17 APR-20
63 Pugalur - North Trichur (Kerala) HVDC BIPOLE 320 364 406 314 276 10 APR-20 APR-20
Bipole Link
64 Chandigarh S/s - Panchkula (PG) (incl. 10 D/C 220 52 56 50 50 43 FEB-19 APR-20
KMs underground cable).
74 Pasighat - Roing line. S/C on 132 102 347 347 347 104 DEC-12 JUN-17
D/C
75 Re-conductoring of Agartala GBPP - D/C 132 16 0 0 0 16 MAY-18 FEB-18
Agartala (State) with HTLS conductor
76 Re-conductoring of Imphal (PG) - S/C 132 1 0 0 0 1 JUL-18 APR-18
Yurembam with HTLS conduuctor.
77 Roing - Tezu line S/C on 132 73 244 244 244 72 APR-12 JUN-17
D/C
78 Silchar - Hailakandi (Contingency D/C 132 60 110 110 110 60 NOV-17
arrangement)
79 Tezu - Namsai line. S/C on 132 96 332 332 332 95 DEC-12 JUL-18
D/C
80 Wardha - Aurangabad (on 1200 kV) D/C 1200 696 961 961 961 647 OCT-12 JUN-20
2 Agia-Sonapur (Hatchingmari) S/C line D/C S/C 132 103 387 363 284 0 NOV-19
tower
3 Amguri solar park - Mariani line (GEC-II) D/C 132 0 5 0 0 MAR-20
8 Kokrajhar - Bilashipara - Gauripur S/C on 132 63 203 203 203 63 SEP-13 NOV-19
D/C
9 Kukurmara - Azara line S/C on 132 5 29 29 29 6 DEC-11 NOV-19
D/C
10 Kukurmara(Mirza)-Boko S/C on 132 6 0 0 0
D/C
11 LILO of both ckt of Depota - Gohapur at 2xD/C 132 3 6 6 6 3 NOV-13 JUN-16
Sonabil S/S
12 LILO of Dhaligaon- Bornagar line at Barpeta D/C 132 24 96 63 33 0 APR-20
GSS (Package-A)
17 Sonapur - Jagirod line D/C 132 52 107 107 107 24 NOV-13 DEC-20
26 Raxaul (New) - Gopalganj (TM/ Single D/C 220 130 202 85 43 0 JUN-20
Zebra)
27 Saharsa (New) - Begusarai D/C 220 160 289 156 57 0 APR-20
31 Sitamarhi (New) - Raxaul (New) (Twin D/C 220 160 271 157 120 10 JUN-20
Moose)
32 Betia-Raxaul (2nd circuiting) D/C 132 0 0 0
6 Gurur - Kurud (Bangoli) D/C 220 74 118 118 118 72 JAN-21 JAN-21
11 Raita - Rakhi DCDS line on multi ckt tower D/C 220 140 0 0 0 MAR-22
12 LILO of Electric Lane to Park Street at Dev D/C 220 10 0 0 0 MAR-20 NOV-21
Nagar (U/G Cable)
18 LILO of one ckt of Bamnauli - Naraina Ckt-I S/C 220 2 2 2 0 MAR-15 NOV-17
at Pappankalan-I
19 LILO of Pragati - Sarita Vihar at D/C 220 1
Maharanibagh
20 Maszid Moth - Tughlakabad (U/G) Cable D/C 220 16 DEC-19 MAR-18
2 Amreli - Kasor line D/C 400 460 679 633 574 188 JUN-19
4 Bhachunda - Varsana line (Twin AL-59) D/C 400 280 499 199 172 0 JUN-20
7 Hadala - Shapar line (Twin AL-59) D/C 400 124 198 121 102 0 FEB-21 MAR-19
9 LILO of both ckt. Kakrapar - Vapi (PG) line D/C 400 80 MAR-22
at Chikhli S/s (Twin Moose)
10 LILO of Kasor-Amerli line at Fedra D/C 400 80 OCT-22
12 LILO of one ckt Halvad - Vadavi line at D/C 400 60 411 336 225 140 MAR-21
Chharodi S/s (ACSR Twin Moose)
13 LILO of one ckt Kosamba - Chorania at D/C 400 90 125 125 125 89 JUL-18
Chharodi (ACSR Twin Moose)
14 LILO of one ckt Kosamba-Chorania line at D/C 400 46 66 55 48 0 MAR-19
Fedra
15 LILO of one ckt. of planned Ukai - Kosamba D/C 400 120 MAR-22
line at new s/s near Chikhli
16 LILO of one ckt Wanakbori -Soja line at D/C 400 80 0 0 0 0 MAR-23
Prantji S/S
17 LILO of SSP- Asoj & SSP -Kasor lines at D/C 400 80 0 0 0 0 MAR-21
Achhalia S/S
18 Mundra (Adani) - Zerda line 1 D/C 400 640 997 453 275 0 JUN-19
21 Shapar - Pachham (Fedra) line (Twin AL-59) D/C 400 200 346 14 0 0 JUN-21
23 Soja-Zerda Line D/C 400 266 447 387 381 203 SEP-19 MAR-19
24 Vadinar(Essar)- Amreli (Balance) D/C 400 180 533 490 447 235 NOV-09 DEC-18
26 Wanakbori TPS-Soja D/C 400 212 343 272 271 144 DEC-19 MAR-19
30 BECL (Padva) - Botad line D/C 220 188 292 182 142 34 MAR-19
33 Bhatia - Kalavad line D/C 220 238 373 176 127 11 MAR-20
34 Bhogat - Moti Gop line (AL-59) D/C 220 140 251 89 76 0 MAR-19
35 Bhogat - Ranavav line (AL-59) D/C 220 150 248 99 71 0 JUN-19
39 Chorania - Salejada line (AL-59) D/C 220 135 240 144 131 26 FEB-19
40 Gavasad - Salejada line with AL-59 D/C 220 194 313 278 208 59 JUN-19 JUN-19
conductor
41 Hadala - Rajkot-II D/C 220 25 0 0 0 0 MAR-23
42 Halvad - Sadla line with AL-59 conductor D/C 220 76 124 101 101 59 MAY-19 MAR-19
44 Jambuva - Vadodara (765kV PGCIL) line D/C 220 68 131 50 43 0 JUN-19 JUN-19
with AL-59 Conductor
45 Jasdan - Gondal D/C 220 100 0 0 0 0 MAR-22
46 Kalavad - Kangasiali line D/C 220 112 191 177 159 64 DEC-20
61 LILO of Godhra -Kadana line at Lunawada D/C 220 5 223 223 214 80 DEC-18
62 LILO of Jamnagar - Jetpur line-I at Sikka D/C 220 116 178 0 0 0 MAR-21
81 LILO of Vadavi - Chhatral line at Santej S/s D/C 220 51 88 69 60 1 AUG-13 MAR-20
85 LILO of Vapi - Chikhli & Bhilad - Chikhli D/C 220 150 MAR-20
lines at Chikhli
86 LILO of Wanakbori TPS - Zalod line at D/C 220 270 MAR-22
Savdasna Muvada
87 LLO of 220 kv Vadavi - Chhatral line at D/C 220 43 74 69 60 0 MAR-14 MAR-20
Santej S/s
88 Mitha - kotasan D/C 220 33 SEP-19
89 Palanpur - Amarigadh (DFCC) line D/C 220 80 144 119 64 0 MAR-20 MAR-20
100 Termination of one Achhalia- Jambuva line D/C 220 70 130 124 124 44 SEP-18
at Jarod
101 Utran - Kosamba Line-II D/C 220 86 DEC-09
102 Vadavi - Sanand (DFCC) line D/C 220 61 108 61 45 0 APR-15 MAR-19
5 Essar (Latehar) - Latehar D/C 400 81 122 121 115 43 DEC-20 JUN-20
7 Latehar (JSUNL) - PTPS D/C 400 220 304 275 260 82 JUL-20 DEC-20
27 Chaibasa - Gua TL D/C 220 168 278 127 110 0 OCT-20 DEC-20
32 Chatra - Latehar D/C 220 208 340 340 335 206 MAR-20 MAY-20
33 Chatra - PBCMP (Barkagaon) D/C 220 117 185 129 83 0 DEC-20 JUN-20
36 Godda - Dumka line D/C 220 139 248 248 248 139 MAR-20
40 Jasidih - Dumkaa (Madanpur) D/C 220 148 239 239 239 148 MAR-20 JAN-20
41 Jasidih - Giridih line D/C 220 153 288 266 255 58 MAR-20 JUL-19
42 Koderma (JSEB) - Koderma(DVC) D/C 220 21 0 0 0
49 Link Line Daltonganj - Garhwa TL D/C 220 82 110 106 95 44 MAR-22 JUL-19
(Bhagodih END)
50 Mander - Tamar D/C 220 56 0 0 0
60 TTPS - Govindpur TL D/C 220 181 300 289 284 141 NOV-20 MAR-20
12 (PMDP - Kashmir) New Wanpoh - Mir Bazar D/C 220 10 14 7 0 SEP-20 OCT-20
line
13 Thein (RSD)-Hiranagar (2nd ckt) S/C 220 40 117 117 117 40 MAR-08 DEC-19
19 (PMDP - Jammu) Hiranagar - Kathua line D/C 132 152 0 0 0 MAR-19 DEC-19
(Reconductoring)
20 (PMDP - Jammu) LILO of Canal - Miran D/C 132 16 3 0 0 MAR-19 MAR-20
Sahib at Chatha
18 Chitradurga - Hiriyur S/S D/C 220 78 152 142 103 56 MAR-19 DEC-19
19 Devanhalli -(Hardware Park 2nd ckt) and M/C 220 113 0 0 MAR-20 SEP-19
Doddaballapura (2nd ckt)
20 Gulbarga - Afzalpur (Ganagapura) D/C 220 0 0 0 SEP-19 SEP-19
21 HDVC Kolar - T. Gollahali (Thimmasandra) D/C 220 54 162 143 84 13 AUG-20 DEC-19
line
27 Itagi - Kudligi (Badeladaku) line D/C 220 65 119 112 95 0 AUG-19 DEC-19
29 Jagalur (Hiremallanahole) - Kudligi D/C 220 83 159 159 159 83 JUL-19 APR-20
30 Jagalur (Hiremallanahole) - Kudligi line D/C 220 83 159 159 159 83 JUL-19 MAY-20
31 Kolar - Malur at Somanahalli D/C 220 180 280 271 267 146 MAR-18 DEC-19
32 Kothipura (Ramanagara) - Tubinakere D/C 220 142 290 290 290 142 JUN-09
33 Kudagi - Vajramatti line D/C 220 159 267 224 141 4 OCT-19 FEB-19
63 Tubinakere - Ramnagar (Kothipura) line D/C 220 142 290 290 290 142 JUN-09 MAY-20
3 Upgradation of 220kV S/C line from D/C 400 178 260 260 260 98 NOV-19
Madakkathar - Malaparambu line
4 Brahmapuram - Kaloor line D/C 220 23 16 14 13 4 APR-20 JUN-20
2 Jejuri - Hinjewadi - I and II D/C 400 207 277 204 187 70 MAR-20
14 Solapur (PG) - Narangwadi D/C 400 81 250 238 210 56 MAR-20 DEC-20
15 220 kV M/C LILO of one Ckt. of 220 kV M/C 220 117 117 64 0 0 DEC-19 DEC-21
Tarapur -Borivali and Boisar-Ghodbandar
line on M/C toweres at 400kV Kudus S/S
28 Deoli (PGCIL) - Yavatmal D/C 220 84 144 137 103 8 JUN-19 DEC-20
29 Dondaicha - Nandurbar D/C 220 80 MAR-23
31 Georai - Thapti Tanda s/s D/C 220 109 167 167 167 103 MAR-22 JUN-20
37 Koradi II - Butibori D/C on 220 106 189 133 117 22 MAR-11 MAR-20
M/C
38 Koradi-II - Uppalwadi UG and O/Hline D/C 220 15 13 4 0 0 DEC-20 FEB-21
39 Kumbhargaon (Nanded) - Kurunda D/C 220 121 224 148 94 0 FEB-21 DEC-20
51 LILO on 220 kV Deoli (PG) - Ghatodi line D/C 220 20 42 42 42 20 JUN-19 JUL-20
for 220kV Yavatmal
52 LILO on Babhaleshwar - Nashik at Sinnar D/C 220 20 MAR-20
66 LILO on two ckts Boisar (M) - Borivalli at D/C on 220 100 117 64 0 0 MAR-19 MAR-21
Kudus M/C
67 LILO on two ckts Boisar - borivalli at Boisar M/C 220 1 7 7 7 4 MAR-20 JUN-20
108 Vish Wind - Bhenda (GEC-I) D/C 132 0 140 106 75 2 MAR-21 NOV-20
5 Indore (PGCIL) - Ujjian (GEC-I) DCDS 400 91 130 126 121 78 NOV-20 MAR-20
14 Nagda - Ujjain line (GEC-I) D/C 400 53 152 152 150 61 SEP-20 FEB-20
19 Badod - Nalkheda (Susner ) (GEC) DCDS 220 104 169 158 132 13 DEC-20 JUN-20
26 Julwaniya - Kukshi line DCDS 220 126 200 148 95 17 MAR-21 MAR-20
36 LILO of one Ckt of Ashta- Dewas line at 220 DCDS 220 66 109 107 104 58 DEC-19 MAR-20
kV S/S Chapda S/S
37 LILO of one ckt of Bansagar (Tons) - Satna D/C 220 2
at Sirmour
38 LILO of one Ckt. of Bhopal - Hoshangabad D/C 220 6 0 0 0 6 JUN-20
at Adampur
39 LILO of one ckt of Bina - Gwalior at Datia D/C 220 10
46 Mandsaur (Sitamau) - Marut Shakti Pool DCDS 220 92 147 147 147 72 OCT-20 JUL-20
(GEC-I)
47 Morena - Malapur D/C 220 80
51 Rajgarh (B) - Nalkheda (GEC) D/C 220 144 209 169 96 MAR-20
54 Shujalpur - Narsinghgarh Line DCDS 220 51 170 170 170 51 JAN-21 MAR-20
56 Ujjain - Nalkheda (GEC) DCDS 220 160 252 181 132 25 FEB-21 JAN-21
4 Kesinga - Baliguda D/C 220 200 376 315 271 JUN-17 MAR-21
5 LILO of Balimela-Malkangiri at Gobindpalli S/C + 220 80 146 136 126 21 MAR-20 OCT-20
D/C
3 Bawktlang (Kolasib) S/S - Sihhmui S/S D/C 132 47 135 135 135 47 DEC-16
4 LILO of 2nd ckt of Tuirial-Aizwal at Kolasib D/C 132 105 0 0 0
26 Rudrapur - Srinagar line ( from srinagar to D/C 220 150 260 202 133 10 JUN-19 JUN-19
interconnection point of Singoli Bhatwari
HEP of M/s L and T
3 Suratgarh TPS - Babai ( Jhunjhunu) D/C 400 480 676 676 676 469 APR-19 JUN-20
4 Akal- Jaisalmer-2 line (GEC-I) D/C 220 112 195 190 174 47 NOV-20 AUG-20
5 Gajner - Chhatargarh line (GEC-I) D/C 220 167 297 280 268 118 JAN-21 AUG-20
6 GSS Basni (Jodhpur) - GSS NPH (U/C) D/C 220 3 18 18 13 1 JUN-20 DEC-20
Jodhpur
9 LILO of Jhalawar - Chhabra line at 220kV D/C 220 98 158 138 125 64 JUN-20
GSS Aklera
4 North Chennai PS - Ariyalur D/C 765 542 799 796 791 494 NOV-20 MAR-20
7 Ennore SEZ - North Chennai Pooling Station D/C 400 24 34 12 9 SEP-18 JUL-20
9 ETPS exp. - North Chennai Pooling Station D/C 400 24 106 27 19 SEP-18 MAR-19
20 Rasipalayam - Dharmapuri (Palavadi) D/C 400 390 564 560 556 309 JUN-17 MAR-20
52 LILO the existing 230 kV P.P Nallur - D/C 230 30 0 0 0 SEP-18 MAR-20
Thanjavur at proposed Narimanam 230 kV
SS
53 LILO the existing 230 kV P.P.Nallur - D/C 230 31 0 0 0 SEP-18 MAR-19
Thiruvarur at the proposed Narimanam 230
kV SS
54 Neyveli 230/110 kV SS to the existing D/C 230 18 14 14 14 6 SEP-18 MAR-19
Thiruvannamalai and Cuddalore feeders.
55 Neyveli - Kadalangudi line S/C 230 77 326 326 326 77 MAR-20 MAY-20
58 Palavady - Thirupathur line D/C 230 75 299 283 226 22 JUN-20 MAR-20
19 Vemagiri - Kamavarapukota D/C 400 185 268 226 202 80 MAR-20 JUN-21
25 Hindupur (400) - Pampanur Tanda (220) D/C 220 70 239 98 41 DEC-20 DEC-20
(GEC-I)
26 Hindupur - Penukonda D/C 220 253
29 Jammalamadugu - Chakrayapet D/C 220 172 296 283 281 164 JAN-15 NOV-18
30 Jammalamadugu - Porumamilla D/C 220 198 338 328 327 193 JAN-15 OCT-18
36 LILO of Both ckt Pulivendula - Hindupur at D/C 220 200 91 66 41 0 DEC-14 SEP-19
Gollapuram
37 LILO of Pendurthy - Garividi at Garividi D/C 220 140 202 29 0 0 MAR-20
53 Uravakonda - Kalyanduring D/C 220 100 160 147 137 42 NOV-14 OCT-19
7 Julurupadu - Kamalapuram LI TMDC line D/C 400 80 123 115 100 27 FEB-20
17 NTPC - Ramadugu (QMDC) line D/C 400 104 161 161 161 98 AUG-19 JAN-20
20 Sirichilla (NTPC) Common Point ) - D/C 400 171 492 492 492 347 FEB-19 JAN-20
Narsapur
21 Telangana STPP - Narsapur D/C 400 360 492 492 492 347 DEC-19 JAN-20
22 Telangana STPP - Ramadugu D/C 400 110 161 161 161 101 DEC-19 JAN-20
3 Anpara D - Unnao S/C 765 416 1225 1225 1214 406 APR-19 SEP-20
4 Ghatampur TPS-Agra line S/C 765 240 579 535 445 105 SEP-20
7 Ghatampur TPS-Hapur Line S/C 765 400 1052 811 624 95 MAR-21
14 Ghatampur TPS-Kanpur PG Line D/C 400 120 136 136 136 98 APR-21
15 Gonda - Shahjehanpur (PG) D/C 400 460 543 296 140 0
37 Tanda TPS Extn- Basti (Q) S/C 400 43 137 135 134 40 OCT-19 JUN-20
38 Varanasi (PG)-Jaunpur Line D/C 400 115 211 176 123 18 FEB-21
81 Bhadrekhi (Orai) - Jalaun line (GEC-II) S/C 132 0 103 101 60 4 SEP-20
82 Dakore (Solar plant) - Bhadrekhi (Orai) line D/C 132 0 105 105 105 70
(GEC-II)
83 Dumariaganj- - Utraula S/C 132 114 114 114 40
26 Subashgram (PG) - Baruipur D/C 220 64 126 125 123 49 NOV-20 APR-20
7 North Karanpura - Gaya line (NKTL - D/C 400 185 289 39 13 SEP-19 SEP-19
TBCB)
2 Latehar - Namkum D/C 400 216 320 293 274 132 AUG-16
2 Warangal (New) - Chilakaluripeta (WKTL - D/C 765 395 565 446 341 FEB-20 FEB-20
TBCB)
3 Warangal (New) - Hyderabad (WKTL - D/C 765 265 344 312 247 DEC-19 DEC-19
TBCB)
4 Warora (Pool) - Warangal (New) (WKTL - D/C 765 645 827 773 423 59 DEC-19 NOV-19
TBCB)
5 Babai (RRVPNL)- Bhiwani (PG) (NRSS- D/C 400 221 299 265 215 1 JUN-20 JUL-19
XXXVITL-TBCB)
6 Koteshwar (PS) - Rishikesh (HTLS) (NRSS- D/C 400 81 106 16 0 DEC-19 DEC-19
XXXVITL-TBCB)
9 Warangal (New) - Warangal (Existing) (Q) D/C 400 95 130 9 0 FEB-20 FEB-20
(WKTL - TBCB)
GATI INFRASTRUCTURE PRIVATE LIMITED(GIPL)
1 LILO of one circuit of Chujachen - Rangpo 2xS/C 220 10 MAY-18
line at Bhasmay
GMR ENERGY LIMITED(GMR ENERG)
1 LILO of Talchar -Meramundli at Kamalanga D/C 400 1 3 3 3 1 MAY-12
TPP
2 Alaknanda HEP - Joshimath D/C 220
5 Sipat/Korba (PS) Seoni (NKTL - TBCB) S/C 400 334 0 0 0 NOV-13 DEC-16
2 Mainpuri - Unnao (Quad) S/C 765 188 449 380 274 0 JUL-17
2 Khandwa Pool - Dhule (KTL - TBCB) D/C 765 379 492 476 474 350 MAY-20 JUL-20
4 Silchar (PG) - Misa (PG) (Q) line (NER-II D/C 400 357 487 471 406 187 JUL-20 JUL-20
TL-TBCB)
5 Surajmaninagar - P. K. Bari line (NER-II D/C 400 155 208 194 169 71 APR-20 JUL-20
TL-TBCB)
9 Biswanath Chariyalli (PG) - Itanagar (Zebra) D/C 132 134 211 161 145 45 MAR-20 JUL-20
line (NER-II TL-TBCB)
Remarks
12.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Yet to be awarded.
Commissioned 05/20.
Commissioned 04/20.
Shutdown awaited.
Charged on 31.08.2015.
ROW issues at many locations. change in scope of work due to
technical issues. (LILO to Barpeta GSS is from Dhaligaon-
Nalbari line, not from Dhaligaon-Barnagar line)
M/s BGCL
Related to BGCL
charged
M/s BGCL
M/s BGCL
Completed
Completed
M/s BGCL
M/s BGCL
M/s BGCL
M/s BGCL
M/s BGCL
Completed
completed
Completed
Completed
CL)
Work in progress.
land for substation not finalized
Work in progress.
"1) Both circuits i.e. Ckt.-I & Ckt.-II have been charged on
31.03.2020. "
Work completed
r)
Work almost completed except two spans of 700 m due to forest
clearance.
35% work completed
WIP
Yet to award.
WIP
WIP.
WIP.
Yet to award
WIP (Repeated)
WIP
WIP
Yet to award
Yet to award
Yet to award
Yet to award
WIP
WIP
WIP
Tender to be done
Tender to be done
Tender on website and last date is 10.12.2018. (Risk & cost for
Balance work).
Yet to award.
WIP.
Tender on website and last date is 17.12.2018. (Risk & cost for
Balance work).
WIP
WIP.
Yet to award
Yet to award
WIP
WIP .
Yet to award
Tender on website and last date is 17.12.2018. (Risk & cost for
Balance work).
Inter connection of Utran-Kosamba charged under stop gap
arrangement (Kosamba-Mota & Utran-Mota) on 16.06.2018 as
per system requirement.
WIP
Yet to award
Yet to award
Yet toaward
WIP.
Yet to award
WIP
Yet to be awarded.
yet to award
WIP
WIP
Yet to award
WIP
Yet to award
"Tender re-invited for balance work at Risk & Cost of Contractor
and last date of tender is 28.02.2018. Tender under acceptance."
Yet to award
Yet to award
Yet to award
WIP
Yet to award
Yet to award
WIP
WIP
WIP
Price Bid Opened & amp; under approval
Work in progress
work awarded to M/S Feeder and Work in progress.
CL)
Work in Progress
Line Commissioned
Work in Progress
Delay in FC.
power of kashang and other generating projects in vicinity was
planned to be pooled at Jangi pooling station, since other
generating projects have withdrawn LTA therefore the
construction of Jangi pooling station has been dropped for the
time being.
Delay FCA approval.
Work in Progress
Work is in Progress.
commissioned.
Slow progress.
Rerouting of line and ganglas s/s droped. Leh Army S/S shall be
connected with Leh S/S.
work under planning stage.
CC-I meeting held on 3rd and 4th of June 2019 and minutes of
meeting yet to be issued.
Out of 40 Kanals of land 20Kanals land has been acquired.
Preliminary works (soil testing and demarcation) are under
progress. Layout also approved.
LOA issued .
)
DPR approved. To be tendered
Contractor has stooped the work from March 2017 fue to ROW
issues. Notice issued to the agency. In meeting held on 31.07.19 at
Tumakuri Tz, agency requested for time extension and PV
approval to Zonal office and instructed agency to recommence the
work but agency is demanding for approval to recommence the
work.
220kV line passes through Balekatte minor forest area land
covering of 1.724 Hectares. Forest clearance for stage-1 proposal
resubmitted by attending, all the observations made by forest
officers. The proposal acepted by APCCF through online on
26.03.19. Hard copies of the proposal submitted by EE, MWND
to the DCF Ramangara on 05.04.19. The same has been forwarded
to RFO Magadi for verification on 25.04.2019. After Verification
by RFO Mogadi , reports submitted to DCF Ramanagar on
17.07.19. Verification is under progress.
Commissioned 04/20
Commissioned 05/20.
Malur-Kolar line charged (42 Ckm). Line from Malur end upto
Loc 137 charged (68.98 Ckm).Line from Somanahalli end upto
Loc 55 charged (23.64 Ckm). Total line charged 134.62 Ckm.
Work short closed and LOI issued on 15.09.2017 for balance
portion of work. Case pending in High Court: (i) Loc 84, 85, 86,
88 & 89: Case filed by KPTCL in DC Court on 27.01.2014 ,
LHD: 14.02.2017. Posted for orders. (ii) Loc 84, 85, 86 : Case
filed by party in Court of Civil Judge (Jr Dv), Anekal .LHD:
14.06.2018 . NHD:10.08.2018. (iii) Loc 88 & 89: Case filed by
KPTCL in DC Court Bangalore Urban District on 27.01.2014
LHD: 14.02.2017 posted for orders. (iv) Loc 88 & 89: Case filed
by party in Court of Junior Civil Judge, Bangalore Rural District
on 11.02.2014 . LHD: 10.01.2018. NHD: 11.07.2018
Commissioned 04/20
Commissioned on 14.09.2018.
Work completed
2.5.km old 110kV D/C line dismantling and RoW used for new
MCMV line. work under progress. Time extension issued. (RoW
issue at Brahmapuram Waste Disposal Plant).
Survey 19 Km completed
work started
Workcompleted
Work awarded to M/s. Sterlite Power Transmission Ltd on
10.11.2017. 400/220kV MCMV line 97.38 ckm and 220/110kV
MCVM line 20.20 ckm completed . Balance work in progress.
Work in progress.
Total length 21.05 ckm. Line partly test charged on 31.12.19 from
loc no 4 to 43.
Work in progress.
Work is stopped.
Work in progress.
Work in progress.
commissioned 03/16
Line cancelled.
L)
L)
Double Entry
double entry
Commissioned 05/20.
Double Entry
Double Entry
)
Delayed due to forest clearance issue
Commissioned 05/20.
O)
Concept Note is being submitted
L)
Contract awarded in 03 no. packages in Sep 2017. Forest proposal
had been submitted on dated 24.11.2018 for Package-I, on dated
23/10/2018 for Package-II and on dated 23/02/2019 for Package-
III. Stage-I clearance of forest case for Package I, II and III is
expected by Oct'19, Oct'19 and Nov'19 resp. Construction work of
line will be started after approval of stage-I clearance of forest.
Work has been awarded to Tata and route alignment & survey has
been completed. Line is passing through forest land and forest
proposal is under process.
Contract had been awarded to M/s Cobra but due to poor financial
condition of company, M/s Cobra had abandoned the
project.Fresh tendering in process for the project.
L)
W/O Issued to Moji Const. Jaipur vide no. 456 dt. 26.09.19 of CE
(Contract).
M)
Completed.
Yet to award
O)
All works completed.
Tender to be floated.
Work in progress.
Tender to be floated.
Tender to be floated.
Tender to be floated.
Work Completed.
Energised 0n 26.07.18
Work completed.
Commissioned 04/20.
Work completed.
Works are being executed in slow pace due to ROW issues and
due to limited working season (45 days only) at 137 Locations
9 Nos ROW.
Programmed to charged on March 2020
L)
Fund not yet tied up. Proposed under World Bank Financing
/SPA/NEC.
RoW issue
Work in progress.
To be deleted
Work in progress.
To be deleted
Work in progress.
Work in progress.
Work in progress.
Work is in progress.
Work in progress.
To be deleted.
To be deleted.
to be deleted
to be deleted
to be deleted
Work in progress.
Energised on 06/11/2017
Only the line is kept on hold as fund has not been made available
by UPNEDA. Solar Project sanction is yet to be finalised.
Baramwari Srinagar 220 kV D/C line and LILO of this line at
Singoli Bhatwari HEP are required for transfer of power from
Singoli Bhatwari HEP up to Srinagar pooling station.But after the
works of Phata Byung (2x38 MW) being severely affected due to
flash floods in June, 2013 and all works being stalled since July,
2017 due to Funds constraints with the developer , this Baramwari
switching station is not being constructed, therefore currently
above line is being constructed from 400kV S/s Srinagar to
interconnection point of 99MW Singoli Bhatwari HEP.This line is
of 150 Ckm out of which 72 Ckm stringing have been completed.
Also out of 220 tower locations, 210 fdns have been completed
and 182 towers have been erected
BSETCL)
Fresh order has been placed. work in progress
Forest : Nil
Interim arrangement.
RL)