6 - Master Production Schedule
6 - Master Production Schedule
6 - Master Production Schedule
1
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
2
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Detailed
Material
Capacity
Requirements
Planning
Planning (MRP)
Material and
Capacity Plans
Engine
Shop-floor Purchasing
Control Systems
Systems Back End
3
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Capacity constraints
Production plan
Master When to produce
Scheduling
Customer order How much to produce
4
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
5
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
6
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Master schedule
Production Plan
8
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
9
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Finished
product Finished
Finished product
product
10
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Vehicles
PLANNING
BILL
Body J
Interior C Transmissions G 0.30
Engine A 0.40 0.60
0.60 Body K
Interior D Transmissions H 0.30
0.30 0.25
Engine B Body L
0.40 Transmissions I 0.20
Interior E
0.20 0.15 Body M
0.10
Interior F
Body N
0.10
0.10
11
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
12
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
For the same situation given above (for the level strategy),
the MPS record, when chase strategy is followed, is given
13
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Week Number
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 20 20 20 20 20 20 20 20 20 20 20 20
MPS 5 5 5 5 5 5 15 15 15 15 15 15
On hand 20
Week Number
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 15 10 5 30 25 20 5 20 5 20 5 20
MPS 30 30 30 30
On hand 20
Fig. 9: MPS with Lot sizing
• Manufacturing in batches produces inventories that last
between production runs. This inventory is called cycle
stock.
Safety Stock in MPS
14
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Week Number
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 15 10 35 30 25 20 35 20 35 20 35 20
MPS 30 30 30 30
On hand 20 Safety stock = 5
Fig. 10: Modified MPS record considering safety stock
Rolling Through Time
• This helps to updates the record to reflects the actual
conditions
• It is necessary not only to construct the MPS but also to
process actual transactions and modify the MPS
• Consider the MPS record given in Fig. 9.
➢ The first week is over and the following changes
occurred: The actual sales were 10 units in the first
week instead of 5 units and a different forecast is
available for the next 12 weeks.
➢ The new forecast at the end of the first week is for 10
units per week for the next 5 weeks and 15 units per
week for the following 7 weeks (7 through 13).
➢ The new 12-week forecast incorporates 25 more units
than the original 12-week forecasts in the first five
weeks.
15
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Week Number
2 3 4 5 6 7 8 9 10 11 12 13
Forecast 10 10 10 10 10 15 15 15 15 15 15 15
Available 0 -10 10 0 -10 -25 -10 -25 -10 -25 -10 25
MPS 30 30 30 30
On hand 10
17
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Order Promising
• For many products, customers do not expect immediate
delivery, but place orders for future delivery
• The delivery date (promise date) is negotiated through a
cycle of order promising, where the customer either asks
when the order can be shipped or specifies a desired
shipment date
• If the company has a backlog of orders for future
shipments, the order promising task is to determine when
the shipment can be made
• The delivery date promise procedure is explained with an
MPS record of an item shown below
Week Number
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 15 10 5 30 25 20 5 20 5 20 5 20
MPS 30 30 30 30
On hand 20
Fig. 15: A typical MPS plan for ATP incorporation
19
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
ATP 10 30 30 30 30
MPS 30 30 30 30
On hand 20
Fig. 16: MPS record with ATP
• Suppose an order for 35 units was booked for week 10 in
the current period for the above item
• The ATP row changes as follows
Week Number
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Orders 5 3 2 35
Available 15 10 5 30 25 20 5 20 5 0 -15 0
ATP 10 30 25 0 30
MPS 30 30 30 30
On hand 20
Fig. 17: MPS Record with ATP showing ATP calculation
under subsequent period ATP deficiency
20
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
22
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
23
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
SunRay Series
Period 1 2 3 4
Forecast 4000 5000 2000 2000
Available 2000 -- 1000 2000
MPS 3000 3000 3000 3000
On-hand 3,000
24
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
StingRay Series
Period 1 2 3 4
Forecast 9000 10,000 6000 7000
Available -- -- -- --
MPS 4000 10,000 6000 7000
On-hand 5000
25
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
SunRay Series
Period 1 2 3 4
Forecast 4000 5000 2000 2000
Available 3000 1000 2000 1000
MPS 4000 3000 3000 1000
On-hand = 3,000
Lot Size = 3000
Ending inventory = 1000
StingRay Series
Period 1 2 3 4
Forecast 9000 10,000 6000 7000
Available 7000 4000 3000 3000
MPS 11,000 7,000 5000 7000
On-hand = 5000
Lot Size = 4000
Ending inventory = 3000
27
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Solution
(a)
Week
1 2 3 4 5 6 7 8
Forecast 20 20 20 30 30 30 30 30
Orders 25 15 12
Available 45 25 5 25 45 15 35 5
Available to promise 18 50 50 50
MPS 50 50 50 50
On hand = 20, MPS lot size = 50.
28
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
29
Master production scheduling
National Institute of Technology Calicut Department of Mechanical Engineering
Week
1 2 3 4 5 6 7 8
Forecast 20 20 20 30 30 30 30 30
Orders 25 15 12
Available 45 25 5 25 45 15 35 5
Available to promise 18 50 50 50
MPS 50 50 50
Scheduled receipt 50
Planned order release 50 50 50
30
Master production scheduling