Sediment Removal Technology
Sediment Removal Technology
Sediment Removal Technology
Presentation
www.sedicon.no
Sedicon and HDM JV in India
• Sedicon is a Norwegian Company established in 2001. Sedicon is the supplier
of sediment removal system.
• This JV has already achieved an order for supply of two units of Sedicon
Sluicers in a 6 MW small hydro power project in Himachal Pradesh.
SediCon Technologies and services
The unique principle of self-regulated, gravity powered sediment suction:
• Assessment of sediment
https://www.youtube.com/watch?v=4RK06KCODGo
Sedicon Dredge Agoyan Project
• The 200 000 m3 reservoir was more than 50% filled with sediments in Dec. 2011.
(Up to 8 meters of cohesive sediment, very rich in organic material)
• 12” SediCon Dredge connected to 600 mm bottom outlet pipe, with an efficient 75
kW water jetting system.
• More than 100 000 m3 (twice the expected
volume) was removed in 2012, long term
sediment removal capacity has exceeded 100
m3/hour
The project:
• Malana is a 86 MW run-of-river (ROR) hydropower plant utilising 600 m head on the
Malana River. It consist of head regulator, four desilting basins, a 249 000 m3 storage
reservoir, a 3.3 km long headrace tunnel with 7 % slope ending in an inclined surge
shaft.
The challenge:
• The power plant has since commissioning in 2001 suffered from abrasive sediments,
leading to severe turbine wear. The turbine wear is caused by the fine sediments
particles that pass the desilting basins and is temporarily trapped in the storage reservoir.
SediCon Dredging in Malana Project - India
The solution:
• SediCon supplied a SediCon Dredge, allowing sediment removal without input of power
of any kind, The Hydrosuction system utilises only excess water during monsoon, so no
water is lost for production.
The results:
• During two months in the summer of 2005, 36 000 m3 sediments were removed from the
storage reservoir and design capacity was more than verified. As sediments were
removed only during monsoon and when there is excess water, no water was taken from
production.
100 MW Pillur Dam – Tamil Nadu
• Bhavani River
• Reservoir Capacity – 44.40 M
Cubic Meter
• Current Capacity – 25.91 M Cubic
meter
• Sediment Deposit – 18.49 M Cubic
meter
• Dredging – proposed unit for 500
cubic meter of sediment removal
per hour
• Time period required to complete
the dredging is 4 to 10 years,
depends upon the number of
dredging unit and number of
operating hours.
The SediCon Sluicer: for desanders
• The available head between the sand • Can be designed for any capacity.
trap and the outlet is the driving force.
• Sediment up to 200 mm in diameter.
• Very low water consumption
• sediment deposits of any thickness
• No movable parts and extreme
reliability
2000, Nepal: SediCon Sluicers at
Khimti HPP pressurised sand trap
• 100 m3 tunnel sand trap in the headrace tunnel
https://www.youtube.com/watch?v=CA7WAiCB26I
SediCon Sluicer at 60 MW Khimti, Nepal
Illustration of the basins with Construction works for 8 basins, Outlet of bypass channel
SediCon Sluicers (red) each 150 m long and 13 m wide
SediCon Sluicers discharge
into bypass channel
SediCon Sluicers for 6 MW Baner Sangam, India
• Location: Baner River, Kangra, Himachal
Pradesh
• 6 MW: Head 42 meter, Discharge 17 Cumecs
• Client: Yogindera Powers Pvt Ltd
• Two SediCon Sluicer Units, one basin
• 940 ton/hour removal capacity Excavated Desilting Basin
• No movable parts, designed for 50 years life.
• Supply mid 2015