Pmu Bayan Lepas Splliting Bus Bar 275/132kV TNBT 867/2006: Trans
Pmu Bayan Lepas Splliting Bus Bar 275/132kV TNBT 867/2006: Trans
Pmu Bayan Lepas Splliting Bus Bar 275/132kV TNBT 867/2006: Trans
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
1
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
2
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
2) Switches Isolation
1. E01 LCP Supervisory panel need to change into LOCAL mode and Panel
to be lock
lock
3.Testing
1.Terminate both end cable, in order to terminate the supply cable the
insulation test need to be carried out to ensure each phase of cable are in
good condition(in order to void phase shorting, leakage)
3
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
2. For earthing continuity, since the new building is new the complete earthing
system has been install and tested no testing require, we need to ensure all
the connection is secure with tester test result in hand.
4) Personals involve
1. Site Supervisor.
2. Electrician/General workers.
3. Electrical Chargeman /HT
4. Jointer
4
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
5) Machinery/Equipment/Material
5
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No
6
Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
Owner Tenaga Nasional Berhad
Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV
Trans grid
Doc.
Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No