Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Pmu Bayan Lepas Splliting Bus Bar 275/132kV TNBT 867/2006: Trans

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7

  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation

    Owner Tenaga Nasional Berhad


    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

PMU BAYAN LEPAS SPLLITING BUS BAR


275/132kV
TNBT 867/2006

1
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

METHOD OF STATEMENT FOR


132kV Interconnector Sealing End (Bay E01) at Hyundai GIS work PMU Bayan
Lepas
 
 
 
1)  Work SCOPE
 
1. Degassing work for E01 Power Cable Compartment
2. To removed the E01 132kV(cable box) GIS compartment(132kV
Interconnector Bay)
3. To adjust the RYB phase of sealing end into correct position.
4. Placed the GIS compartment (cable box) and begin with docking process.
5. Re route the 120 Sqmm power cable for suitable bending radius before
docking works.
6. Vacuuming works after completion of sealing end installation.
7. Fill up the SF6 gas for Bay E01 cable box compartment.
8. Cable testing including Insulation, shield and phasing testing.

2
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

2) Switches Isolation

1. E01 LCP Supervisory panel need to change into LOCAL mode and Panel

to be lock

2. 801A Earth Switch needs to put on Close position and switches to be

lock

3. Q8 must be close position and lock

3.Testing

1.Terminate both end cable, in order to terminate the supply cable the
insulation test need to be carried out to ensure each phase of cable are in
good condition(in order to void phase shorting, leakage)

3
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

2. For earthing continuity, since the new building is new the complete earthing
system has been install and tested no testing require, we need to ensure all
the connection is secure with tester test result in hand.

3.The IR Test -The majority of utilities, including competent engineer, hire


consultants to conduct such tests because interpretation of results requires
both advanced training and skills generally not available in-house. The
necessary equipment for XLPE testing is also generally not available in-house.
But now by using the Insulation Tester Unit select Voltage into 1kV for the
mean time place the prop ground and other prop to Power Cable amour
sheath.

Competent Chargeman shall maintain testing by injecting the 1kV Voltage


within 1 minute time durations.

4) Personals involve

1. Site Supervisor.
2. Electrician/General workers.
3. Electrical Chargeman /HT
4. Jointer

 
 

4
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

5) Machinery/Equipment/Material

1. Chain block and Cable Jack


2. Insulation and Resistance Test Meter.
3. Phase rotation test meter.

5
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

6
  Project BAYAN LEPAS SPLLITING BUS BAR 132/275Kv Substation
    Owner Tenaga Nasional Berhad
    Main Contractor System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV.
 
  Contractor's Consultant System Protection Sdn.Bhd and Transgrid Ventures Sdn Bhd-JV

Trans grid
Doc.
      Document Title Works Method Statement BPLS-E-WMS-02 REV-00
No

You might also like