Criticalities in High Pressure Cryogenic Test Facilities: Riticalities and Olutions Dopted
Criticalities in High Pressure Cryogenic Test Facilities: Riticalities and Olutions Dopted
Criticalities in High Pressure Cryogenic Test Facilities: Riticalities and Olutions Dopted
Facilities
A.S.Ramasubramanian1, S. Antony Manicka Raja2, V.Michael Packiaraja3
TCT/CTTF/CSSTF/TSE/IPRC, Mahendragiri
s_rama@iprc.gov.in1,antony1985@iprc.gov.in2, michael@iprc.space.gov.in3
2
Fig. 4: Super insulated SI pipeline routing from high
pressure cryogenic run tank to thrust chamber interface.
3
sequence for the operations. Hence, a closed loop control for pipeline pressure at the inlet to aid in closing the valve and
the process (tank pressure) was achieved by Controller with thus better leak tightness. But to avoid oversized actuators to
Proportional, Integral and Derivative terms acting on the overcome this pressure aided valve closure configuration a
error signal.(Set point-actual pressure) .The control valve pilot plug inside the main plug is configured which reduces
opening was adjusted based on the error signal between the the differential pressure across main plug, thus enabling
set point and the tank pressure. opening of valve with lesser actuator thrust.
Based on mathematically arrived PID constants, trials The body bonnet flange joints of electro-pneumatic
were conducted to further fine tune the constants based on isolation and control valves were selected to be twin seal
the system and process behavior. Final sequence used for with inter-seal venting option. The vent cavity of the inter-
tank pressurization was seal space was maintained with helium purge to prevent
Time period Run tank pressure ingress of moisture during test at high pressures, if there was
T0- 00:00:30 to T0- 00:00:25 0.5 to 10 MPa no leak.
T0- 00:00:25 to T0- 00:00:20 10 to 12.9 MPa
T0- 00:00:20 to T0- 00:00:15 12.9 to 14.5 MPa The DN150 flange joints were used to reposition a pipe
T0- 00:00:15- T0+50s 14.5 MPa±0.3 MPa spool to divert propellant service between sea-level and high
altitude simulation test bay. The flange and seal
With fine tuned PID constants, a typical tank configuration of these joints were selected to be wedge type
pressurization plot is given in the figure below. seal with malleable indium based seal material. These seals
expand against the walls and offer better leak tightness at
high pressure.
III. SUMMARY
The procedures and the component selections detailed in
this document were implemented in the thrust chamber test
facility to qualify the CE20 thrust chamber successfully.
ACKNOWLEDGMENT
We would like to thank the management of IPRC,
Mahendragiri for giving us the freedom, guidance and
wisdom to overcome the different challenges encountered
during the realization and operation of high pressure
cryogenic test facility.
REFERENCES
[1] Anand Kumar Parsai et. Al. , “Modeling and Simulation of High
Pressure Cryogenic Process for Optimum Closed Loop Control,”
D. Selection of Flow Components for High pressure 2015 International Conference on Industrial Instrumentation and
applications Control (ICIC), DOI: 10.1109/IIC.2015.7150980, July 2015
The flow components had to be selected with special [2] A. Narayanan et al on “Design of Fluid Sytems for Thrust chamber
features for application in high pressure service. The test facility” Report No:LPSC/LMF/CTF/TR/123/2003 (controlled
document), March 2003
electro-pneumatic valves for isolation in DN150 pipeline
[3] D.H. Liebenberg, J.K. Novak, F.J. Edeskuty on “Cooldown of
were flow to close type valve with a pilot plug within main Cryogenic Transfer Systems” AIAA Paper No. 67-475, August 2012
plug configuration. Flow to close type configuration enables