Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Yet-Agru-Exe-Meb-000-Cmm-Prc-0001 Comm & Start Up Philosophy

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Doc No:

YET-AGRU-EXE-MEB-000-
CMM-PRC-0001

Revision: A

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION,


INSTALLATION & COMMISSIONING (EPCIC) FOR YETAGUN ACID GAS Page: 1 of 6
REMOVAL UNIT (AGRU) PROJECT

PROJECT TITLE : PROVISION OF ENGINEERING,


PROCUREMENT, CONSTRUCTION,
INSTALLATION & COMMISSIONING
(EPCIC) FOR YETAGUN ACID GAS
REMOVAL UNIT (AGRU) PROJECT

OWNER : PETRONAS CARIGALI MYANMAR (HONG


KONG) LIMITED

CONTRACT NO. : A/PCML/C/18/004

DOCUMENT : COMMISSIONING & START UP


TITLE PHILOSOPHY

DOCUMENT
REVIEW : Z
CLASSFICATION

9 July
A Issued for Review RY RR
2019
Prep’d App’d Rev’d Endorsed App’d
Rev’d By
By By By By By
Rev Date Description
MEB PCML

© 2017 PETROLIAM NASIONAL BERHAD (PETRONAS). All rights reserved. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording
or otherwise) without the permission of the copyright OWNER.

COMMISSIONING & START UP PHILOSOPHY


Doc No:
YET-AGRU-EXE-MEB-000-
CMM-PRC-0001

Revision: A

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION,


INSTALLATION & COMMISSIONING (EPCIC) FOR YETAGUN ACID GAS Page: 2 of 6
REMOVAL UNIT (AGRU) PROJECT

AMENDMENT SUMMARY
This sheet must be completed in detail at each revision once this document has been approved.
Details must include revision number, description and indication of which pages and paragraphs
have been revised, date of revision approval, approvers’ title and signature.

Rev Description Date Approver Title Name

A Issued for Review 9-07-2019 Project Manager

Notes
:
(1) Document Holders to update Amendment Record as and when amendments/new
revisions are received.
(2) For description of amendment the Document Holder should indicate correction,
modification, and update or deletion issue.
(3) Document Holder to enter their company reference number, sign and date the
record of entry.
(4) Where part amendments are issued, the relevant page(s) will be identified with a
lower-case letter in the revision status line in the header.

COMMISSIONING & START UP PHILOSOPHY


Doc No:
YET-AGRU-EXE-MEB-000-
CMM-PRC-0001

Revision: A

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION,


INSTALLATION & COMMISSIONING (EPCIC) FOR YETAGUN ACID GAS Page: 3 of 6
REMOVAL UNIT (AGRU) PROJECT

TABLE OF C0NTENT
1.0 INTRODUCTION.....................................................................................................4
1.1 PROJECT OVERVIEW..............................................................................................4
1.2 OBJECTIVE ...........................................................................................................5
2.0 SCOPE ...........................................................................................................5
3.0 DEFINITIONS........................................................................................................... 5
4.0 ABBREVIATIONS....................................................................................................6
5.0 APPENDIX ...........................................................................................................6

COMMISSIONING & START UP PHILOSOPHY


1.0 INTRODUCTION

1.1 PROJECT OVERVIEW


The Yetagun Field (Yetagun Main) is located in Andaman Sea, offshore of Myanmar in
Blocks M12, M13 and M14. PC Myanmar (Hong Kong) Limited (COMPANY) assumed
operatorship of the blocks on 12 September 2004. The participating interest in the
blocks is PCSB, MOGE, Nippon Oil and PTTEP.
Yetagun Main consists of 4 platforms namely, Yetagun A Wellhead platform, Yetagun
B Central Processing Platform and Living Quarters, Yetagun C Booster Compressor
Platform and Yetagun D Remote Wellhead Platform. Yetagun A, B and C is bridge-
linked. Sales gas is exported via 24-inch pipeline from Yetagun A to onshore Pipeline
Operating Centre (POC).
Stabilized Condensate is exported via 6-inch pipeline to Floating Offloading (FSO)
from Yetagun A. Full Well Stream (FWS) from Yetagun D is transported via 10-inch
pipeline to Yetagun C.
Yetagun Main is currently operating with Low Pressure (LP) Mode whereby limiting
the FWS from Yetagun-D to maximum 55 MMSCFD instead of 70 MMSCFD Pipeline
capacity due to high CO2 from Yetagun D.
The high CO2 gas with 34 mole% from Yetagun-D is blended with lean gas from
Yetagun Main to meet Gas Sales Agreement (GSA) requirement of less than 15 mole
% CO2 and GHV to be 950 - 1050 Btu/scf. However, Yetagun-A production has been
declining rapidly. This has resulted Yetagun-D gas production to be curtailed down in
order to meet the 15 mole% CO2, hence, lowering the potential of high Recovery
Factor (RF).
In order to maintain the overall production rate, COMPANY intends to install Acid Gas
Removal Unit (AGRU) at Yetagun-C to remove the CO2 from the Yetagun-D gas. The
product gas from AGRU (i.e. the Yetagun-D gas with CO2 content less than 15 mole
%) will be commingled with the low CO2 gas from Yetagun Main and send to gas
treating and conditioning system at Yetagun B prior to export.
As of June 2018, average production from Yetagun Main is 130 MMscfd whereas
Yetagun North is 30 MMscfd. Yetagun field is currently producing at average 160
MMscfd of gas and 3.3 kbd of condensate.
Field development activities which were executed at Yetagun facilities during the
different phases are described as below.
Phase 1: Installation of 20-slot wellhead platform (Yetagun-A), production platform
(Yetagun-B), and Floating Storage & Offtake (FSO) Vessel, with Daily Contract
Quantity (DCQ) of 200 MMSCFD of gas and 5400 BPD of associated condensate.
Phase 2: Capacity up gradation of the DCQ from 200 MMSCFD to 260 MMSCFD from
1st October 2002.
Phase 3: Facility Modifications to increase the production capacity to 400 MMSCFD
DCQ capacity from 1 April 2004.
Phase 4: Drilling of 4 new wells in 2008 and installation of Booster Compression
Platform in 2011/2012
Phase 5: Installation of 4- legged satellite wellhead platform (Yetagun-D) in
2014 with additional production of 70 MMSCFD.
Phase 6: Infill drilling of 3 new wells at Yetagun-A platform in 2015 and
upgrading of Yetagun-A with full SIPROD capability
Phase 7: Infill Drilling of 2 infill wells and 1 basement well at existing Yetagun-A
platform to increase production rate
Phase 8: Facility modification and Installation of Acid Gas Removal Unit, AGRU at
Yetagun- C Platform and tie-in at Yetagun-B platform

COMMISSIONING & START UP PHILOSOPHY


1.2 OBJECTIVE
The objective of this document is to provide the overall overview of the
commissioning and start up sequence based on specific system priority for the
Yetagun’s Acid Gas Removal Unit (AGRU) Project.

2.0 SCOPE

This document is applicable for Yetagun’s Acid Gas Removal Unit (AGRU) Project and
shall be referred in order to:
1. Identify the specific System and/or Equipment priority for the project
commissioning and start up;
2. To define the Commissioning and Start-Up flow/sequences to be followed by
CONTRACTOR in order to achieve smooth facility start up.
All works activities that required to be performed by CONTRACTOR during Testing,
Commissioning and Start Up executions are in accordance with CSP-20: Testing, Pre-
commissioning and Commissioning Guideline. Detailed activities such as scope of works,
vendor support and pre-commissioning and commissioning tasks shall be elaborated
further in each system detail procedure.

3.0 DEFINITIONS
COMPANY : PETRONAS CARIGALI MYANMAR (HONGKONG) LTD.
(PCML)
[The party who initiates the project and is ultimately
responsible for the funding of the project]

CONTRACTOR : MUHIBBAH ENGINEERING BHD. (MEB)


[The party who carries out EPCC for the project]

HUC SUB-CONTRACTOR : TRANSFAME SDN. BHD. (TRANSFAME)


[The party who sub-contracted by CONTRACTOR to
carry out the onshore pre-commissioning and offshore
HUC scope for the project]

VENDOR : Party who supplies and manufactures equipment/


materials or services specified and ordered by
CONTRACTOR

SUBCONTRACTOR : Party who providing subcontracting packages or


services specified and ordered by CONTRACTOR

4.0 ABBREVIATIONS

AGRU : Acid Gas Removal Unit


CMS : Completion Management System
CSP : Carigali Standard Procedure
DMCC : Discipline Mechanical Completion Certificate
FAT : Factory Acceptance Test
FSO : Floating, Storage & Offloading
HUC : Hoop-Up and Commissioning
HSSE : Health, Safety, Security and Environment
ITR : Inspection Test Record
JHA : Job Hazard Analysis
MEB : Muhibbah Engineering Berhad
PCML : Petronas Carigali Myanmar Ltd
PCSB : Petronas Carigali Sdn Bhd
PSV : Process Safety Valve

COMMISSIONING & START UP PHILOSOPHY


PTR : Performance Test Run
PTW : Permit to Work
RFC : Ready for Commissioning
SAT : Site Acceptance Test

5.0 APPENDIX

 Appendix I: Commissioning and Start Up Sequence

COMMISSIONING & START UP PHILOSOPHY

You might also like