Yet-Agru-Exe-Meb-000-Cmm-Prc-0001 Comm & Start Up Philosophy
Yet-Agru-Exe-Meb-000-Cmm-Prc-0001 Comm & Start Up Philosophy
Yet-Agru-Exe-Meb-000-Cmm-Prc-0001 Comm & Start Up Philosophy
YET-AGRU-EXE-MEB-000-
CMM-PRC-0001
Revision: A
DOCUMENT
REVIEW : Z
CLASSFICATION
9 July
A Issued for Review RY RR
2019
Prep’d App’d Rev’d Endorsed App’d
Rev’d By
By By By By By
Rev Date Description
MEB PCML
© 2017 PETROLIAM NASIONAL BERHAD (PETRONAS). All rights reserved. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording
or otherwise) without the permission of the copyright OWNER.
Revision: A
AMENDMENT SUMMARY
This sheet must be completed in detail at each revision once this document has been approved.
Details must include revision number, description and indication of which pages and paragraphs
have been revised, date of revision approval, approvers’ title and signature.
Notes
:
(1) Document Holders to update Amendment Record as and when amendments/new
revisions are received.
(2) For description of amendment the Document Holder should indicate correction,
modification, and update or deletion issue.
(3) Document Holder to enter their company reference number, sign and date the
record of entry.
(4) Where part amendments are issued, the relevant page(s) will be identified with a
lower-case letter in the revision status line in the header.
Revision: A
TABLE OF C0NTENT
1.0 INTRODUCTION.....................................................................................................4
1.1 PROJECT OVERVIEW..............................................................................................4
1.2 OBJECTIVE ...........................................................................................................5
2.0 SCOPE ...........................................................................................................5
3.0 DEFINITIONS........................................................................................................... 5
4.0 ABBREVIATIONS....................................................................................................6
5.0 APPENDIX ...........................................................................................................6
2.0 SCOPE
This document is applicable for Yetagun’s Acid Gas Removal Unit (AGRU) Project and
shall be referred in order to:
1. Identify the specific System and/or Equipment priority for the project
commissioning and start up;
2. To define the Commissioning and Start-Up flow/sequences to be followed by
CONTRACTOR in order to achieve smooth facility start up.
All works activities that required to be performed by CONTRACTOR during Testing,
Commissioning and Start Up executions are in accordance with CSP-20: Testing, Pre-
commissioning and Commissioning Guideline. Detailed activities such as scope of works,
vendor support and pre-commissioning and commissioning tasks shall be elaborated
further in each system detail procedure.
3.0 DEFINITIONS
COMPANY : PETRONAS CARIGALI MYANMAR (HONGKONG) LTD.
(PCML)
[The party who initiates the project and is ultimately
responsible for the funding of the project]
4.0 ABBREVIATIONS
5.0 APPENDIX