Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ITR For Electrical Instrument PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4
At a glance
Powered by AI
The documents describe checklists for inspecting and testing various electrical and mechanical systems.

Instrument air supply piping/tubing, cabling and wiring, electrical motors, and electrical panels are being checked and tested.

Visual inspections, continuity tests, insulation resistance tests, and other parameter measurements are recorded for each check along with inspection dates, inspected by details, and remarks.

CHECK AND TEST INSTRUMENT AIR SUPPLY PIPING/TUBING

Project Title :
Company : Date :
Contractor : Report No :
Sub-Contractor : Page of

RESULT INSPECTED BY
INSPECTION
No. TAG No. VISUAL INSPECTION SUB- REMARKS
BLOW TEST LEAK TEST DATE KPMOG
CONTRACTOR

REMARKS :

Prepared by, Witnessed/Reviewed by, Witnessed/Reviewed by

Print name Date Print name Date Print name Date


CHECK AND TEST CABLING AND WIRING
Project Title :
Company : Date :
Contractor : Report No :
Sub-Contractor : Page of

VISUAL INSULATION RESISTANCE TEST (MΩ) INSPECTED BY


INSPECTION
No. TAG NO. CONTINUITY REMARKS
INSPECTION DATE
CORE TO CORE TO SUB-
RESULT KPMOG
CORE EARTH CONTRACTOR

REMARKS :

Prepared by, Witnessed/Reviewed by, Witnessed/Reviewed by

Print name Date Print name Date Print name Date


CHECK AND TEST ELECTRICAL MOTORS
Project Title :
Company : Date :
Contractor : Report No :
Sub-Contractor : Page of

REFERENCES
Drawing No. Location
Revision Equipment ID
Sheet System No.

Approval
No. Description of Checks Remarks
Sub-Con KPMOG CPGL
Verify that the name plate date included area clarification is correct as
1 per drawings
2 Verify that installation location and orientation is as per drawings
Verify that the motor rotor turns easily by hand and there is no friction or
3 binding
Verify that the bolting and weatherproofing of the terminal box are
completed and
4 tight. the terminal connections and control cable connections are correct
and tight.
5 Check that the enclosure seals and gaskets of terminal boxes are intact.
6 Verify that the glands and plugs are complete and tight with accessory.
7 Verify the continuity of equipment earthing connection.
Verify that the local control station included control wire is properly
8 installed with
Perform the insulation resistance test of motor winding with cable
9
RYB – E: _______________MΩ
Perform the insulation resistance test of space heater with cable
10
L – E: _______________MΩ
11
Perform the polarization index test of motor (Applicable for MV Motor
Only)
Applicable / Not Applicable

RST — E: Min (10 minutes test)

RST-E:

COMMENT

Prepared by, Witnessed/Reviewed by, Witnessed/Reviewed by

Print name Date Print name Date Print name Date


CHECK AND TEST FOR PANEL
Project Title :
Company : Date :
Contractor : Report No :
Sub-Contractor : Page of

REFERENCES
Drawing No. Location
Revision Equipment ID
Sheet System No.

Approval
No. Description of Checks Remarks
Sub-Con KPMOG CPGL
1 Check that the control panel has no mechanical damage.
2 Check that the board assembly, bolting, orientation, alignment and
leveling are satisfactory.
3 Check the safety features are satisfactory.
4 Check the nameplate details.
5 Check the components of panel are correct.
6 Check the close and open operation of mcb’s by hand.
7 Check and continuity test of earthing connection to main grid
system.
8 Verify the equipment has been thoroughly cleaned.
9 Perform the insulation resistance test

(Applied voltage is 500 V Line to earth : MOhm

(Acceptance criteria is above 1.0 mohm)

COMMENT :

Prepared by, Witnessed/Reviewed by, Witnessed/Reviewed by

Print name Date Print name Date Print name Date

You might also like