ITR For Electrical Instrument PDF
ITR For Electrical Instrument PDF
ITR For Electrical Instrument PDF
Project Title :
Company : Date :
Contractor : Report No :
Sub-Contractor : Page of
RESULT INSPECTED BY
INSPECTION
No. TAG No. VISUAL INSPECTION SUB- REMARKS
BLOW TEST LEAK TEST DATE KPMOG
CONTRACTOR
REMARKS :
REMARKS :
REFERENCES
Drawing No. Location
Revision Equipment ID
Sheet System No.
Approval
No. Description of Checks Remarks
Sub-Con KPMOG CPGL
Verify that the name plate date included area clarification is correct as
1 per drawings
2 Verify that installation location and orientation is as per drawings
Verify that the motor rotor turns easily by hand and there is no friction or
3 binding
Verify that the bolting and weatherproofing of the terminal box are
completed and
4 tight. the terminal connections and control cable connections are correct
and tight.
5 Check that the enclosure seals and gaskets of terminal boxes are intact.
6 Verify that the glands and plugs are complete and tight with accessory.
7 Verify the continuity of equipment earthing connection.
Verify that the local control station included control wire is properly
8 installed with
Perform the insulation resistance test of motor winding with cable
9
RYB – E: _______________MΩ
Perform the insulation resistance test of space heater with cable
10
L – E: _______________MΩ
11
Perform the polarization index test of motor (Applicable for MV Motor
Only)
Applicable / Not Applicable
RST-E:
COMMENT
REFERENCES
Drawing No. Location
Revision Equipment ID
Sheet System No.
Approval
No. Description of Checks Remarks
Sub-Con KPMOG CPGL
1 Check that the control panel has no mechanical damage.
2 Check that the board assembly, bolting, orientation, alignment and
leveling are satisfactory.
3 Check the safety features are satisfactory.
4 Check the nameplate details.
5 Check the components of panel are correct.
6 Check the close and open operation of mcb’s by hand.
7 Check and continuity test of earthing connection to main grid
system.
8 Verify the equipment has been thoroughly cleaned.
9 Perform the insulation resistance test
COMMENT :