1 Design of Irrigation Water Conveyance and Control Systems
1 Design of Irrigation Water Conveyance and Control Systems
SYSTEMS
1.1. Introduction
Water for irrigation is conveyed from its source to the field by means of canals or channels
and pipe. A channel or lateral is needed as an integral part of an irrigation water conveyance
system. In an open channel, water flows at atmospheric pressure under the force of gravity. In
most cases, a gentle slope is provided in the open channel to facilitate this flow. The words
Canal and channel are interchangeably used in the literature. Basically, canal is artificially
constructed (man-made), and channel is a natural water passage. A hydraulic engineer is
concerned with the design, construction, operation, maintenance, and improvement of such
channels.
The conveyance efficiency in irrigation projects is poor due to seepage, percolation, cracking,
and damaging of the earth channel. Seepage loss in irrigation water conveyance system is
very significant, as it forms the major portion of the water loss in the irrigation system.
Irrigation conveyance losses controlled through lining may reduce the drainage requirement and
also enhance irrigation efficiency. As such, reliable estimates of quantities and extent of
seepage losses from canals under pre-and post lining conditions become important.
Irrigation efficiency is greatly dependent on the type and design of water conveyance and
distribution systems. Designing of economic cross-sections of various types of irrigation channels
is important to minimize cost, water loss, and land requirement.
Irrigation canals should be designed to meet the varying irrigation requirements at farm level.
The design of irrigation canals is based on the following criteria:
1. Capacity. The capacity of irrigation canals is determined by the water delivery method
which describes how irrigation requirements are delivered in time and place in the
irrigation system. Delivery methods differ from each other with the scheduling of the
water demands. The World Band (1986) classifies the water delivery schedules as:
On demand: Water delivery reacts instantaneously to the water demand;
Continuous: the irrigation canals supply a varying or constant continuous flow
during the whole irrigation season;
In storage irrigation scheme, a dam is constructed across the river, thus forming a reservoir
on the upstream side of the river. The water from this reservoir is taken into the main canal
through the outlet sluices. It is, however, not at all necessary that the main canals take-off
from the reservoir, and in fact, they rarely do so. In most storage schemes, canals usually
take-off from a pick up weir or a barrage, located downstream of the reservoir. The
requirement of the construction of such a pick up head works may become necessary when
the irrigation command area is far away from the dam site.
Figure 3. Arrangement of main canal off-take from the reservoir and pick up weir
1.4. Terminology
Gross Command Area (GCA). It is the total area, bounded within the irrigation boundary of
a project which can be economically irrigated without considering the limitation of the
quantity of available water.
Cultivable Command Area (CCA). It is all land of CGA on which cultivation is possible.
Non-Cultivable Command Area (NCCA). It is part of the gross command area which
includes residential areas, ponds, reserves forest, cemetery, etc.
Irrigation Engineering Lecture Notes Tesfaye B.
4
Intensity of irrigation. The percentage of CCA proposed to be irrigated in a given year is
called the intensity of irrigation of that year.
Time factor of distributary. It is the ratio of the actual operating period of a distributary to
the crop period.
1. The Rabi Crops. Crops which require water from December to April.
2. The Kharif crops. Crops which requires water from December to November.
3. Perennial crops. Crops requiring water through the year. E.g. Sugar cane and Garden
Crops.
The canal may be designed for a capacity equal to the greater of the water requirement of
Rabi and Perennial crops or Kharif crops and perennial crops. Kor-watering is water required
by the crop at its peak demand. The depth of water required during kor-period is known as
kor-depth. The most important point which must be kept in mind while fixing the channel
capacity is to take into considers the keenest demand of the crop and not the average
demand.
864𝐵𝑘𝑜𝑟𝑝𝑒𝑟𝑖𝑜𝑑
𝐷= (4.1)
∆𝑘𝑜𝑟𝑑𝑒𝑝𝑡
𝐴
𝑄= (4.2)
𝐷
Where 𝐷 = Duty of water (ha/m3/s), 𝐷 = delta of crop (cm), 𝐴 is area of crop (ha) and 𝑄 =
flow rate (m3/s). Duty of water and delta of crop is explained in detail in chapter 3.
The need of conveying different amounts of water to meet the irrigation requirements for a
required water level is the main criterion for canal design. Furthermore, the design must be
compatible with a particular local sediment load in order to avoid silting and scouring. The
diverted discharge should meet the irrigation requirements and at the same time the least
deposition and erosion should occur in the canal system.
It was suggested that the irrigation network should be designed and operated is such a way
that:
During the design phase, irrigation canals are divided into three categories, as follows:
Canals with a rigid boundary. The canal design is based on the determination of the
velocity at which any sediment entering into the canal will not settle on the boundary.
High velocities are allowed, but they should not produce damage to the lining or create
large disturbance in the water surface. A simulation of the changes of the flow
conditions during the irrigation season becomes an important to ensure that the
sediment doesn’t deposit, even due to low velocities.
Canals with erodible boundary and carrying clean water. The canal design is based
on the sedimentation of the cross section for which the bed material does not move.
The smallest cross section with a velocity as large as possible and without scouring of
the bed should be the result of the canal design.
One of the important topics in the area of free surface flows is the design of channels
capable of transporting water between two locations in a safe, cost effective manner. Even
though economics, safety, and aesthetics must always be considered, in this unit thrust is
given only to the hydraulic aspects of channel design and the design of channels for uniform
flow. The two types of channels considered are:
There are some basic issues common to both the types and are presented in the following
paragraphs.
Table 1. Suitable side slopes for channels built in various types of Materials
Permissible non-erosive velocity of a channel is dependent upon the stability of lining materials
and channel vegetation, as follows:
𝑣 = 𝐶 𝑅𝑆 (4.3)
Where 𝑣 is velocity of flow, 𝑅 is the hydraulic radius of flowing section, 𝑆 is the slope of
water surface which is taken as equal to the slope of channel bed (m/m), 𝐶 is the Chezy’s
constant which varies with surface roughness and flow rates.
1 2 1
𝑣 = 𝑅3 𝑆2 (4.4)
𝑁
Where 𝑣 is average flow velocity (m/s), 𝑁 is the Manning’s roughness coefficient, 𝑆 is the
channel slope (m/m), 𝑅 is the hydraulic radius (m), 𝐴 is the flow cross sectional area (m2).
Based this, Manning suggested the relationship between 𝐶 and 𝑁 as follow:
1
𝑅6
𝐶= (4.5)
𝑁
The Manning’s equation is best used for uniform steady-state flow. However, these assumptions
are rarely achieved in reality. Manning’s equation is still used to model most open channel
flow.
Alluvial soil. The soil which is formed by continuous deposition of silt is known as alluvial
soil. The river carries heavy charge of silt in rainy season. When the river overflows its
banks during the flood, the silt particle get deposited on the adjoining areas. This
deposition of silt continues year after year. This type of soil is found in delta region of a
river. This soil is permeable, soft and very fertile.
Non-alluvial soil. The soil which is formed by the disintegration of rock formation is known
as non-alluvial soil. It is found in the mountains regions of a river. The soil is hard and
an impermeable in nature. This is non-fertile.
Silt factor (f). In the designing of a canal in alluvial soil, the suspended silt and the
deposited silt in the canal bed should be taken into consideration with great importance.
During the investigation work in various canals in alluvial soil, Lacey’s established the effect
of silt on the determination of discharge and the canal section. So, Lacey introduced a
factor which is known as ‘silt factor’. It depends on the main particle size of silt and
expressed as:
Where 𝑑 = mean particle size of silt (mm), 𝑓 = silt factor as shown in table 5.
Mean velocity (V). The velocity distribution in a canal section usually varies from one point
to another. This is due to shear stress at the bottom and at the sides and due to the
presence of the free surface. Field observation shows that average velocity for open
channel flow to be the average velocity measured at 0.2 and 0.8 of depth of flow (y) from
the water surface.
𝑉 = 𝑉0.2𝑦 + 𝑉0.8𝑦 (4.7)
Where 𝑉0.2𝑦 = the velocity at 0.2y from the water surface, 𝑉0.8𝑦 = the velocity at 0.8y from the
surface, 𝑦 = depth of flow.
Critical velocity (𝑽𝒐 ). When the velocity of flow is such that there is no silting and
scouring action in the canal bed, then that velocity is known as critical velocity. Generally
the critical velocity depends on the nature of the soil formation in which the water flows.
Table 4 shows the critical velocity for different soil formations.
Critical Velocity Ratio (m). The ratio of the mean velocity to the critical velocity is known
as critical velocity ratio.
𝑉
𝑚= (4.8)
𝑉𝑜
Regime channel. A channel in which neither silting nor scouring takes place is called
regime channel or stable channel.
Erodible channels which scour but do not silt. The behavior of flow in erodible channels is
influenced by several parameters and precise knowledge is not available on various aspects.
Unlined channels with channel bed and banks composed of earth, sand or gravel must be
designed so that they maintain a stable configuration. There are three procedures for design of
earthen channel:
𝛾𝑤 𝐴𝐿𝑆
𝐹 = 𝛾𝑤 𝐴𝐿𝑠𝑖𝑛𝜃 = (4.9)
𝑃𝑤 𝐿
Where, 𝛾𝑤 is unit weight of water; 𝐴 is the wetted area, 𝐿 is the length of the channel
reach, and 𝑆 is the slope. Thus, the average value of the tractive force per unit wetted area
is called unit tractive force (𝝉𝒐 ).
𝐹 𝛾𝑤 𝐴𝐿𝑆
𝜏𝑜 = = = 𝛾𝑤 𝑅𝑆 (4.10)
𝐴 𝑃𝑤 𝐿
Where 𝑃𝑤 = the wetted perimeter and 𝑅 = the hydraulic radius. For wide rectangular channel,
it can be written as:
𝜏𝑜 = 𝛾𝑤 𝑦𝑆 (4.11)
In most channels, the tractive force is not uniformly distributed over the perimeter.
Inciption motion condition or the critical condition or the threshold point is the stage at
which the shear force exerted by the following water on the bed particles will just exceed
the force opposing their movement. Knowledge of velocity at which such a critical condition
occurs is quite helpful in designing stable non-scouring channel admitting clear water.
Where 𝐹𝑠 = the shield function, which is equal to 0.056, 𝑆𝑐 is the specific gravity of particle,
𝑑 is the diameter of particle.
For designing non-scouring channels in coarse alluvial soil with 𝐹𝑠 = 0.056 and 𝑆𝑐 = 2.65;
𝜏𝐶
0.056 = → 𝜏𝑐 = 0.056 𝛾𝑤 𝑑 1.65 (4.13)
𝛾𝑤 𝑑 2.65 − 1
For the channel to be non-scouring, 𝜏0 ≤ 𝜏𝑐 and equating equation (4.10) and (4.13):
Equation (4.14) gives the minimum size of the bed material or lining stone that will remain at
rest in a channel of given 𝑅 𝑎𝑛𝑑 𝑆. The critical shear stress can be given as a function of
particle size:
0.409𝑑2
𝜏𝑐 = 0.155 + (4.15)
1 + 0.177𝑑 2
𝑁
Where 𝜏𝑐 is the critical shear stress (𝑚 2 ), 𝑑 is the diameter of particles (mm).
Consider a sediment particle submerged in water and resting on the side of a trapezoidal
channel.
Under equilibrium conditions, drag force must be equal to the resisting forces:
𝜏𝑠2 + 𝑊𝑠𝑖𝑛𝜃 2
= 𝑊𝑐𝑜𝑠𝜃𝑡𝑎𝑛𝜙 2
(4.17)
𝜏𝑏 2 𝜏𝑏 2
𝜏𝑠2 + 𝑠𝑖𝑛𝜃 = 𝑐𝑜𝑠𝜃𝑡𝑎𝑛𝜙
𝑡𝑎𝑛𝜙 𝑡𝑎𝑛𝜙
𝜏𝑠 tan2 𝜃 sin2 𝜃
𝐾= = 𝐶𝑜𝑠𝜃 1 − ( ) = 1−( ) (4.18)
𝜏𝑏 tan2 𝜙 sin2 𝜙
In figure (8) the particle size is the diameter of the particle of which 25 percent of all the
particles, measured by weight are larger.
Straight canals have straight or slightly curved alignments are typical of canals built in
flat plains, which is typical of slightly undulating topography.
Moderately sinuous canals have a degree of curvature, which is typical of moderately
rolling topography.
Very sinuous canals have a degree of curvature which is typical of canals in foothills
or mountainous topography. Then, correction factors can be defined as in table 8.
5. Estimate tractive force ratio (K), between the side slope and the bottom of the channel
𝜏𝑠 tan 2 𝜃 sin 2 𝜃
K = = 𝐶𝑜𝑠𝜃 1 − ( ) = 1−( ) (4.21)
𝜏𝑏 tan 2 𝜙 sin 2 𝜙
6. Determine the maximum permissible tractive force for the channel forming material.
Bed of channel: 𝜏𝑏 = 𝐶𝑠 𝜏𝑜 (4.22)
Side slope: 𝜏𝑚𝑎𝑥 = 𝐾𝜏𝑏 (4.23)
7. Assume that the stress acting on the side slope channel limits our design and
determine the uniform flow depth of channel.
𝜏𝑜′
𝜏′0 = 0.75𝛾𝑤 𝑅𝑆 → 𝑅 = (4.24)
0.75γw 𝑆
8. Calculate channel dimension from the geometry of channel
𝑄𝑁
From Manning 𝐴= 2 1 (4.25)
𝑅3 𝑆2
From Geometry: 𝐴 = 𝐵𝑦 + 𝑚𝑦 2 (4.26)
9. Check that the permissible tractive stress is not exceeded on the channel bed
Actual tractive force: 𝜏0 = 𝛾𝑤 𝑅𝑆 ≤ 𝜏𝑏 (4.28)
10. Check that the design velocity exceeds the minimum permitted velocity (usually 0.6 to
0.9 m/s) and check the Froude number is less than 1, i.e., subcritical flow.
𝑄
𝑉= 4.29
𝐴
𝑉
𝐹𝑟 = (4.30)
𝐷𝑔
𝐴
𝐷= (4.31)
𝑇
11. Estimate the required freeboard. The free board (measured from full supply level to the
top of channel) depends on the size of canal, velocity of flow, curvature of alignment,
wind and wave action and method of operation.
United State Bureau of Reclamation (USBR) provided recommended free board based on the
design discharge.
Table 8. The free board recommended by USRB for channel based on design discharge
Where 𝑉𝑜 is the critical velocity (m/s), 𝑚 is the critical velocity ratio, 𝑦 is the depth of flow
(m). The constant 0.546 and index 0.64 depend on the characteristic of silt and the type of
silt. Where 𝑚 is incorporated to show the role of sediment size.
𝑄 = 𝐴𝑣 (4.33)
𝑉 = 𝐶 𝑅𝑆 (4.34)
After study, Lacey’s theory gave four fundamental equations for design of irrigation channel:
𝑉0 = 0.639 𝑅𝑓 (4.37)
𝐴𝑓 2 = 141.2𝑉05 (4.38)
2 1
𝑉𝑜 = 10.8𝑅 3 𝑆 3 (4.39)
𝑓 = 1.76 𝑑 (4.40)
𝑉𝑜2
𝑉𝑜 = 0.639 𝑅𝑓 → 𝑅 = 2.46 (4.42)
𝑓
141.2𝑉05 𝑉04 𝐴
= 2
→ 141.2𝑉𝑜 =
𝐴 0.1667𝑅 0.1667𝑅2
𝐴 𝐴2
141.2𝑉𝑜 = 𝐴 → 141.2𝑄 =
0.1667𝑅2 0.1667𝑅2
𝐴 𝑃2
141.2𝑉𝑜 = 𝐴 → 141.2𝑄 =
0.1667𝑅2 0.1667
𝑃 = 4.825 𝑄 (4.44)
To permit the transmission of water at high velocities through areas of deep or difficult
excavation in a cost effective manner;
To decrease canal seepage, thus conserving water and reducing the water logging of
lands adjacent to the canal;
To reduce the annual cost of operation and maintenance;
To ensure the stability of the channel section.
The design of lined channel from the view point of hydraulic engineering consists of
proportioning an assumed channel cross section. A recommended procedure for proportioning a
lined section is summarized below. It is assumed that the design discharge (𝑄), the
longitudinal slope of the channel (𝑆), the type of cross section (rectangular, triangular,
trapezoidal, etc), and the lining material have all been selected prior to the initiation of the
channel design process.
We always search for an efficient and economical channel section. The most economic section
is one, which can carry maximum discharge for a given cross-sectional area. i.e., the channel
which require minimum cross-sectional area (excavation) for a given discharge. For practical
purposes, discharge is fixed, and the minimum cross-sectional area is of interest.
The earthen channel of rectangular section is not used except in heavy clay or rocky soils,
where the faces of rocks can stand vertically. A concrete channel of rectangular configuration
is generally used. Thus, the hydraulically efficient section of the concrete channel is important.
For the maximum discharge conditions, the criteria of channel configuration are as follows
Many natural and manmade channels are approximately trapezoidal. In practice, the trapezoidal
section is normally used in earthen channel. Generally, the side slope in a particular soil is
decided based on soil type. In loose soil, flatter side slopes are provided, where as in hard
one, steeper side slopes are allowed.
For maximum discharge or maximum velocity, the two conditions are as follows:
𝑏+2𝑧𝑑
2
= 𝑑 𝑧2 + 1
2. Hydraulic radius is half of flow depth
𝑑
𝑅=
2
1
3. Side slope: 𝐻: 1𝑉
3
In addition to that the conveyance of channel will be efficient when the channel section have
minimum perimeter for a given area, slope and roughness coefficient.
Figure 9 shows the economical section of channel and aims at balancing the quantity of earth
work in excavation with that in filling. Sometimes when the natural surface level (NSL) is
above the top of the bank, the entire canal section will have to be in cutting, and it shall be
called canal in cutting. Similarly, when the NSL is lower than the bed level of the canal, the
Side slopes. The side slopes should be such that they are stable, depending upon the
type of the soil. A comparatively a steeper slope can be provided in cutting rather than in
filling as a soil in cutting shall be more stable.
Berms. It is the horizontal distance left at ground level between the toe of the bank and
the top edge of cutting.
Service roads. Service rods are provided on canals for inspection purposes, and may
simultaneously serve as the means of communication in remote areas. They are provided
0.4m to 1m above FSL, depending upon the size of the channel.
1.6.7 Fixing the L-Section of the Canal and other Design Considerations
If a channel is designed according to Lacey’s theory, it shall have a fixed slope and a fixed
section for a given discharge and silt factor. But on the other hand, if the channel is designed
on Kennedy’s theory, it can have different sections for different slopes. However, the slope of
the channel is fixed on available slope consistent with economy. A steeper slope governed by
maximum permissible velocity, will be most economical, but it will lower the FSL causing less
irrigation. Hence, the maximum possible irrigation would be at flatter slopes governed by
minimum permissible velocity. A via media between these two limits must be adopted for
selecting a suitable bed slope for the channel.
If the chosen designed slope is found to be flatter than the natural available slope, the
difference can be adjusted by providing suitably designed canal falls. But if the designed slope
After marking the ground surface level, a trial bed line, and water depths, FSL line on the L-
section of the channel is checked. FSL is governed by the following considerations:
The FSL of the channel should be about 0.1 to 0.2m above the ground level for the
most of its length;
The water depth of FSL governs the depth of excavation and hence, attempts should
be made to equate depth of excavation with balancing depth, so that the channel
becomes in balanced earthwork;
For branch canal where some distributaries have take-off from it, the FSL of the
channel should be kept 15cm higher than the FSL of the off-taking channel, so as to
allow for losses in head regulator;
Note. A suitable adjustment in the bed slope, depth of flow, etc, can be made for fixing FSL
on the above considerations.