Milestone Confirmation of The Process Order With Multiple Operations & With Multiple Phases Involved
Milestone Confirmation of The Process Order With Multiple Operations & With Multiple Phases Involved
Milestone Confirmation of The Process Order With Multiple Operations & With Multiple Phases Involved
Dear All,
For a Process Order, with multiple Operations & each Operation contains multiple Phases.
During the confirmation of the last Phase of the last Operation, (which contains Milestone
confirmation) System should automatically confirm all preceding Phases in all the
Operations
Please find the sequence of steps involved in executing this Business Process/Requirement
1.Create Material Master for the FG/SFG & Raw Materials required, Transaction code ;
MM01
Created the below Materials for this scenario
For Example : Finished Product: FNP1 & Raw Material: QMATR1
2. Create the BOM for the finished Product, using he Transaction Code: CS01
Created the BOM for the Finished Product : FINP1, with the required set of
components
In the initial screen, that is displayed, enter all the required fields & Press Enter
In the next screen, that is displayed, enter the required fields, then Press Enter
In the Next screen that is displayed, enter the required data
Enter all the sequence of Operations & the Phases of the respective Operations
Look at the details of the Control key settings
Now, maintain the Relationship, between the Phase with Milestone Confirmation
(0080 Phase), in all the other Phases (0020, 0040, 0060, 0070)
How to Maintain the Relationship (for Ex: for the Phase 0020)
Select the Phase & Click on the Relationships Icon (as shown)
In the next screen, that is displayed, enter the required data
Continue the same, for all the remaining Phases: 0040, 0060, and 0070
Make Sure, all the relationships are also updated in the Phase: 0080, as
Predecessors
Click on Materials Tab, Enter the required Data
In the Next Screen, that is displayed, If required, Check for Consistency & then
save
Recipe was saved with group 50000162 and material FINP1.
Make sure, Material Master of the FG, is correctly updated with Production Version details