Review Hydrology
Review Hydrology
Review Hydrology
• Hydrologic Cycle
• Precipitation
– Average over Area
– Return Period
• Abstractions from Rainfall
• Runoff
– Hydrographs
– Determination methods
Hydraulics of Structures
• Weir flow
• Orifice flow
• Pipe flow
• Spillway flow
– Stage-Discharge relationship
Open Channel Flow
• Channel geometries
– Triangular
– Trapezoid
– Parabolic
• Manning’s equation
– Manning roughness, “n”
• Grass waterway design
A few comments
• Material outlined is about 3 weeks or more in a
3-semester hour class. I’m compressing at least
6 hours of lecture and 3 laboratories into 2
hours, so I will:
– Review highlights and critical points
– Do example problems
• You need to:
– Review and tab references
– Do additional example problems, or at least
thoroughly review examples in references
Hydrologic Cycle
Consider:
Raingage data
• Gages (clockwise from upper left): 1.9”,
2.1”, 1.8”, 1.9”, 2.1”, 2.2”
A. 2.0”
B. 2.1”
C. 2.2”
D. 1.9”
Theissen calculation
• Uses areal weighted average, so the sum of the
products of area x depth divided by total area
• Hint: If you measure the areas yourself, the
denominator should be the sum of the areas, not
the known watershed area
• So, average Theissen rain: Answer B, 2.1”
(65*1.9+150*2.1+55*1.8+140*1.9+215*2.1+270*2.
2)/(65+150+55+140+215+270)=2.07”, which is
best represented as 2.1” given most data is 2
significant digits.
Return Period (two descriptions)
• A 10 year-24 hour rainfall volume is that
depth of rainfall over a 24 hour period that
is met or exceeded, on the long-term
average, once every 10 years.
• Another way to describe it is the 24 hour
rainfall depth that has a 1 in 10 (10%)
chance to be met or exceeded each year,
on the long term average.
US 100yr-24hr Rainfall
A. 4.5”
B. 3.9”
C. 4.1”
D. Cannot estimate from available maps
10yr-24hr map from Haan, Barfield & Hayes (1994)
Example
• Answer is C. From map, 10yr-24hr rainfall
in NE Illinois is just over 4”, use 4.1” to be
conservative.
Abstractions from Rainfall
• Abstractions from rainfall are “losses” from
rainfall that do not show up as storm water
runoff:
– Interception
– Evapotranspiration
– Storage
• In bank
• On surface
– Infiltration
Runoff by other names…
• “Effective” rainfall
• Rainfall “excess”
Runoff
If rainfall rate exceeds the soil infiltration
capacity, ponding begins, and any soil
surface roughness creates storage on the
surface. After at least some of those
depressions are filled with water, runoff
begins. Additional rain continues to fill
depressional storage and runoff rate
increases as more of the hill slope and
subsequently the watershed contributes
runoff.
Rainfall/Runoff process
Time of Concentration, tc
The time from the beginning of runoff to the
time at which the entire watershed is
contributing runoff that reaches the
watershed outlet is called the Time of
Concentration. It is also described as the
“travel time from the hydraulically most
remote point in a watershed to the outlet”.
Curve Number method
CN Method, continued
Time of Concentration, tc
CN values
Runoff Volume determination
Runoff Example
In a previous problem, a design rain event in NE
Illinois was determined to be 4.1”. Assuming the
watershed in question was a completed 300 ac
residential area with an average lot size of ½ ac,
all on Hydrologic Group C soils, what is the
needed pond volume?
A: 2.5 runoff-inches
B: 53 acre-inches
C: 630 acre-ft
D: 53 acre-ft
Runoff Example, continued
Runoff Volume determination
Answer to Runoff Example
The answer is D, 53 acre-ft. From the table,
the CN for Hyd group C soil with ½-ac lot
is 80. Using the graph with a 4.1” rainfall,
runoff depth is 2.1”. Volume is then
300ac*2.1in = 630 ac-in, divided by 12 is
53 ac-ft.
Additional example
You discover that the subdivision is actually 100
acres of ½ ac lots on C soils, 100 acres of ½ ac
lots on D soils, 50 acres of ¼ ac lots on B soils
and 50 acres of townhouses on A soils. What
CN value would you use?
A: 79
B: 85
C: 80
D: 75
Answer
The correct answer is C, 80. Use an area-
weighted average, similar to Theissen
method. The respective CN values for ½
ac on C, ½ ac on D, ¼ ac on B and
townhouses on A are 80, 85, 75 & 77.
The area-weighted CN is then
(80*100+85*100+75*50+77*50)/300 =
80.33, which is more appropriately 80.
Peak Discharge
The CN method also provides for Peak
Discharge estimation, using graphs or
tables. Required information includes
average watershed slope, watershed flow
path length, CN, and rainfall depth. The
graphical method from the EFM is:
Peak Runoff Discharge
Peak Discharge Example
Same residential watershed that produced
2.1” of runoff from a 4.1” rainfall. Flow
length is 2500’, slope is 2%. CN is 80, so
S is 2.5”. Ia = 0.2*S = 0.5”. Ia/P =
0.5/4.1=0.122.
Tc = 2500^0.8*(1000/80-9)^0.7/1140/2^0.5
=0.8hr
Example solution
From graph, with Ia/P of 0.122 and Tc of
0.8hr, unit peak discharge is 0.57 cfs/ac/in
or qp = 0.57*300*2.1 = 360 cfs
Rational Method
The Rational Equation is:
Qp = CiA
where:
C is a coefficient
i is rainfall intensity of duration tc
A is area in acres
From:
http://www.erh.noaa.gov/er/hq/Tp40s.htm
Hydraulics of Structures
Flow through structures is important given
that such structures control the rate of
flow. Sizing of such structures is then
important to allow flow to pass while
protecting downstream areas from the
effects of too high a flow rate. Structures
may also be used for measurement of
water flow. Each type of structure will
produce different types of flow depending
upon size and flow rate passing through it.
Weirs
• Sharp-crested
• Broad-crested
Weir Equation
Where:
A: 140 cfs
B: 8.5 cfs
C: 100 cfs
D: 200 cfs
Solution