Instruction 14-06-2017 FC
Instruction 14-06-2017 FC
Instruction 14-06-2017 FC
Technical Branch
***
144, Anna Salai, Chennai – 2.
2. Under this scheme, the Domestic and Commercial buildings which require low
tension electricity service connections should be within 100 feet from the electricity
mains of TANGEDCO and if so, the electricity service connection can be effected on
the same day or a maximum time of 48 hours in cases which involve road cut for
laying of underground service connection cable.
iii) If the applicant is not the owner, consent letter from owner in FORM
No.5 or valid proof of occupancy and indemnity bond in Form No. 6.
5. Due care shall be taken by the concerned section officer before cancelling the
applications. In case of cancellation of the applications, the entire amount except
registration charges should be returned to the applicants by the concerned Section
Officer with the prior approval from the Superintending Engineer concerned.
2. In this regard, working instruction for drawal of rolling stock meters and
other related issues is enclosed in the Annexure A. Further, a register for
rolling stock of meters should be maintained as prescribed in Annexure B.
6. The applicants shall pay the above charges at the time of registering the
application in the TANGEDCO office or through online application itself. In
case of three phase Domestic and Commercial service connections, it is
sufficient that the applicants can pay the above miscellaneous charges
only for 4 kW demand at the time of registering the application and avail
the service connections.
7. The estimate charges and miscellaneous charges (for the demand applied
over and above 4 kW in respect of three phase Domestic / Commercial
Service connections) if any are due from the consumers, the same shall
be collected in the first Current Consumption (CC) bill and this fact has to
be intimated to the intending consumer through notice / e-mail / SMS etc.
11. The Executive Assistant to the Director (Distribution) shall also coordinate
with the Distribution Circles for better reach out of this scheme among the
general public and to monitor the progress of implementation of the
scheme.
12. There are some complaints that the intending consumers are insisted to
supply the underground service connection cable or asked to pay for the
same for effecting service connections. In case of such complaints, the
intending consumers can give complaints to the Director General of Police
/ Vigilance / TANGEDCO through Email: adgp@tnebnet.org, Phone No.
044-28520416, Fax No. 044-28520749.
13. The complaints received in the office of the Director General of Police /
Vigilance shall be investigated by the vigilance wing and appropriate
disciplinary action will be taken against the erring official. A copy of the
complaint will be sent to the Superintending Engineer concerned. The
Superintending Engineer concerned shall send the action taken report on
the complaints to the Superintending Engineer/Commercial, who in turn
shall put up the consolidated report on the complaints along with the
action taken to the CMD/TANGEDCO once in fortnight.
8. In view of the above, all the Chief Engineers/Distribution Regions are instructed to
fix the responsibility to the concerned Superintending Engineers of the EDCs to
strictly follow the above instruction by the field officers under their control for
effecting LT Domestic and Commercial service connections (other than special and
multi-storeyed buildings) applied through either in person or through online.
9. This scheme of ‘one day service connection’ will come into effect from 01-07-2017
and any lapses in this regard, will be viewed seriously.
To
Rural Section - 3 1
Urban Section - 7 3
12. The estimate for keeping the rolling stock will be sanctioned by the
Superintending Engineers concerned and it is a onetime sanction. Meters from
this rolling stock should not be used for any purposes in the distribution.
13. Rolling stock of meter should be drawn and kept at the section office. It is the
personal responsibility of the section officer to keep the rolling stock account
properly to avoid any misuse.
14. The Assistant Executive Engineers should check frequently to ensure that the
meters on rolling stock are properly used and scheme is implemented
effectively.
15. This scheme has to be monitored on a daily basis and the Executive Engineer
& the Superintending Engineer concerned will be held responsible for any let
up in this issue.
16. In case of online application, after effecting service connection, a print out of
the application along with relevant documents, test report, etc. shall be
submitted to the Office of the Executive Engineer (Revenue Branch) for
record purposes.
Sanction Memo.No. :
Work Order No. :
Requisition :
Number of Meters : 1 Phase 3 Phase
Sanctioned.
III PAGE:
I : II
BLUE INK : GREEN INK
:
Sl. ROLLING STOCK METER DETAILS : Name of SC.No. TF
No. Regn. Make Cap. Sl.No. MRT No. IR : Consumer Date
No. dt. :
1 2 3 4 5 6 7 : 8 9 10
----------------------------------------------------------------------
III
----------------------------------------------------------------------
RED INK
----------------------------------------------------------------------
RECEIPT ENTRY
(1) Details relating to Meter drawn against “INITIAL ROLLING STOCK” will have
entry only in Column I.
(2) Details relating to Meter drawn against SC SANCTION & taken into Rolling
Stock will find entry in Column III & in Column I.
Example: - Details of meter drawn against sanction for first applicant in this
scheme will have entry in Column III against Sl.No. 1 & again in Column I
immediately below the initial set of Rolling Stock meters.