Construction Cost Control Assignment 1: The End of The Project)
Construction Cost Control Assignment 1: The End of The Project)
ASSIGNMENT 1
•The mobilization and site clearance can commence on day one (June 1st), will take six
weeks and will cost $60,000.
•Foundation and slab construction will cost $96,000, can commence two weeks after
day one and will take eight weeks.
•Erection of the building will take eight weeks at a cost of $10,000 per week and will
commence immediately after delivery of the building.
•Internal tenant improvements and equipment will cost $360,000, take 12 weeks and
can commence two weeks after erection of the building commences.
•Commissioning of the equipment will cost $4,000 per week, will commence two weeks
before the pre-manufactured building is complete and cannot be completed until two
weeks after the tenant improvement and equipment installation are complete.
•Completion of the site development will cost $72,000, take eight weeks and will
commence immediately after the erection of the pre-manufactured building is complete.
•Site overheads are $6,000 per month and head office fees and overheads are 10% of
direct project costs. (Site overheads and head office fees should be every month till
the end of the project)
•All activity costs are deemed to occur evenly during the duration of the activity.
List any other assumptions required:
Page 1
Requirements:
Prepare two bar charts (one original and one revised) as in the template on
blackboard.
Revised total duration and revised cost of the project incorporating the following event:
The foundations and slab construction activity took 125% of the planned time and cost
50% more than originally estimated?
AND
Using the data presented and assuming that:
•Progress draws subject to 10% holdback are made monthly (four week monthly
periods);
Draw a monthly income and expense profile for the project. Clearly indicate the
cumulative monthly figures throughout the duration of the profile.
**Hint:-
Page 2