Problem 1
Draw an activity network for the following activities. Assuming that
the project starts at day 0, calculate the ES, EF, LS and LF and the
earliest completion time of the project. Calculate also the total slack
on all activities and identify the critical path
Activity A B C D E F G H I
Immediate
- - A A,B B,C C,D C,D E,F E,G,F
Predecessor
Activity
Duration 3 5 6 2 4 7 3 4 5
(Day)
Problem 2
The director of continuing education at Bluebird University has just
approved the planning for sales training seminar: Her administrative
assistant has identified the various activities that must be done and
their relationships to each other, as shown below:
Immediate
Activity Description
Predecessor(s)
Design brochure and
A -
course announcement
Identify prospective
B -
teachers
Prepare detailed outline of
C -
course
Send brochure and
D A
student applications
E Send teacher applications B
F Send teacher for course C,E
G Accept students D
H Select text for course F
I Order and receive texts G,H
J Prepare room for classes G
The director wants to conduct the seminar 47 working days from now.
What is the probability that everything will be ready on time?
Problem 3
Your company has just received an order from a good customer for a
specially designed electric motor. The contract states that, starting on
the thirteenth day from now, your firm will experience a penalty of
$100 per day until the job is completed. Indirect project costs amount
to $200 per day. The data on direct costs and activity precedence
relationships are given in the following table:
Problem 4
A project consists of seven activities. The precedence relationships are
given in the following table:
Time Immediate
Activity
(Days) Predecessor(s)
A 32 -
B 21 -
C 30 -
D 45 A
E 26 A,B
F 28 C
G 20 E,F
Number of Number of
Activity
Welders Required Pip Fitters Required
A 6 10
B 3 15
C 8 8
D 0 20
E 10 6
F 10 9
G 4 14