CP&M - Lec 10 CPM
CP&M - Lec 10 CPM
CP&M - Lec 10 CPM
BACKGROUND
• Managers have been planning, scheduling, monitoring, and controlling
large scale projects for hundred years, but it has only been in the last 50
years that management science techniques have been applied to major
projects.
• In 1957, the Critical Path Method (CPM) was developed by Kelly and
Walker to assist in building and maintenance of chemical plants.
PERT/CPM
A - 3
B A 7
C A 4
D B 5
E B,C 8
Question no 2 Draw Arrow Network and perform the CPM
calculations for the following schedule of the Project
Activity IPA Duration(Weeks)
A - 7
B - 10
C A 15
D A,B 8
E C,D 4
Question no 3 Draw Arrow Network and perform the CPM
calculations for the following schedule of the Project
Activity IPA Duration(Weeks)
A - 2
B A 4
C A 6
D A 9
E B 5
F B,C 7
G D,E,F 3
Question no 4 Draw Arrow Network and perform the CPM
calculations for the following schedule of the Project
Activity IPA Duration(Weeks)
A - 6
B - 2
C A 8
D A,B 5
E B 3
F D,E 6
G C,D 5
H F,G 2
Question no 5 Draw Arrow Network and perform the CPM
calculations for the following schedule of the Project
Activity IPA Duration(Days)
A - 6
B - 2
C - 8
D A 5
E C 3
F D 6
G A,B 5
H E 2
I F 12
J G 3
K H 4
L I 5
M G,K 6
N J,L 7
O J,M 1
Que.
A project consists of 13 activities in all from A to N. Assume time
required for each activity as “R”, “R+1”, “R+2”.,,,,,.
Activity A and N are the first and last activity of the project,
respectively. At the end of activity A, activities B and C can be started
simultaneously. Activity D follows B and activities E and F follows C.
Activity G can be started on the completion of D & E. Activity H follows
F and activities K and M can be started simultaneously on completion
of H. Activity I follows G and K both, and activity N is the last activity
which can be started on completion of M, and L which is a succeeding
activity of M, the work finishes at the end of N.
i. Construct a precedence diagram, ii. On the diagram, compute the four
schedule dates (ESD, EFD, LSD, LFD) and the floats for each activity, also
Identify the critical path.