Planning and Construction of Highway: Bachelor of Technology in Civil Engineering
Planning and Construction of Highway: Bachelor of Technology in Civil Engineering
Training Report
Submitted
In partial fulfillment
of
Bachelor of Technology
In
Civil Engineering
2016-2020
SUBMITTED TO SUBMITTED BY
ACKNOWLEDGEMENT
I would like to thank for providing me the opportunity to undergo summer training in one of
project improvement.
I am very thankful to Mr.Banwari Lal Saini for giving me permission for my training.
I would like to thank Mr.Sachin Patel , for helping me in my training it was there helping and
friendly behaviour which made this training a memorable experience for me.
I am also thankful to my internal project guide Mr. Smeet Faldu (Professor of engineering)
and Mr. Vikram Suthar (Professor of civil engineering) for his guidance in my project.
TABLE OF CONTENT
‘SHAPOORJI PALLOJI & CO. PVT. LIMITED’ is a Joint Venture between NHAI
Specialized in Highways, Bridges and Airport and Railways construction is one of the
renowned infrastructure companies in India contributing to the Nation’s Economic and
infrastructure growth. Known for its excellence in project management and quality
execution, promoted by professionals with over three decades of experience, backed by
competent and highly motivated team of experts, using state of the art technologies
combined with high degree of mechanization, a strong base of human resources and abilities
to forge partnerships for execution of projects, ‘SHAPOORJI PALLOJI & CO. PVT.
LIMITED’ is poised to play a vital role in Nation’s tryst with Glory.
Four Leaning Of NH-27 from 3507 KM in the State of Rajasthan Under NHDP Phase
III on Design, Build, Finance, Operate & Transfer (the “DBFOT”) Toll Basis.
Figure 1. NH-27
Project Map
PROJECT HIGHLIGHTS
S Description Number
No
.
1 ROB 1
2 Minor Bridges 2
3 VUP 1
4 Single cell Box culvert 13
5 Multi cell Box culvert 2
6 Slab culvert 81
CHAPTER 2
HISTORY OF ROADS AND HIGHWAY
CHAPTER 3
TYPES OF ROAD
3.1 ROAD
Road as a line of communication (travelled way) using a stabilized base other than rails or air
strips open to public traffic, primarily for the use of road motor vehicles running on their own
wheels, which includes bridges, tunnels, supporting structures, junction, crossings,
interchanges, and tool roads, but not paths.
6
Indian road network current status
7
CHAPTER 4
EARTH WORK
8
4.3 COMPACTION
Compaction is what happens when something is crushed or compressed. In many places,
garbage undergoes compaction after it's collected, so that it takes up less space. The process of
making something more compact, or dense and very tightly packed together, is compaction.
9
CHAPTER 5
ROADWAY COSTRUCTION
5.1 CARRIAGEWAY
A carriageway or roadway consists of a width of road on which a vehicle is not restricted by
any physical barriers or separation to move laterally. A carriageway generally consists of a
number of traffic lanes together with any associated shoulder, but may be a sole lane in width.
5.2 PAVEMENT
Pavement is finished with a hard smooth surface. It helped make them durable and able to with
stand traffic and the environment. They have a life span of between 20-30 years.
5.3 EARTHWORK
The subgrade soil is prepared by bringing is to the desired grade and camber and by
compacting adequately. The subgrade may be either in embankment or in excavation,
depending on the topography and the finalized vertical alignment of the road to be constructed.
10
5.4 EXCAVATION
The excavation commonly used in highway projects include bull dozers, scrapers, power
shovels, draglines, clamshells and hoes. However in small projects excavation is carried out
manually using hand tools. However scrapers are not capable of digging very stiff material.
5.5 KERB
The height of this kerb is about 10 cm above the pavement edge with a slope which allows the
Vehicle to climb easily submerged kerbs. They are used in rural roads. The kerbs are provided
at pavement edges between the pavement edge and shoulders. They provide lateral
confinement and stability to the pavement.
5.6 SHOULDER
A road shoulder is a strip of land immediately adjacent to the traffic lane of a road not bordered
by kerb & channel. The shoulder may be sealed in the case of highways and major roads, but it
is typically unsealed and of a lesser depth and perhaps constructed of inferior material than the
adjacent traffic lane.
11
Fig 5.3 Shoulder
5.7 SIDEWALKS/FOOTPATH
A sidewalk also known as a footpath or footway is a path along the side of a road. It is often
constructed of concrete or cement, though occasionally asphalts, and is designed for
pedestrians.
12
5.8 EMBANKMENT
When it is required to raise the grade line of a highway above the existing ground level it
becomes necessary to construct embankment. The grade line may be raised due to any of the
following reasons.
5.9 SUBGRADE
Subgrade is the native material underneath a constructed road, pavement or railway (US
railroad) track. It is also called formation level. The term can also refer to imported material
that has been used to build an embankment.
13
CHAPTER 6
BITUMEN ROAD CONSTRUCTION
PROCEDURE
It is desirable to lay AC layer over a bituminous base or binder course. A tack coat of bitumen
is applied at 6.0 to 7.5 kg per 10 sq.m area, this quantity may be increased to 7.5 to 10 kg for
non-bituminous base.
6.4 ROLLING
A mix after it is placed on the base course is thoroughly compacted by rolling at a speed not
more than 5km per hour. The initial or break down rolling is done by 8 to 12 tonnes roller and
the intermediate rolling is done with a fixed wheel pneumatic roller of 15 to 30 tonnes having a
tyre pressure of 7kg per sq.cm. The wheels of the roller are kept damp with water.
There are six types of roller generally used in road.
• Tire weight.
• Region of contact.
• Tire weight might be up to around 7 kg/cm2.
• The scope region is around 80%.
• The most extreme thickness can be accomplished by 8 goes of the roller. The ideal
speed of roller is between 6 to 24 km/h.
• They are especially productive when used to complete off the dike compacted by step
foot roller or on free sandy soils.
• This kind of roller is fitted with maybe a couple smooth surfaced steel wheels 0.9 m to
1.5 m in distance across and 1.2 m to 1.8 m wide.
• Self -moved vibratory rollers are presently accessible weighing from 4 to 6 tons.
16
• These rollers have a round and hollow substantial steel surface comprising of a system
of steel bars shaping a network with squire gaps and might be ballasted with solid
pieces.
• They are by and large towed units and can work at rates somewhere around 5 and 24
km/h.
• Framework rollers give high contact weight however small working activity and are
reasonable for compacting most coarse grained soil.
17
CHAPTER 7
INTRODUCTION OF PAVEMENT DESIGN
Sufficient thickness to distribute the wheel load stresses to a safe value on the sub-
grade soil.
Structurally strong to withstand all types of stresses imposed upon it.
Adequate co-efficient of friction to prevent skidding of vehicles.
Smooth surface to provide comfort to road users even at high speed.
Produce least noise from moving vehicles.
Dust proof surface so that traffic safety is not impaired by reducing visibility.
Impervious surface, so that sub-grade soil is well protected.
Long design life with low maintenance cost.
7.3 TYPES OF PAVEMENT
There are two types of pavement.
7.3.1 Flexible Pavement
7.3.2 Rigid Pavement
18
7.3.1 FLEXIBLE PAVEMENT
Flexible pavements will transmit wheel load stresses to the lower layers by grain-to-grain
transfer through the points of contact in the granular structure.. The wheel load acting on the
pavement will be distributed to a wider area. Hence, the design of flexible pavement uses the
concept of layered system. Based on this, flexible pavement may be constructed in a number of
layers and the top layer has to be of best quality to sustain maximum compressive stress, in
addition to wear and tear.
A typical flexible pavement consists of four components:
a) Soil Subgrade
b) Base Course
c) Surface Course
The flexible pavement layer transmits the vertical or compressive stresses to the lower layers
by grain to grain transfer through the points of contact in the granular structure.
Fig 7.1 Flexible Pavement
19
Different layers of Flexible Pavement :
7.3.1.5 SUBGRADE
Subgrade is constructed for both flexible and rigid pavements. The thickness of subgrade is
generally 500 mm for important road like National and State highway. The top soil or sub-
grade is a layer of natural soil prepared to receive the stresses from the layers above.
20
7.3.1.6 EMBANKMENT CONSTRUCTION
Embankment is constructed for both flexible and rigid pavement. A highway is generally
designed and constructed such that the formation level is above the general ground level and
also substantially above the highest water table.
22
CHAPTER 8
CONSTRUCTION METHODOLOGY OF FLEXIBLE PAVEMENT
The highway embankment is generally constructed using locally available soil by spreading the
loose soil and compacting the same at the OMC of the soil in layers. The compacted thickness
generally varies from 100 mm to 300 mm.
Figure 8.1 Highway Embankment Constructions
The steps for the construction of highway embankment are given below:-
a) The selected soil in loose condition is spread to uniform thickness using appropriate
equipment over the prepared ground the thickness of loose soil is decided so as to
obtain the specified compacted thickness of layer.
b) Additional water as required is sprayed so as to obtain the OMC of the soil determined
from the laboratory compaction test.
c) The soil with the added water is mixed thoroughly using appropriate equipment so that
the water gets distributed in soil layer uniformly.
23
d) The soil layer is compacted by rolling using the selected equipment so as to obtain the
specified density.
The highway subgrade is generally constructed using suitable soil fulfilling the requirements or
specified properties that are transported from identified borrow pits. It is also possible to utilize
locally available inferior soils which could be improved by appropriate soil stabilization
technique. The maximum compacted thickness is generally limited to 200 mm.
Figure 8.2 Subgrade Construction
The steps for the construction of highway subgrade are given below:-
a) The selected soil in loose condition is spread to the required grade and cross slope in
layer of desired thickness using appropriate equipment such as blade grader, over the
prepared surface.
b) Additional water as required is sprayed so as to obtain the OMC of the soil determined
from the laboratory compaction test.
24
c) The soil with the added water is mixed thoroughly using appropriate equipment so that
the water gets distributed in soil layer uniformly.
The GSB layer is constructed on the top of the prepared subgrade therefore first the surface of
the subgrade is checked and grass and vegetation if any is removed. The grade and cross slope
of the top surface of the subgrade are corrected as required.
Figure 8.3 Sub Base Layers
a) The sub-base material is spread to uniform thickness and specified cross slope using a
motor grader by adjusting the blade of the grader.
b) The moisture content of the material is checked and the additional quantity of water
required to bring up to the optimum moisture content is sprinkled at a uniform rate
using a truck mounted sprinkler.
25
c) The watered material is mixed properly using machinery such as disc harrows and
rotators.
a) Compaction test is carried out in the laboratory using the selected grade WMM material,
after removing the fraction of aggregates retained on 19 mm sieve and replacing it with
material passing 19 mm sieve and retained on 4.75 mm sieve.
b) The selected WMM mix (with water equal to the optimum moisture content added) is
prepared in a suitable mixing plant like the 'pug mill’.
26
c) If the total design thickness of WMM base course is say 250 mm, the base is constructed
in two layers, each of compacted thickness 125 mm. After compaction of the first layer,
the second layer is laid by a mechanical paver finisher.
d) After the WMM layer is dried for at least 24 hours in dry weather, the preparation for
laying a bituminous pavement layer may start by applying the prime coat.
a) If the profile correction required exceeds 40 mm, a profile corrective course is laid
separately using a mechanical paver and is compacted.
27
If the correction required is less than 40 mm, the pavement layer is spread with
provision for the additional quantity of the mix to meet the profile correction
requirement.
b) The receiving surface is cleaned with a mechanical broom to remove loose materials
and dust and tack coat is applied as specified.
c) Rolling is started as soon as laying is done for short stretches roiling is done in three
stages: (a) initial or break down rolling using a tandem -wheel vibratory roller of dead
weight 8 to 10 tonnes, set with high frequency and low amplitude of vibration (b)
intermediate rolling using a pneumatic roller, with tyre pressure more than 5.6 kg/cm2
d) The compacted density achieved is checked by taking 150 mm diameter core samples;
the density achieved shall preferably be 92 percent of theoretical maximum density of
the mix, so that the initial voids in the mix is about 7 to 8% and due to traffic induced
secondary compaction during the design life, the final voids in the mix is not lower 4%.
e) The average unevenness index or roughness index for the finished surface measured
along the wheel path of each lane of the road using a bump integrator shall not exceed
2000 mm per krn.
Before applying BC layer Tack coat is applied. The main objective of tack coat is to provide
adequate interface bond between the receiving pavement surface and the new bituminous layer
being overlaid. The binder of the tack coat is not expected to penetrate into the pavement
surface and plug the voids.
28
Figure 8.6 Bituminous Concrete Layer
a) If a profile corrective course is laid to correct the cross profile of the receiving surface,
this layer of appropriate mix has to be compacted thoroughly.
b) The surface is cleaned with a mechanical room to remove loose materials and dust.
c) The prime coat and tack coat are applied as specified if the receiving surface is granular
sub-base or base course if it is a bituminous surface, a tack coat alone is sufficient.
d) The hot mix is transported to the construction site in a clean, insulated covered truck.
f) Rolling is started soon after laying the mix and compaction is to be completed before
the mix cools down to the minimum specified temperature of 100°C in the case of VG-l
0 grade and 90°C in VG-20 grade bitumen. Compaction of the BM layer and finishing
are done as described in steps.
29
CHAPTER 9
CONSTRUCTION METHODOLOGY OF RIGID PAVEMENT
The IRC recommends that for the concrete pavements of highways, the subgrade shall consist
of coarse grained soil a minimum CBR value of 8 percent and be of total 500 mrn compacted
thickness cross slope to be provided while finishing the top of the subgrade shall conformity
with the specified cross slope of the CC pavement. The permissible tolerance in surface levels
of subgrade is (+ 20 mrn and - 25 mm).
The drainage layer may be directly laid over the subgrade, however it keeping in view the
desired long life of the CC pavement it is desirable to place a suitable type of geo-filter
between the subgrade and the drainage layer. The drainage layer shall extend up to the full
formation width or up to the side drain. The top surface of the drainage layer or lower sub-base
shall also be in conformity with the specified cross slope of the CC pavement. The permissible
tolerance surface levels of sub-base is (+ 10 mm and - 10 mm).
Concreting shall not be carried out in hot weather when the air temperature is above 35 degree
and the humidity is low as accelerated setting and shrinkage of concrete may take place.
However special precautions may be taken in hot weather conditions, such as use of suitable
admixtures, chilling plant for cooling the CC mix, etc. Concreting shall not be carried out in
very cold weather also when the ambient temperature falls below 4°C, unless special measures
are taken.
Different methods may be adopted for the construction of CC pavement depending on several
factors such as the importance and magnitude of the road project.
31
CHAPTER 10
EQUIPMENT USED FOR ROAD CONSTRUCTION
After telling us about the material and their ratio used in construction work we get information
about the equipment used their uses. Detail about the equipment mostly used in construction
work is given following.
10.2 BULLDOZER
A bulldozer is a crawler (continuous tracked tractor) equipped with a substantial metal plate
(known as a blade) used to push large quantities of soil, sand, rubble, or other such material
during construction or conversion work and typically equipped at the rear with a claw-like
device (known as a ripper) to loosen.
10.3 SCRAPER
Scraper, in engineering, machine for moving earth over short distances (up to about two miles)
over relatively smooth areas. Either self-propelled or towed, it consists of a wagon with a gate
having a bladed bottom. The blade scrapes up earth as the wagon pushes forward and forces the
excavated material into the wagon.
Concrete is a mix of sand (fine aggregate), cement, gravel or crushed stone (coarse aggregate)
and water. On the other hand, mortar uses sand as the sole aggregate. As you walk around on
the road, you can see concrete everywhere.
10.7 BARRICADING