Contract Making (Cost Bidding)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Hephaestus Construction Firm

4108 A.Soriano Building


Listen better. Plan better. Build better.
Tanza, Cavite Philippines

Issue Date: October 5, 2020

Reference no. : 2012346549

Contractors: Hephaestus Construction Firm

Address: Tanza, Cavite

To Mr. Alex De Guzman


Head Manager
YMCA Apartments Estate

The contract stated that the Hephaestus Construction Firm has completed a full evaluation of the site; the following
actions have been implemented to ensure the safety and flexible workflow throughout the project period:

i. The contractors have surveyed the area and provided a foundation plan on how the project will start.
ii. Transparency of project documents such as Bidding Document, Cost of Materials, and Construction Cost.
iii. The total cost of construction is approximately ₱ 13,131,913.24 rest assured that the estimation cost of the
project based on the provided budget plan of the company.
iv. The construction period shall be of 244 days; any extension and reconstruction outside the plan shall be
accompanied with compensation and extra charges.
v. The Firm collaborates with subcontractors and suppliers for the initiation of the plan, rest assured that all
outside collaboration are valid and eligible by the contract.
vi. Collaborators and Suppliers will be noted and represented by this contract. (Logo and Name Below)
vii. When the contract is accepted, the firm will immediately proceed to the scheduled plan and assumes that
the client will uphold their responsibilities in the contract.
viii. If the contract is approved, the management will assign a contractor representative (name below). Contact
us by Cell. No. 09132345467 and hephaestussupport@gmail.com.

Mr. Lawrence Buenviaje


Executive Engineer
Hephaestus Engineering Firm
CONTRACT FOR GENERAL CONSTRUCTION
BID PROPOSAL FORM
October 5, 2020

For

YMCA APARTMENTS Inc.

The bid submission shall be made to the following 2 entities by the scheduled bid time.

Submission of Bids to ATHENA Civil Works:


Email to Engr. Elaine Lumbres at Engr.Lumbres@ACW.org.com

Submission of Bids to ARCHITECHTAS:


Email to Arch. Oliver Austria at Oliveraustria@ARCHITECHTAS.gmail.com
Bids will not be considered valid if not submitted in the above stated manner.

On or before October 8, 2020 at 3:00 P.M. – Bids will not be publicly opened.

Bidder: Engr. Mark Lawrence Q. Buenviaje

The undersigned, hereinafter referred to as the “Bidder” declares that before preparing his bid, he visited
the site and familiarized himself with all factors affecting the cost and construction. He has examined and
read all Plans, Specifications, General and Special Conditions, and other Contract Documents and all
Addenda thereto; and is acquainted with and fully understands the extent and character of the work
covered by this proposal and the specified requirements for the proposed work. He submits this Bid for the
General Construction Contract of YMCA Apartments in the Sky, as prepared by those listed below with no
unanswered questions.

Civil Engineering

ATHENA
5176 South Villa Ave.
Ternate, Cavite PH

Architecture

ARCHITECHTAS
4108 Herath Building
Naic, Cavite PH

All bids shall be for complete work in accordance with construction plans and specifications. (No partial bids
accepted).
If this Proposal is accepted by the Owner, the undersigned agrees to keep the bid in effect for sixty (60)
calendar days from the bid opening date.

The Bidder hereby proposes to furnish all necessary labor, materials, tools and equipment, together with all
other items of cost, including insurance, taxes and supervision, required for the General Construction of
YMCA Apartments in the Sky called for on the contract documents and as otherwise required for the SUM
of:

Stipulated Lump Sum Total of Contract: ₱ 13,131,913.24

Cost Breakdown:

Division 01 – General Conditions ₱1,232,752.50

Division 03 – Concrete ₱3,232,546.50

Division 04 – Masonry ₱1,300,234.12

Division 05 – Metals ₱2,232,967.34

Division 06 – Woods, Plastics and Composites ₱1,984,412.78

Division 07 – Thermal and Moisture Protection ₱850,000

Division 08 – Openings ₱250,000

Division 09 – Finishes ₱250,000

Division 10 ‐ Specialties ₱950,000

Division 22 – Plumbing ₱540,000

Division 23 – Mechanical ₱1,000,000

Division 26 – Electrical ₱650,000

Division 31 – Earthwork ₱120,000

Division 32 – Exterior Improvements ₱870,000

Allowances: Include the allowances listed in the specifications within the Stipulated Lump Sum above.

Alternates: Provide alternate amounts for the following listed alternates:

Pool Heaters ₱150,000 Fiber Duct board ₱100,000 Lightning Protection System₱150,000

Schedule: The Contractor shall prepare its Bid based upon a construction schedule from Notice to Proceed
through Substantial Completion. The construction of YMCA Apartments in the Sky is anticipated to be a six
to eight month construction project. The contractor shall include his schedule with the bid.

Proposed Project Manager: Engr. Mark Lawrence Buenviaje

Proposed Superintendent: Engr. Elaine Lumbres

The bidder shall attach resumes and similar project experience for the proposed project team
CONTRACT FOR GENERAL CONSTRUCTION
BID PROPOSAL FORM
October 5, 2020

For

YMCA APARTMENTS Inc.

BID DOCUMENT RECEIPT

The bidder acknowledges receipt of all Bid Documents as listed on the Document Control Sheets, included within this
Bid Package.

BIDDER (Hephaestus Construction Firm):

By: Engr. Mark Lawrence Buenviaje

Title: YMCA Apartments in the Sky

Date: OCTOBER 5 2020

Witness: Mr. Alex De Guzman (Client), Atty. Niel Luna, Engr. Elaine Lumbres (ATHENA)
YMCA Apartments in the Sky

INSTRUCTIONS TO BIDDERS

Bid Instructions:

1. The Bidder shall study and compare the Bid Documents (specifications, drawings, geotechnical report) with each other,
and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for
which the Bid is submitted, shall examine the site and local conditions, and shall immediately report to the Landscape
Architect errors, inconsistencies, or ambiguities discovered prior to submitting bids.

2. Bidders requiring clarification or interpretation of the Bid Documents shall make a written Request for Information. Only
RFI’s from the Bidder will be accepted and RFI’s direct from sub‐bidders will not be addressed. Requests for Information
shall be submitted no later than October 15, 2020 and be emailed to to Arch. Oliver Austria
Oliveraustria@ARCHITECHTAS.corp.

3. Clarifications and corrections of the Bid Documents will be made by Addendum. Clarifications and corrections
made in any other manner will not be binding.

4. Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder
shall acknowledge their receipt in the Bid.

5. The Bidder’s attention is called to the Report of Geotechnical Exploration contained herein. All construction shall be
completed in accordance with this report. The entire site is available to any bidder for surface or subsurface investigation.
In addition, Geotechnical Exploration reports identify certain ground water depths. The bidders are cautioned that these
depths may not be representative of conditions as they exist today and should be field verified.
6. The bidder shall include any allowances in the total stipulated lump sum bid amount.

7. The Contractor is required to perform all tests as required by the County and applicable utility companies prior to project
acceptance.

8. The contractor shall apply for, secure and pay for all construction permits, building permits, right of way construction
permits, electrical permits, meter, installation fees, and electrical inspection fees, as applicable.

9. The Contractor shall complete his work in a professional and workman like manner typical of his industry. There shall
be no sections or parts missing. Further, the work shall be complete and able to function for its intended use. The
work must be continuous.

10. The Contractor’s Superintendent shall be onsite during hours of construction for the duration of the project.

11. Where specific products, manufacturers or suppliers are indicated or specified by name, these items are to be included
within the Contractor’s bid. Substitution of these items will only be considered as stipulated under the conditions for
product substitutions.

12. All other instructions to Bidders shall be in accordance with AIA document A701‐1997.

END OF INSTRUCTIONS TO BIDDERS


Hephaestus Construction Firm

Listen better. Plan better. Build better. 4108 A.Soriano Building

END OF INSTRUCTIONS TO BIDDERS Tanza, Cavite Philippines

To Mr. Alex De Guzman

Kindly email this letter back to us using the same email format to indicate your acceptance of this offer. We
greatly appreciate your time in browsing the contract and would love to work for you Sir/Maam.

We are confident to serve you with the highest amount of professionalism and quality work. We look
forward to our contribution to a great start of business. Hoping that we have a peaceful and proper
agreement; from start to the end.

Engr. Elaine Lumbres Engr. Mark Lawrence Buenviaje Arch. Oliver Austria
Lead Engineer Executive Engineer Lead Architech
ATHENA Inc. Hephaestus Engineering Firm ARCHITECHTAS

I ACCEPT THE OFFER AS STATED ABOVE,

NAME:_______________________________ SIGNATURE:_____________________

DATE: ___/___/____