Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ETESA - Project Profiles 2016-2017

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Empresa de Transmisión Eléctrica, S.A.

REPUBLIC OF PANAMA

INFORMATION PACKAGE OF PROJECT

January 2016
ESTIMATED TENDERS PROGRAM

The projects listed below refer to projects with an estimated investment amount
greater than US $50 million and an estimated starting execution for 2016 and 2017
fiscal years.
All these projects are emblematic for the current administration led by President Juan
Carlos Varela, due to its high social impact for the country, helping to improve the
quality of life of thousands of Panamanians and economic development in various
areas of the country.

Future Tenders 2016 2017


Panamá II – Chepo – June
Metetí line and associated
substations.
Sabanitas – Panamá III February
line and associated
substations.
Panamá III 230 / 115 KV April
substations.
Chiriquí Grande – March
Panamá III 500 KV line
design and associated
substations.

2|Página
PANAMÁ II – CHEPO – METETÍ LINE AND ASSOCIATED
SUBSTATIONS

TYPE OF PROJECT
230KV Transmission Line
and Chepo, Metetí
Substations.

PROJECT COST

B/. 103,633.000

PROJECT STRUCTURE
There will be a design and construction bid that will include
environmental, sociological, operating and coordination studies.

Project Summary

In the document published by The Secretaría National de Energía (SNE),


"Definition of Policies and Criteria for the Review of the National Interconnected
System 2015 Expansion Plan" it is established that there must be an electrical
integration of the far East Panama Sector. That requires that the electrical
interconnection of Darién province must be completed in a short period with the
construction of a transmission line of 230 KV starting from Panama II substation.
This project requires the construction of the following infrastructure:

a. Increase the capacity of the existing Transmission Line Panama II - Chepo.


b. From the new Chepo substation to Bayano substation, the existing line will
remain as is.
c. New 170 km, 230KV, 300MVA transmission line from Chepo substation –
Meteti substation, this will be a single power circuit in towers of double circuit
capacity.
d. New 230 KV Chepo four bays substation, in scheme of one and medium hybrid
switch.
e. New 230 KV Meteti two bays substation, in scheme of one and medium hybrid
switch with two bays.

Program Date:

June, 2016.

3|Página
SABANITAS – PANAMÁ III LINE AND ASSOCIATED
SUBSTATIONS

TYPE OF PROJECT
230 KV Transmission Line
and Substations

PROJECT COST

B/. 105,771,000

PROJECT STRUCTURE
There will be a design and construction bid that will include
environmental, sociological, operating and coordination studies.

Project Summary

Because the near future integration of new natural gas generation plants at
Colon province in the Atlantic, it is required that the existing transmission
system between the Panama and Colon provinces to be reinforced to transmit
this additional generation. Then it is necessary to construct
a new transmission line from the Colon area, this new 230 KV transmission
line will be built from the town of Sabanitas to the city of Panama (Sabanitas-
Panama III 230 KV); which requires the following works:
a. Line Sabanitas - Panama III 230 KV: line of 230 KV, double circuit, it will
have an approximate length of 50 km.
b. Expansion of the 230 KV Sabanitas substation: Two (2) new bays and
switches for connecting the 230 KV Panama III substation double-circuit
transmission line will be required.
c. Expansion 230 KV Panama III substation bays.

Program Date:

February, 2017.

4|Página
PANAMÁ III 230 / 115 KV SUBSTATION

TYPE OF PROJECT
230/115KV. Panama III
Substation

PROJECT COST

B/. 63,443,633

PROJECT STRUCTURE
There will be a design and construction bid that will include
environmental, sociological, operating and coordination studies.

Project Summary

This project consists on the construction of a new 230/115 KV Panama III


substation, breaker and a half circuit breaker layout in a hybrid distribution
scheme, that is switches, breakers, blades and CTs shall be SF6 encapsulated,
the substation yard will be located in the Mocambo sector near Panama city.

This substation will serve as an interconnection point for new transmission


lines for the distribution companies that feed the demand of through new
smaller substations, and also connecting transmission lines coming from the
West (LT-2 and LT-3) and the line from Sabanitas substation coming from
Colon, where the future thermal power plants will be installed.

Program Date:

April, 2017.

5|Página
CHIRIQUÍ GRANDE – PANAMÁ III 500 KV LINE AND
ASSOCIATED SUBSTATIONS

TYPE OF PROJECT
500 KV Transmission Line
and 500/230KV.
Substation

PROJECT COST

B/. 474,982,000

PROJECT STRUCTURE
There will be a design and construction bid that will include
environmental, sociological, operating and coordination studies.

Project Summary

Due to the construction of new hydroelectric, solar, wind and thermal power stations in
the western side of the country, it´s necessary to increase the transmission capacity of
the electric power lines originating at Chiriquí and Bocas del Toro towards the
metropolitan area of Panama and Colon cities. Given the increase in load in the
metropolitan areas, we require the studies for design and construction of a Fourth
transmission line from Bocas del Toro province, beginning at a new 500KV Chiriquí
Grande substation, to the new 500KV Panama III substation. The following works are
required for the operation of this project:

a. 1280MVA, 500 KV Transmission line with an approximate length of 330 km.


b. Construction of a new 500/230 KV Chiriquí Grande substation, build an extension of
the 500/230 KV Panama III substation and the installation of Static-Var Compensator of
+150 / - 30 MVAR at Panama III substation.

Programing Date:

March, 2017.

6|Página

You might also like