Professional Documents
Culture Documents
Safety of Scaffolding and Tower Cranes in Construction Sites During Typhoon Season
Safety of Scaffolding and Tower Cranes in Construction Sites During Typhoon Season
27 May 2019
Dear Sir/Madam,
Safety of Scaffolding
2. From past experience, most of the incidents involving the collapse of or related to
scaffolding could have been avoided if the following site measures had been taken:-
(a) sufficient ties of adequate strength are provided to secure the cantilever
portion at the topmost floor;
(b) the height above the topmost floor should not be over-extended (maximum
one floor);
(c) adequate putlogs, ties, struts, bracing and steel brackets are provided to secure
the scaffolding framework;
(d) plastic sheeting should be removed and the scaffolding above the topmost
floor should be lowered to not more than half of the floor height under safe
circumstances when a tropical cyclone warning signal or a strong monsoon
signal is announced; and
(e) no loose materials should be placed on/near any scaffolding, or near the
periphery of the site.
7/F-9/F Cityplaza Three, 14 Taikoo Wan Road, Taikoo Shing, Hong Kong. 香港太古城太古灣道 14 號太古城中心三座 7 樓至 9 樓
-2-
3. Please impress upon your site supervision staff on the importance of the safety of
scaffolding and ensure that the above site measures are taken in all scaffolding. When the
building works have been completed, the related scaffolding should be dismantled as soon
as possible. Also, any scaffolding which remains idle should be promptly removed.
4. With regard to the safety of tower cranes in construction sites during typhoon,
suitable safety precautionary measures should be drawn up with regard to the types of crane
towers being used, surrounding site conditions and the tower crane manufacturers’
recommendations. In general, the following safety precautionary measures against strong
wind may be taken:
(a) The main jib should be slewed to the side of the tower away from the wind,
and then put into free slew. However, care must be taken to ensure that the jib
would not collide with adjacent structures or overhead power cables;
(b) The trolley of the crane with horizontal trolley jib should be placed near to the
tower at minimum radius and the hook should be raised to its highest position;
(c) The jib of luffing jib crane (including the articulated jib crane) should be
brought to a position at 15o to the horizontal or other position according to the
manufacturer’s recommendation and the hook should be raised to its highest
position;
(d) If the manufacturer recommends to tie the jib and/or the hook to the specified
anchorage points above the slewing ring, it should be made sure that the tie
wires are of adequate strength and are tightened up properly; and
(e) If situation warrants, the height of the crane tower above the topmost floor
should be lowered as far as practicable.
6. If there are emergency incidents happened on site during the course of typhoon,
staff of this Department may need to contact the authorized person, registered structural
-3-
engineer and/or registered geotechnical engineer for timely handling those situations.
Hence, these registered building professionals are requested to inform this Department as
soon as possible if there are any changes of their emergency contact telephone number or fax
number, by using the letter attached to PNAP ADM-3.
7. After lowering of the typhoon signals, the registered contractors should inspect all
areas of their construction sites as early as possible, and carry out necessary remedial works
immediately if damages are found. Before the resumption of the construction works, it
should make sure that the sites are in a safe condition.
8. I would like to remind you, as a responsible member of the Hong Kong construction
industry, of your responsibilities under regulations 37(1) and (2) and 41(1) of the Building
(Administration) Regulations. For safety issues regarding scaffolding and tower cranes,
your attention is drawn to the Code of Practice (CoP) for Bamboo Scaffolding Safety1, the
Guidelines on the Design and Construction of Bamboo Scaffolds 2 , the CoP for Site
Supervision 2009 3 , the CoP for Safe Use of Tower Cranes 4 and the CoP in times of
Typhoons and Rainstorms 5 .
Yours faithfully,
1
https://www.labour.gov.hk/eng/public/os/B/Bamboo.pdf
2
https://www.bd.gov.hk/doc/en/resources/codes-and-references/code-and-design-manuals/GDCBS.pdf
3
https://www.bd.gov.hk/doc/en/resources/codes-and-references/code-and-design-manuals/SS2009_e.pdf
4
https://www.labour.gov.hk/eng/public/os/B/crane.pdf
5
https://www.labour.gov.hk/eng/public/wcp/Rainstorm.pdf