Standard CHB Sizes Are From Thicknesses of 100mm (4"), 150mm (6") and 200mm (8") X Height of 200mm (8") X Length of 400mm (16")
Standard CHB Sizes Are From Thicknesses of 100mm (4"), 150mm (6") and 200mm (8") X Height of 200mm (8") X Length of 400mm (16")
Standard CHB Sizes Are From Thicknesses of 100mm (4"), 150mm (6") and 200mm (8") X Height of 200mm (8") X Length of 400mm (16")
Cement mortar is a mixture of cement, sand and water. It is used as bonding materials in installing
masonry blocks and various plastering work. Determining cement mortar for CHB is normally by (a)
VOLUME and (b) by AREA method.
*this basically means for every 4” CHB one would need 0.0035m3 of mortar and for 6” it
would be 0.0058 m3
In determining the number of cement and sand for mortar and plaster in cubic meters
refer to the table below:
Table 1
APPLICATION PROBLEM 02: Using the answer in the Application Problem 01 determine
the number of cement and sand needed for the CHB calculated above.
Step 01: Determine the total volume of mortar needed for the calculated number of
CHB
Step 02: Determine the number of cement and sand using the table provided above. If
there are is no Class Mixture provided always use CLASS B as a default value.
NCement = 12 bags/m3 x 13.282m3 = 159.384 bags of 40-kg cement or 160 bags (ANSWER)
NSand = 1cu.m./m3 x 13.282m3 = 13.282 m3 sand or 13.5m3 (ANSWER)
In applying the area method the only thing that you will need is the given table.
Table 2
Estimating cement mortar for plastering can be done by Volume method and Area method.
In plastering by volume method is assumed that the average thickness of plaster is 16mm or 0.016m for
each face of wall.
APPLICATION PROBLEM 03: Using the answer in the Application Problem 01 determine
the number of cement and sand needed for plastering the wall.
Step 02: Assuming an average thickness of 16mm for the plaster determine the volume
Vol = Awall x 0.016m
Vol = 366.36 m2 X 0.016m
Vol = 5.86176 m3
Step 03: Using “Table 1” determine the number of cement and sand
Table 2
Table 3
Cement in Bags
Class
Thickness of Plaster
Mixture
8mm 12mm 16mm 20mm 25mm
A 0.144 0.216 0.288 0.36 0.45
B 0.096 0.144 0.192 0.24 0.3
C 0.076 0.108 0.144 0.18 0.225
D 0.06 0.09 0.12 0.15 0.188
Sand 0.008 0.012 0.016 0.02 0.025
APPLICATION PROBLEM 04: Using the answer in the Application Problem 01 determine
the number of cement and sand needed for plastering the wall using area method with
16mm plaster
Step 02: Using class B mixture determine the number of cement and sand directly using
table 3 of 16mm plaster.
APPLICATION PROBLEM 05: Prepare a simple bill of materials for a wall fence(4” CHB) of
height of 3-m and a length of 5m. – use volume method for all
Solution:
1. Determine the number of CHB
Awall = (5m) (3m) = 15m2
NCHB = (15m2) (12.5pcs/m2) = 187.5 pcs or 188 pcs CHB
Water = 11 x 6 = 66 liters
SAMPLE BILL OF MATERIALS of the answers:
TOTAL: 7180
Activity: For the septic tank design from the 1st activity prepare a bill of materials
(Cement, sand, gravel, CHB, water) if the walls are to be made up of CHB and the top
and bottom floor of concrete. Submit the work for both lecture and lab if you have
laboratory. For your lecture use AREA METHOD and for your laboratory use VOLUME
METHOD. (20 points)