The document calculates the Industrialized Building System (IBS) score for a construction project. It is divided into three parts: structural elements, wall systems, and other simplified solutions. Part 1 achieves a score of 47.5% for elements like precast concrete beams and roof trusses. Part 2 scores 13.5% for internal and external precast walls. Part 3 scores 16% based on the compliance of beams, columns, walls, slabs, doors, and windows with standards. The total IBS content score is calculated to be 77%.
The document calculates the Industrialized Building System (IBS) score for a construction project. It is divided into three parts: structural elements, wall systems, and other simplified solutions. Part 1 achieves a score of 47.5% for elements like precast concrete beams and roof trusses. Part 2 scores 13.5% for internal and external precast walls. Part 3 scores 16% based on the compliance of beams, columns, walls, slabs, doors, and windows with standards. The total IBS content score is calculated to be 77%.
The document calculates the Industrialized Building System (IBS) score for a construction project. It is divided into three parts: structural elements, wall systems, and other simplified solutions. Part 1 achieves a score of 47.5% for elements like precast concrete beams and roof trusses. Part 2 scores 13.5% for internal and external precast walls. Part 3 scores 16% based on the compliance of beams, columns, walls, slabs, doors, and windows with standards. The total IBS content score is calculated to be 77%.
The document calculates the Industrialized Building System (IBS) score for a construction project. It is divided into three parts: structural elements, wall systems, and other simplified solutions. Part 1 achieves a score of 47.5% for elements like precast concrete beams and roof trusses. Part 2 scores 13.5% for internal and external precast walls. Part 3 scores 16% based on the compliance of beams, columns, walls, slabs, doors, and windows with standards. The total IBS content score is calculated to be 77%.
Download as DOCX, PDF, TXT or read online from Scribd
Download as docx, pdf, or txt
You are on page 1of 2
IBS CALCULATION
ELEMENTS AREA IBS COVERAGE IBS SCORE
(m2) FACTOR (%) Part 1 : Structural Elements 1. Precast concrete beam + In-situ concrete using steel formworks + 90.95 0.9 0.5 0.9 0.5 50 Precast half slabs floor. 22.5 2. Roof truss- Prefabricated timber 90.95 1.0 1.0 0.5 50 roof truss 0.5 25 Roof area = Total Part 1 181.9 1.00 47.5 ELEMENTS LENGTH IBS COVERAGE IBS SCORE (m) FACTOR Part 2 : Wall Systems 1. Internal wall using Precast concrete panel 39.1 0.5 0.65 0.5 X 0.65 X 20 = 6.5
2. External wall using 21 1.0 0.35 1 X 0.35 X 20
Precast block works =7 Total Part 2 60.1 1.0 13.5 ELEMENTS COVERAGE IBS SCORE Part 3 : Other Simplified Solutions 1. Beams : 60% complies 60% 2 with MS 1064 Part 10:2001 2. Columns : 100% complies 100% 4 with MS 1064 Part 10:2001 3. Wall : Less than 50% 50% 0 complies with MS 1064 Part 10:2001 4. Slab : less than 50% 50% 0 complies with MS 1064 Part 10:2001 80% 4 5. Doors: 80% complies with MS 1064 Part 4:2001 0% 0 6. Windows : 0% complies with MS 1064 Part 5:2001 7. Horizontal repetition of 100% 6 structure = 100% Total Part 3 16 IBS CONTENTS SCORE OF 77 PROJECT ( Part 1 + Part 2 + Part 3 ) CONCLUSION
The conclusion from this mini project is we are able to make
house plan through autocad. From autocad, we are also able to make a mini house from the plan that we make through the autocad. This mini project make our team and responsibility increase as we are doing it together because it was a group assigment.