Open Pit Planning and Design: G.A. F G C. D, J
Open Pit Planning and Design: G.A. F G C. D, J
Open Pit Planning and Design: G.A. F G C. D, J
1
OPEN PIT PLANNING AND DESIGN
G.A. F OURIE AND G ERALD C. D OHM , J R .
13.1.1.1 Introduction
An open pit mine is an excavation or cut made at the surface
of the ground for the purpose of extracting ore and which is
open to the surface for the duration of the mine’s life. To expose
and mine the ore, it is generally necessary to excavate and relo-
cate large quantities of waste rock. The main objective in any
commercial mining operation is the exploitation of the mineral
deposit at the lowest possible cost with a view of maximizing
profits. The selection of physical design parameters and the
scheduling of the ore and waste extraction program are complex
engineering decisions of enormous economic significance. The
planning of an open pit mine is, therefore, basically an exercise
in economics, constrained by certain geologic and mining engi-
neering aspects.
Several factors are significant indicators of economic and
technological trends in surface mining. Among these are increas-
ing production, a shift in emphasis from underground to surface
mining, a decline in ore grade and quality of some crude materi-
als, and, with few exceptions, an increase in productivity of labor.
Increasing production is the result of a growing demand for
more mineral commodities, induced by an increase in population
and per capita consumption.
Paradoxically, productivity has increased even with declin-
ing grade and quality, which is indicative of the rapid technologi-
cal improvement taking place in open pit mining techniques.
This pattern of change has permitted production from many
formerly uneconomic mineral resources occurring near the sur-
face at a time when higher-grade ores are inadequate to meet
increasing demand.
Fig. 13.1.1.1. Diagrammatic presentation of the design process.
It is generally conceded that surface mining is more advanta-
geous than underground mining in terms of recovery, grade
control, economy, flexibility of operation, safety, and the work- angles, etc. The economics of the mining program, however,
ing environment. There are, however, many deposits that are too depends upon the choice of mining ratio, production rates, and
small, irregular, and/or deeply buried to be extracted economi- equipment, all of which are determined by the mining engineer.
cally by surface mining methods. Furthermore, even where min-
eralization extends to a greater depth in open pit mines, the 13.1.1.2 Open Pit Terminology
rapidly increasing amount of overburden to be handled imposes Persons closely associated with open pit mines have coined
economic limits beyond which mining must either be abandoned terms or phrases for certain operations or for defining commonly
or converted from surface to underground operations. The con- occurring geometric parameters in open pit mining. The follow-
clusions, although valid, are sometimes outweighed by a new set ing are terms that commonly occur in open pit mine planning
of factors that arise from differences in the physical character and are used throughout this chapter. These terms are illustrated
of mineral deposits available for future exploitation and from in Fig. 13.1.1.2, which shows a pit section through an idealized
changes in technology, markets, and public policy. tabular ore body.
Open pit design is conducted in several stages. They consist, A bench may be defined as a ledge that forms a single level
technically, of devising a scheme or set of alternative schemes, of operation above which mineral or waste materials are mined
followed by an evaluation and selection of the optimum scheme, back to a bench face. The mineral or waste is removed in succes-
as illustrated in Fig. 13.1.1.1. sive layers, each of which is a bench. Several benches may be in
The most economic final pit design often depends on factors operation simultaneously in different parts of, and at different
that are largely outside the mining engineer’s control, such as elevations in the open pit mine.
the geometric outline of the ore body, the distribution of ore The bench height is the vertical distance between the highest
within the ore body, topography, maximum allowable slope point of the bench, or the bench crest, and the toe of the bench.
1274
OPEN PIT PLANNING AND DESIGN 1275
exploration. Decisions regarding pit size and layout, production
rate, and the mineral processing flowsheet are critically depen-
dent on exploration data input. Procedures and particulars of
mineral prospecting and exploration are provided in Section 4
and of project geology in Section 5.
A successful exploration program culminates in drilling and
sampling information, useful in establishing mine operation pa-
rameters, geotechnical design, geohydrologic conditions, and
mineral processing or metallurgical extraction. Two of three—
geotechnical and geohydrologic investigations—warrant further
discussion here. For detailed coverage of geomechanics, see Sec-
tion 10.
Geotechnical Investigations. While soil masses are often ho-
mogeneous and relatively isotropic, this is rarely true of rock
masses. The main reason for this is the presence of ubiquitous
Fig. 13.1.1.2. Section through an open pit in an idealized tabular discontinuities in rock masses compared with soils. The behavior
ore body.
and stabilities of rock masses are controlled mainly by the nature
and orientation of these discontinuities, while the stability of soil
masses is controlled mainly by the strength of the intact material.
The importance of geotechnical and geohydrologic factors
on open pit mining operations has been a very popular topic
The bench height is normally governed by the specifications of among researchers and cannot be overemphasized.
operating machines, such as drills and shovels, and by govern- However, there is no definite system available prescribing
ment mining regulations. geotechnical data-collection procedures; for this reason, mining
The bench slope is the angle, measured in degrees, between companies seldom take into account geotechnical considerations
the horizontal and an imaginary line joining the bench toe and during the initial exploration stage of the investigations, resulting
crest. in drill cores being disposed of shortly after completion of the
Pit limits are the vertical and lateral extent to which the open drilling program. Geotechnical engineers are often consulted at
pit mining may be economically conducted. The cost of removing an advanced stage of project evaluation, resulting in additional
overburden or waste material vs. the minable value of the ore is expenditures in order to obtain sufficient information.
usually the prime factor controlling the limits of the pit. Other Requirements for effective geotechnical drilling are briefly
factors that can influence pit limits are existing surface infra- as follows:
structures, such as townships, rivers, etc. 1. Boreholes must be cored from as close as possible (or
In order to enhance the stability of a slope within the pit— practicable) to surface through the overburden to at least 35 ft
and for safety reasons— berms may be left. A berm is a horizontal (10 m) into the footwall. If there is any suspicion of permeable
shelf or ledge within the ultimate pit wall slope. The berm inter- zones at greater depth, the boreholes should be extended.
val, berm slope angle, and berm width are governed by the 2. Cores should preferably be at least 2 3/8 in. (60 mm)
geotechnical configuration of the slope. The overall pit slope in diameter and drilled with triple-tube core barrels to ensure
angle is the angle at which the wall of an open pit stands, as minimal core disturbances.
measured between the horizontal and an imaginary line joining 3. In many cases, it may be desirable to drill inclined rather
the top bench crest with the bottom bench toe. than vertical holes for the purposes of
For the duration of open pit mining, a haul road must be a. Orientating the core, either from the bedding traces or
maintained into the pit. A spiral system is an arrangement by the use of a core orientation.
whereby the haul road is arranged spirally along the perimeter b. Intersecting steeply dipping joints, which are common
walls of the pit so that the gradient of the road is more or less in flat-lying sediments and which are poorly sampled by vertical
uniform from the top to the bottom of the pit. A zigzag or holes.
switchback system is an arrangement in which the road sur- The density of geotechnical drilling will be dependent pri-
mounts the steep grade of a pit wall by zigzagging, generally on marily on the degree of variability of the material over the pro-
the footwall side of the pit. The choice of spiral or zigzag is posed mining area.
dependent upon the shape and size of the ore body, truck eco- Drilling must be supervised by an experienced exploration
nomics, and pit slope stability. geologist to record hole depths, core losses, and any other signifi-
Haul road width is governed by the required capacity of the cant aspects (e.g., water losses) during drilling. Continuous liai-
road and type of haulage unit. The grade may be defined as the son between the exploration geologist and the mine planning
inclination of the road in terms of degrees from the horizontal engineer is important to ensure that all mining-related data are
or percentage of rise to the horizontal. collected.
The angle of repose or angle of rest is the maximum slope at As each core run is recovered, it should be carefully trans-
which a heap of loose material will stand without sliding. ferred to the core tray and allowed to dry before being
The suboutcrop depth represents the depth of waste that has 1. Photographed in color, ensuring that the core trays are
to be removed before any ore is exposed. This waste is often adequately labeled and oriented.
referred to as preproduction stripping. 2. Logged in detail for the following features:
a. Rock type.
b. Degree of weathering.
13.1.1.3 Exploration Input for Open Pit Planning c. Description of weak rocks or weak zones.
In addition to defining the extent and value of a mineral d. Location, description, and orientation of any breaks
deposit, exploration supplies data vital to mine development and in the core.
1276 MINING ENGINEERING HANDBOOK
3. Sampled for materials testing.
Color photographs are an invaluable record of the original
core condition. The core, even if available at a later date, may
have deteriorated or be incomplete as a result of sampling.
Geologic data should be presented in graphical form to high-
light the similarity or variations in properties across the proposed
mining area. Rock hardness and bedding, or joint frequency, can
be plotted in histogram form along the borehole paths. Such
plots can be made with an exaggerated vertical scale to provide
adequate detail, but it is also important to plot natural-scale
sections in order to place the data into its actual physical content.
A basic program of materials testing is required to determine
significant material properties and to confirm visual estimates
during core logging. The relevant testing for open pit mines
includes
1. Slaking and classification tests on weathered or suspected Fig. 13.1.1.3. Block model of an ore body.
weak materials that could influence dump and pit stability.
2. Shear strength tests on soft or weak layers, particularly
in the floor, and on overburden materials showing strong slaking
behavior, for use in analysis of pit stability.
3. Compressive strength, point load strength, and drillabil-
ity tests to provide information for estimation of overburden and
ore excavation characteristics.
Geohydrologic Investigations. The presence of groundwater
in the rock mass surrounding an open pit has a detrimental effect
on mining operations for the following reasons:
1. Water pressure reduces the stability of pit slopes by reduc-
ing the shear strength of potential failure surfaces. Water pres-
sure in tension cracks, or similar near-vertical fissures, reduces
stability by increasing the forces tending to induce sliding.
2. High moisture content results in an increased unit weight Fig. 13.1.1.4. Overall stripping ratio representation.
of the rock and hence gives rise to increased transport costs.
Changes in moisture content of some rocks, particularly shales,
can cause accelerated weathering with a resultant decrease in
stability. Both methods abound with practical difficulties; however,
3. Freezing of groundwater during winter can cause wedg- because of the very important influence of water pressure on
ing in water-filled fissures due to temperature-dependent volume slope stability, it is essential that the best possible estimates of
changes in the ice. Freezing of surface water on slopes can block these pressures be available before a detailed open pit stability
drainage paths, resulting in a buildup of water pressure in the analysis is attempted.
slope with a consequent decrease in stability.
4. Erosion of both surface soils and fissure infilling occurs
as a result of the velocity of flow of groundwater. This erosion
13.1.1.4 Bench Plan Preparation and Presentation
can give rise to a reduction in stability and also to silting up of A key point in the design and operation of a modern mining
drainage systems. operation is the construction of what is called an ore body model
5. Discharge of groundwater into an open pit gives rise to or block model. This model is a representation of reality con-
increased operating costs because the water must be pumped structed from predicted information. The blocks involved are
out, and also because of the difficulties of operating heavy equip- merely subsets of the overall model that allows manipulation of
ment on very wet ground. Blasting problems and blasting costs the contained information on a local scale. In general, block
are increased by wet blastholes. models enable mine planners to effectively select the most prom-
6. Liquefaction of overburden soils or waste dumps can pre- ising means of extracting the ore both physically and economi-
vail where water pressure within the material rises to the point cally. The uses of a block model can be quite diversified, but one
where the uplift forces exceed the mass of the soil. This can must realize that a single model that satisfies all curiosities and
occur if drainage channels are blocked or if the soil structure forms of expertise is difficult to construct.
undergoes a sudden volume change, as can happen under earth- Because material removal or mining takes place along a
quake conditions. particular bench, it is firstly important to prepare a series of
By far, the most important effect of the presence of ground- bench plans that, when combined, forms the overall block plan
water is the reduction in stability resulting from water pressures of the modeled ore body. This is illustrated in Fig. 13.1.1.3.
within discontinuities in the rock mass. With the assistance of modern computer facilities, sophisti-
There are two possible approaches to obtaining data on water cated and complex bench plans can be prepared.
pressure distribution within a rock mass:
1. Deduction of the overall groundwater flow pattern from 13.1.1.5 Stripping Ratio Considerations.
consideration of the permeability of the rock mass and sources
of groundwater. The parameter known as the stripping ratio is almost univer-
2. Direct measurement of water levels in boreholes or wells sally used and represents the amount of uneconomic material
or of water pressure by means of piezometers installed in bore- that must be removed to uncover one unit of ore. Fig. 13.1.1.4
holes. represents an idealized open pit ore body, dipping at angle a.
OPEN PIT PLANNING AND DESIGN 1277
Fig. 13.1.1.5. Declining stripping ratio method. Fig. 13.1.1.6. Increasing stripping ratio method.
The initial cutoff grade does not take into account primary
stripping and associated waste. Using the ratios established in
the first pass, the cutoff grade is recalculated.
Cutoff grade calculations are based on total operating costs,
utilizing the overall ratio of tons of waste to tons of potential ore
(Table 13.1.2.3).
production cost
grade =
value × % recovery
$24.80/ton
(13.1.2.2)
= $25/lb × 0.90
= 1.10 lb/ton (0.55 kg/t)
1.10 lb/ton
= = 0.055%, say, 0.06%
EVALUATION PARAMETERS. There are physical and finan- 20 (conversion factor)
cial evaluation parameters to be imposed.
Physical—A geotechnical evaluation was undertaken that The higher cutoff grade creates a new category of material,
indicated the overall pit slopes in Table 13.1.2.1 as acceptable between 0.040% and 0.060%, which is classified as low grade.
for design purposes. Under certain circumstances, it may be economically advanta-
The specific gravity SG of representative rock samples was geous to process this material. This detail is reviewed later under
tested yielding an average value of 2.00. To convert the volume marginal analysis.
of rock to be mined and milled, a tonnage factor TF is calculated: D RILLHOLE E VALUATION. A simple approach for illustra-
tion is to use the polygon method to assign an area of influence
2000 lb/ton for each drillhole. With the drilling grid on 200-ft (60-m) centers,
TF = = 16 ft3/ton (0.50 m3/tonne) the area of influence is 40,000 ft2 (3720 m2). Dividing the area
SG (2.00) × 62.4 lb/ft3
by the tonnage factor, one finds:
(13.1.2.1)
40,000 ft2
Initial metallurgical flowsheets and design criteria were also = 2500 tons/vertical ft (7440 t/m)
developed. The process is to be conventional acid leach-solvent 16 ft3/ton
extraction with an average recovery of 90%.
Financial— As a starting point for the calculations, regional For simplicity, the deposit is assumed to be dry. The weight
operating and capital costs for operations having similar size, of water, when present, must be added to the weight of the
geology, and equipment are used. Amenability studies on which rock. The total weight will then be used in the determination of
to base process specifications, reagent consumption, and product operational costs, disposal considerations, and capital require-
recovery are performed. ments.
Regional operating economics (expressed in dollars/ton) in- All drillholes are evaluated from top to bottom. The eco-
clude primary stripping (0.65); associated waste and ore mining nomic bottom limit of mining is the depth at which the maximum
(1.50); milling (7.00); direct costs such as salaries, utilities, main- net profit is realized. No credit is assigned to any values con-
tenance, consumables, etc. (3.50); and indirect costs such as tained in material below the cutoff grade as they, in themselves,
taxes, interest, depreciation, and corporate overhead (2.80). cannot justify any change in pit outline. This process is shown
For purposes of this example, the selling price of the recov- in Fig. 13.1.2.3.
ered uranium oxide is set at $25/lb. The evaluation is repeated for all drillholes. This evaluation
The drillhole grid is on 200-ft (60-m) centers, sufficient to should also include those holes that obviously carry a negative
outline the mineralized zone and associated overburden. value. In the expansion of the total reserves, many instances will
BREAKEVEN ANALYSIS. Establishing a cutoff grade for ore be found where profitable holes will offset some negative values.
is necessary for drillhole evaluations. The process involves two The value of each must be known before a final determination
steps and utilizes a tabulation of the mineral inventory in the can be made. The complete analysis is essential in establishing
area being considered for development (Table 13.1.2.2). the ultimate pit limits, as discussed next.
1280
Overall pit slope angles are not only a function of the actual
rock conditions encountered and the total vertical lift but also
of the duration of exposure and the amount of water indigenous
to or added to the formation. The effects of the latter two can
be lessened by timely back filling and by either or both a mine
dewatering program and a surface runoff diversion system.
Where variable heights affect the ultimate design, a graph can
be utilized relating height to slope angle at a safety factor where
the slope is close to failure but does meet risk standards set
within corporate guidelines.
In the example utilized herein, all slope angles are a direct
Fig. 13.1.2.4. Ore block smoothing. function of height (Fig. 13.1.2.5). It must be remembered that
in rough terrain, it is the difference in elevation from the surface
to the economic bottom of the pit that ultimately establishes the
final slope angle.
O PEN P IT D ESIGN. The ultimate limits of the pit do not Design— One must provide adequate operating room for ma-
precisely follow the economic limits established in the drillhole neuverability and mining flexibility in ore/waste segregation re-
evaluation. Refinements to the pit outline result from various quirements. A 0.5:1 pit slope between benches is used for design
working, financial and safety constraints. In practice, close- purposes. The desired overall slope angle is achieved by adjusting
spaced development drilling will eventually be undertaken to the widths of the benches:
better define pit boundaries and to develop information on where
to commence mining activities. The bottom of mining may also horizontal displacement
be affected by the adjacent drillholes if bottom ore elevations bench width = (13.1.2.3)
vary to any appreciable extent. no. benches required
Operation Efficiency—Operational efficiency increases ad- vertical height × (overall slope ratio –
vantageously as the horizontal section is smoothed by eliminat- slope ratio between benches)
ing projections and generally irregular configurations. The drill-
hole evaluation helps with the smoothing of the pit walls and = (vertical height ÷ bench height) – 1
inclusion of waste by showing where positive values offset nega-
tive values. The objective is to maximize the total value and, at In this example,
the same time, provide adequate access and working room (Fig.
13.1.2.4). 500 ft × (1.5 – 0.5) 500 ft
Overall Pit Slope—Use the steepest possible pit slope with width = =
(500 ft ÷ 50 ft) – 1 9 benches
regards to the safety factor deemed acceptable for the particular
pit. = 56 ft (17m)
OPEN PIT PLANNING AND DESIGN 1281
Table 13.1.2.4. Marginal Analysis Ore Reserves Table 13.1.2.5. Optimized Net Profit
13.1.2.12 and 13.1.2.13). A property should not be dependent Rolling resistance is the measure of force required to over-
on one prime earthmover because of downtime considerations come the retarding effect between the tires and the ground.
and reduced flexibility in the operation, and to reiterate, equip- RoRi is primarily the cumulative effect of vehicle weight, tire
ment should be standardized whenever possible. Therefore, the penetration, and road grades.
following examples consider only two or more of the same shov- Vehicle weight is the primary factor in the amount of force
els as viable options. required to overcome RoRi. Using level, compacted roads as the
It should be noted that the production from a nominally base, the RoRi is 40 lb/ton (18 kg/t) vehicle weight, or expressed
sized bucket does not always meet requirements. However, by as a percentage:
upsizing the bucket within the manufacturer’s guidelines, the
required capacity will be generated. 40 lb
Once a shovel is selected, the dipper capacity is sized to = 2%
2000 lb/ton
accommodate various truck capacities. Manufacturers’ guide-
lines suggest that with the overburden specific weight of this Tire penetration or road flex is an added resistance factor
example, dipper capacities shown in Table 13.1.2.14 may be due to soft conditions. Use 30 lb RoRi/in. (0.54 kg/mm) tire
utilized. Four or five passes per truck is considered optimum, penetration. When expressed as a percentage:
although six is acceptable under normal conditions.
Truck fleet options are generated by matching dipper sizes 30 lb
to number of passes to rated hauler capacities. Maximizing truck = 1.5%/in. (0.06%/mm) penetration
size to shovel capability is an effective objective, although adverse 2000 lb/ton
haulage grades, equipment availability, and cumulative bucket
capacities also contribute to the final selection. In the planning stage some basic assumptions must be made
A modifier to be used when establishing shovel cycle times regarding penetration in various areas. This example utilizes the
is to increase cycle times by 1 second for each 2 yd3 (1.5 m3) following:
above nominal dipper capacity. It also should be noted that
nominal truck capacity may be exceeded by up to 5%; however, l Loading areas and waste dumps 2 in.
increased maintenance and tire wear can be expected under these l Approaches 1 in.
conditions. l Established haul roads 0 in. (base)
Although not limited to the shifts or truck sizes in Table
13.1.2.15, the choices that follow have been made to simplify the For grades both positive and negative, use 20 lb RoRi/ton (10
comparison process. kg/t) per % grade. Expressed as a percentage, this becomes
After sizing the truck, it is important to select the engine
horsepower, gear ratios, and tire size necessary to provide satis- 20 lb
= l%/% grade
factory performance under anticipated working conditions. 2000 lbs/ton
Manufacturers provide performance charts that relate the power
provided by the vehicle power train (rimpull) to the vehicles To bring all the factors together, consider a truck leaving the
weight and total rolling resistance (RoRi). shovel approach area on a gentle 2% uphill grade:
OPEN PIT PLANNING AND DESIGN 1287
Table 13.1.2.15. Truck-Shovel Combinations
(13.1.2.10)
slightly higher. When determining the total number of trucks access road, electric power, water, and natural gas. The assigned
required, round 0.00 to 0.29 to zero, and above 0.29 is rounded costs are listed in Table 13.1.2.19.
up. A recap of truck requirements is shown in Table 13.1.2.18. One should establish specifications for the major equipment.
C APITAL C OSTS. No attempt is made in this example to Work closely with vendors who not only have access to their
derive the costs of the mill and related administration and main- technical data, but are also experienced with applications over
tenance facilities nor of any offsite facilities. Offsites include diverse conditions. Once the major rolling stock has been speci-
OPEN PIT PLANNING AND DESIGN 1289
Table 13.1.2.19. Mill and Offsites Costs Table 13.1.2.21. Production Equipment Capital Costs
$7500/tire × 6 tires
= $11.25/hr
4000 hrs
Table 13.1.2.24. Equipment Operating Hours per Year 30 gal/hr × $0.80/gal = $24.00/hr
The fleet operating costs become the basis for estimating the
ancillary operating costs. Allocation of operating costs is highly
variable. Expected operating conditions are influenced heavily $6102.50/shift
= $1.74/ton ($1.92/t)
by weather conditions, rock characteristics, general terrain, etc., 3500 tons/shift
and should so be anticipated when assigning operating costs.
This example utilizes the generalized percentages outlined in
Table 13.1.2.27.
The total ancillary operating costs represent 20% of the total The mining fleet will be depreciated over an average life
operating costs. When expressed in terms of shovel-truck cost, 50,000 hours. The ownership cost/ton milled is the same in all
this percentage becomes 25% (2/8). four cases as mining-fleet size is directly proportional to mining
The production fleet overall operating cost/hour for mine tonnage requirements.
lives and equipment combinations is given in Table 13.1.2.28
based on the same equipment options shown in Table 13.1.2.22.
OWNING AND OPERATING COSTS. Capital costs are depreci-
ated, using the straight-line approach for simplicity, over the 50,000 hrs
expected useful life of the individual components. The results Ownership period: = 8.89 yr
5625 hrs/yr
are expressed in dollars/operating hr and, when combined with
operating costs, provide total ownership and operating costs
(0 and 0) from which a single fleet will be selected for each mine
life. Tonnage: 8.89 yr × 2,100,000 tons of ore, low-
Ownership costs are obtained by dividing capital costs by grade and associated waste/yr. =
the expected life of each type of equipment. Ancillary costs are 18,699,000 tons (16,964,000 t)
split between mobile and stationary equipment because of the
difference in their expected lives. Operating hours for mobile
ancillary equipment should be the same as the truck fleet. The
stationary equipment is utilized for 8 hr/shift (Table 13.1.2.29). $3,975,000 capital cost
A compilation of the 0 and 0 costs for the 12-year life case, Ownership cost: = $0.21/ton
18,669,000 tons
utilizing 525-kW shovels and 120-ton (109-t) trucks, is shown in
Table 13.1.2.30. Total 0 and 0 costs for the equipment combina-
tion options are listed in Table 13.1.2.31. ($0.23/t)
1292 MINING ENGINEERING HANDBOOK
Table 13.1.2.28. Overall Fleet Operating Costs
Total 0 and 0 costs for the mining fleet are $1.74 + $0.21 = jected operating costs to modify criterion illustrated in Fig.
$1.95/ton ($2.15/t). 13.1.2.9.
CUTOFF GRADE. The calculation utilizes the initial cutoff
13.1.2.4 Ore Reserves Reanalyzed grade of 0.06% and original waste and low-grade-to-ore ratios
to establish new cutoff grades. The second step uses the revised
The original ore cutoff grade of 0.06% was based on prelimi- cutoff grades to establish new waste-to-ore ratios.
nary data. New cutoff grades are now established reflecting re- Direct operating costs are tabulated in Table 13.1.2.34 and
spective operating costs of each case. Reanalysis utilizes pro- extended to calculate total direct operating costs for each ton of
ore processed. The resultant cutoff grades are then calculated.
Ore reserves generated for each case are different. Ore grades
change as do the waste to ore ratios, as shown in Table 13.1.2.35.
Table 13.1.2.29. Anticipated Equipment Life DESIGN ALTERNATIVES. At this point it would be prudent
to reanalyze drillhole data as some alteration in pit design may
result. This example will not make that iteration, because all four
cases bracket the original example without significant deviation
( ± 15% of grade).
MARGINAL ANALYSIS. The new stripping ratios have the
potential to further alter cutoff grades. This process can be re-
Table 13.1.2.30. Total Fleet Ownership and Operating Cost Breakdown (12-yr life case)
It is apparent that the incremental gains do not warrant the Postponing the milling of marginal ore to the last years of
expenditures necessary to increase the size of the project to 7000 mine life results in a net NPV increase of $22,795,415 or 12%.
tons (6400 t)/day. After 5000 tons (4500 t)/day, the IE drops From a practical standpoint, unless the higher-grade ore is
substantially and the capital investment requirement, per percent located in distinct areas of the pit and can be accessed in a
gain, blossoms almost fourfold. normal operational flow, the preceding illustration is not possi-
Based on the preceding analysis, the optimum plant size is ble. However, the engineer should always keep his eyes open to
in the range of 5000 tons (4500 t)/day. Adjustments may be the potential of opening the pit in a higher-than-average grade
possible by bracketing the case with 4000 and 6000 tons/day area and sequencing the advances such that higher-grade mate-
(3600 and 5400 t/day) options and repeating the analysis using rial is exposed first. If that opportunity exists, an improved cash
data generated in the first iteration. flow often is possible.
MARGINAL ORE UTILIZATION. As earlier mentioned, post- The time value of money is critical when planning property
poning the milling of the marginal ore to the last few years of development. Deferment of the ICI is possible by the following
the property enhances the NPV. The ore reserves and values for steps:
the 5000-ton (4500-t)/day case are listed in Table 13.1.2.43. 1. Contract out the initial stripping until a positive cash flow
To illustrate the difference in values, cumulative NPV fac-
is experienced.
tors are applied to each scenario.
2. Strip initially in areas with lower overburden to ore ratios
Option 1. Marginal ore milled after ore milled:
to reduce equipment requirements.
3. Minimize the preproduction construction and mine devel-
opment period to the greatest extent possible.
A final consideration is what to do with the low grade be-
tween 0.030 and 0.045%. This material will not contribute to
Option 2. Uniform milling of combined reserves:
the economics of the project, but it should not be treated as
12 yr @ $31,536,000/yr × 5.813 = $183,319,760 waste. Low-grade stockpile areas should be provided so that an
1296 MINING ENGINEERING HANDBOOK
Table 13.1.2.41. Cash Flow Statement
Table 13.1.2.42. Incremental Gains Analysis 5000-ton (4500-t)/day target can be bracketed and ancillary cost-
ing performed in addition to the loading and hauling costs. The
analysis should then be repeated in the same manner until one
is satisfied that more significant improvement is not likely.
SENSITIVITY ANALYSIS. The analysis is sensitive to the un-
certainties inherent in any new project. The most critical parame-
ters in terms of effect on the evaluation are
1. Ore reserves: Has the mineral been properly sampled?
2. Mill recoveries: Are the amenabilities studies based on
representative samples?
3. Product selling price: What is the market volatility in this
commodity? Are long-term sales contracts obtainable?
Each can have a profound effect on the ultimate outcome of
the property as they all have a direct influence on the total value
option exists to mill the material after the mine has closed or if of the deposit. Capital and operating cost variations also can
market conditions improve substantially. have an effect, but because these are generally more predictable
The first evaluation has now been completed. The degree and less volatile, their variations have less impact on the overall
of accuracy presented herein is adequate for many engineered cash flow.
feasibility studies. Further optimization is probable, first by re- As the major sensitivities directly influence the anticipated
analyzing the ore reserves using the recalculated ore cutoff grade. revenue, it is a relatively simple exercise to generate a spectrum
Reconfiguration of the pit boundaries may result. Secondly, the of annual revenues based on variations in ore reserves, mill recov-