PID Template To Submit
PID Template To Submit
PID Template To Submit
PRINCE2
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing
system.
1.4 Distribution
This document has been distributed to:
Page
2 Table of Contents
3 Project Definition
4 Project Approach
5 Business Case
7 Role Descriptions
12 Project Plan
13 Project Controls
14 Tailoring of PRINCE2
3 Project Definition
Project Background
The University of Northampton has addressed the ideology of creating income
for the university through developing a new project. As a group, through
thorough discussion the idea of an onsite nursery or ‘creche’ is a missing
resource that could be utilised in aspects such as childcare, student support
as well as education.
4 Project Approach
As a group and working according to Prince2, below is a breakdown as to
how as a team we have approached the project. The group recognises that
there are constraints to abide to, such as the budget spend of £1.5 million and
a timescale for the project to start in June 2020 and to be completed by July
2021.
Stakeholders
Gathering Requirements:
● As a group, identify the stakeholders who will be involved and
develop a questionnaire to send to those identified. (N.B – due
to the current situation with COVID-19, the group were not able
to gather a select number of stakeholders to take part in a focus
group, to further our requirement gathering)
● Stakeholders identified were students and tutors (N.B –
COVID-19 has limited our ability to contact all students and
tutors)
● Questionnaire was sent out over social media to which 51
students took part in the questionnaire
Construction
● Meet and identify an architect who will work alongside the
group to develop drawings and design of the childcare facility.
Education
● Liaise with tutors who will be involved in the student learning
curriculum
● Monitor and manage the programme that will be developed
working alongside external examiners and the Dean of the
University
5.4 Reasons
Working as a team, identifying what stakeholder group will be the primary
group is students and further onto that, the group wanted to explore a facility
that will also be beneficial to faculty members. By looking at what similarities
these two stakeholder groups have and personal experience (as masters
students, within the group a couple of mature students who have peers who
have children and have missed lectures due the lack of childcare) decided on
this idea. Identifying all the facilities on Waterside is already excellent, the one
facility that looks to be missing is a childcare facility.
The reasons behind what facilities within the Creche will be identified through
the questionnaire that was sent out to students.
This facility will not be a free service for students, but to gain income from
charging on an hourly, half day, daily and weekly fee (and a ‘membership’
idea with discounted fees) will generate income on the premise that each
semester that is enough children.
If the programme is successful, the facility can be available for the local community.
Charitable Causes Further discussions once the Creche is operating over 2 years,
showing profit is increasing.
Northampton Being a town where the university are thinking about families and
Community not just students. With solar panels and recycled materials for the
soft play, the university will help with the town becoming more
sustainable and promote the town.
Children Being comfortable with separation anxiety know parents are not too
far away
Early educational activities
Early exposure to children and adults other than family to help
before starting school
5.8 Timescale
A brief summary of the project plan and how we have identified 10 Milestones.
The list of activities will be presented, and a more detailed breakdown will be
presented in the Project Plan Part Appendix 5.
Milestones:
● Creche Planning Schedule
● Requirement Gathering
● Planning and Preparing PID
● Budgeting
● Construction and Execution
● Interiors & Exteriors
● Bookings and Marketing
● Student Enrollment and Staff Recruitment
● Grand Opening
Results from Questionnaire
As a group, identify the stakeholders who will be involved and develop a questionnaire to
send to those identified. (N.B – due to the current situation with COVID-19, the group were
not able to gather a select number of stakeholders to take part in a focus group, to further
our requirement gathering).
Ideally, in normal circumstances we would have interviewed around 50 people each, with a
wider number of participants, we would have been able to establish a larger stakeholder
group.
The questionnaire was distributed among the groups social groups who attend university
and the following UoN Facebook Groups:
● Mature Students Association – University Of Northampton
● 2018 Students – University of Northampton
● 2019 New Students – University of Northampton
1) Participants
Out of the 51 participants, we can see that only 7 participants think that The University of
Northampton should not have a creche, where 44 participants think UoN should. Even
though the number of participants are limited, it did give the group confidence that the rest
of the data is relevant due to over half of the participants do have children at 30. More
results showed that out of the 30 participants who have children, 25 currently use childcare
facilities.
2) Requirements
As a group, we agreed on a list of what the main requirements we would assume would be
expected in a creche. By asking the participants what they think are Very Necessary, Ideally
and Not Necessary. With the results, we have been able to establish the requirements for an
attractive option for childcare whilst studying at the university.
From the results, we have devised our priority list and broken them down in Must-have,
Should-have, Could-have and Won’t have this time.
Priority Requirements
● Early Learning Facilities - teaching the children the basics before
going into primary school.
● Outdoor Play Area - need to find a space on campus where
there is enough room for a safe outdoor area for children to
play outside.
● Changing Facilities - ease of access to change nappies
● Security Access (Student ID Card Access) - same ID access as the
rest of the university but only access for students who have
children in the creche or students who are teaching in the
creche.
● Breakfast, Lunch and Tea - all meals throughout so parents don't
Must-Have have to worry about pack lunches.
● Kitchen - basic facilities to prep for meal times
Should-Have Indoor Softplay - safe indoor play area
● Car Park - access to a car park - as there is parking on campus
already, this is not a priority.
Could-Have Lockers - if the budget permits, we will add simple lockers
Another element of our questionnaire that was very important to the group on deciding
whether a creche is a viable option for the university to invest is making profit (or at least
breaking even, gaining more students enrolling and choosing University of Northampton will
bring in more revenue to the
university). The questions were broken down into hourly rates, day rates, week rates. We
understand that students can receive funding to contribute to childcare. Just
Based on the business options described previously, the requirements and priority list and
budgeting, Option 2 is the best one to cater to the requirements.
5.9 Costs
Below is a break projected costs for each section.
Outgoing costs:
ADDED WHEN DOCUMENT DOWNLOADED
Estimated Staffing Costs
Option 2 -
Below is the table that shows that the investment option is on Option 2, with additional
income with tuition fees. It shows that within the sixth year of operating, we will breakeven
and return the investment. As it is noted, that as a group, our budget shows that it is well
below the overall budget of £1.5M.
Communications
Irfan Shafi Manager
7 Role Descriptions
Project Board
● Each PRINCE2 project has a project board. It’s made up of the customer (or executive), someone
representing the user side and someone representing the supplier or specialist input.
● In PRINCE2, they are the customer, senior user and senior supplier respectively.
● The Project Manager reports regularly to the project board. The board is informed of progress and
any foreseeable problems.
● The project board provides the Project Manager with a set of necessary decisions. They determine
how the project will proceed and overcome its problems.
Project Manager
● The Project Manager takes on the responsibility of organising and controlling by sequence.
● Selects people to do the project work and ensure it's done properly and on time.
● Draws up the project plans that describe what the project team will be doing and when they expect
to finish.
● Responsible for the day to day management of the project within the constraints laid down by the
project board.
● Monitor how well the progress matches with the plan.
● Perform initial risk assessment before the project begins which means I need to differentiate,
highlight, assess and categorise all identified risks and put forward possible solutions and
strategies.
13 Project Controls
Having established that Time and Cost have restrictions, majority of our project controls will be based
around these. The three largest therefore are:
Cost and Risk in particular have limited margins to work in due to the limited budget left for emergencies,
while Time has a greater degree of flexibility due to the project plan being designed with break periods
allowing for delays.
The Benefits of the Service desk have been calculated at such a high rate it will take a considerable about of
change for them to become a worry as such it has been allowed a greater range than the standard ones
around costing.
Throughout the project, we will use Earned Value Analysis will be used for any Cost Assessment, and
Earned Schedule Analysis will be used for any Time assessments, this is due to advice by Turley and Rad
(2013).
14 Tailoring of PRINCE2
By working through the theories of Prince2, researching the roles taken within the group
and following the steps of how the PID is structured, the team used Prince2 and its
principles
1. Continued Business Justification - breaking down all the cost elements, expenditure,
and what working out the timeline throughout creating the PID.
2. Learn from Experience - Although this was a new experience for all members, previous
work experience working on time management, financing and the knowledge of Prince2
and working on requirements. Lessons with be logged by team members.
5. Manage by Exception - A newly formed group, every member needed to work out the
expectations.
6. Focus on Products - the main products that needed focus was the building itself, the
children learning development and undergraduate education for students.
7. Tailor to the Environment - as this is a product for students both who are the parents
and ones who want to work in the childcare profession. THe creche needed to be
acknowledged as a separate building to the rest of the university and known to be out of
bounds to students who have no use for it.
PROJECT DOCUMENTATION
Release: 29/05/2020
Date: 29/05/2020
PRINCE2
Document Ref:
Version No: 1
1 Quality Management Strategy History
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
1.4 Distribution
This document has been distributed to:
2 Table of Contents
3 Introduction
6 Records
7 Reporting
6 Records
All the records will be posted on the Nile site (the university website) on the group board, which
will allow everyone in the team to see. We also back up the records in our Google Doc. that shared
to everyone in the group. This can make sure that all the ideas, plans, important information and
documents will be kept safe.
7 Reporting
Our team will update the report every week in order to prevent some unexpected problems or even
unexpecting issues. For example, during the processes of the project, there might be several issues
that can occur, so it is better to keep writing a report to update these circumstances to the project
manager, a board of director, or even stakeholder. The report will provide the information on
updating the processes, cost and budgeting, quality, and etc. All these reports will be kept in the file
on Google Doc., which will allow everyone in the team to access through that information.
Moreover, there is another report called an exceptional report, which refers to a finished process
with the confirmation of quality control. This report will update after any activity process has been
done and already check the quality of the activity, with no any error or mistake in that process.
Roles Responsibilities
Member of Project Board ● Each PRINCE2 project has a project
board. It is made up of the customer
(or executive), someone representing
the user side and someone
representing the supplier or specialist
input.
● In PRINCE2, they are the customer,
senior user and senior supplier
respectively.
● The Project Manager reports regularly
to the project board. The board is
informed of progress and any
foreseeable problems.
● The project board provides the Project
Manager with a set of necessary
decisions. They determine how the
project will proceed and overcome its
problems.
Project Manager ● The Project Manager takes on the
responsibility of organising and
controlling by sequence.
● Selects people to do the project work
and ensure it's done properly and on
time.
● Draws up the project plans that
describe what the project team will be
doing and when they expect to finish.
● Responsible for the day to day
management of the project within the
constraints laid down by the project
board.
● Monitor how well the progress
matches with the plan.
Assistant Project Manager – ● Create coordination plans for
Communications stakeholders, including both internal
and external about implementing
contact plans during the whole project.
● Monitoring of current and possible
impacts on primary stakeholder and
predict any substantial adverse effect
or lack of positive impacts, which also
liaise with the project director to
resolve the problems.
● Capture details and answer
collaborator inquiries, then send them
to the director of the project at
frequent intervals with serious
problems developing as soon as the
problems are detected.
Assistant Project Manager – ● It requires to perform an initial risk
Risk Management assessment before the project begins,
which means the risk manager needs
to differentiate, highlight, assess and
categorise all identified risks and put
forward possible solutions and
strategies.
● Provide risk management policy and
guidance.
● Ensure that the implementation of the
risk management framework and
process is appropriate.
● Managing risks is beyond the
responsibility of the project team and
links with other functional
departments.
Assistant Project Manager – ● Establishing a quality control program
Quality Assurance to make sure the standard of each
process meets the qualification. This
will apply for all main elements of the
project function, including building
design, teachers, machine and
equipment, construction material, and
etc.
● Make sure that the quality control plan
is followed by the program and the
period of time during the project life
cycle. Also, keep updating and raising
any reported problem and liaising with
the project manager or other assistants
in specific areas of problem.
● Plan and perform a quality audit to
validate the efficacy of quality control
methods; submit results to the project
manager and project board.
● Evaluating each process during the
project and also appraising all project
members for the best quality of work
to the customer.
Assistant Project Manager – ● Performing the calculation of financial
Finance forecast to determine the project
viability will make other assistants to
understand the budget of the whole
project life cycle. Also creating
expenditure evaluations to consider an
alternative outlined to save costs.
● Allocating budgets for every project
part and sector such as track costs for
construction or even raise major
variances; liaise with the director of
the project and also with all project
assistants to find triggers and devise a
suitable solution.
● Responsible for day-by-day
transactions in case of necessary or
emergency use of budget during the
whole project time period.
PROJECT DOCUMENTATION
Release:29/05/2020
Date:29/05/2020
PRINCE2
Client:University Of Northampton
Document Ref:
Version No:1
1 Risk Management Strategy History
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
1.4 Distribution
This document has been distributed to:
2 Table of Contents
3 Introduction
6 Records
7 Reporting
10 Scales
11 Proximity
12 Risk Categories
15 Risk Tolerance
16 Risk Budget
3 Introduction
The purpose: is to identify and highlight the potential issue which could occur in a crèche project.this helps
to mitigate the risk which could impact in the project failure, risks faced in construction, resources,
machinery, conflicts between project members and stakeholders and others.
Objectives:
● To reduce any sort of threats and improve opportunities for example employment opportunities for
personals in the field such as operational risk manager, risk analyst, risk manager, financial services
risk management manager, insurance risk management executive, and more.
● Another objective will be to recognize any major risks such as construction obstacles & delays,
issues caused by weather conditions, chemical usage in construction, etc and how we are going to
mitigate and control those risks/factors.
The Scope: is to build a new creche on the university campus, which helps the current students and the
faculty members. Using the risk management strategy helps the project team to identify the risk in each
stage of the project like construction, lectures, team management and working on those risks to
mitigate/control them.
Risk analysis
Potential risks in the future are presented based on PESTEL analysis (Political, Economic, Social,
Technological, Environmental and Legal). These risks will be further classified in the risk categories
section. The basic license is indispensable to launch the project as well as proceed smoothly. The
negative impact on the project is caused by poor project cost management, lack of experience human
resources, delayed project execution time due to epidemics, delayed construction due to poor
contractors, natural disasters, pollution, higher-than-expected cost of materials and equipment for
various reasons.
Risk evaluation
● Provide the required documents of the entire project and demonstrate coming profitability
as well as empower the university in the future to apply for permits from the council and
stable funding from the University of Northampton.
● Estimate, evaluate and scale costs thoroughly for all project activities such as purchasing
and selling equipment and materials, staff salaries, project maintenance as well as risk
expenses.
● The responsibilities, roles and specific tasks of team members must be clearly defined and
properly scheduled. The project leader in general and team leaders in particular should
capture the progress of the project through regular meetings in order to compare, evaluate
and urge the members to complete the set goals on time. In situations where face-to-face
meetings are not possible, virtual meeting applications should be synchronized by all
members and used with care.
● Minimize the risk of dissent in a group based on three basic steps: collecting opinions of
team members, identifying the source of internal conflicts and providing the most
appropriate solutions in the earliest meetings.
● Approve the availability and quantity of required items with stakeholders. Also consider
and prepare alternative supplies as contingency plans when a bad situation occurs.
● Testing and hiring instructors with experience and skills needed in this project.
● Regularly inform the progress of project to the University as well as require their support
such as volunteer jobs, advertising campaigns or workshops for propaganda purposes .
● Strength: Building a creche will help students and faculty members to manage their
childcare needs while in university effectively. It also provides an exclusivity and priority to
the users, which provides a good customer base and consistency in income and profits.
● Weakness: lack of interest in the creche from current students (Employability factor), lack
of users on term holidays.
2. Probability and impact matrix: After the conclusion of SWOT analysis, it will be time to understand
the probabilities and impacts of the risk. This assessment will help us to identify the major risks and
control it.
3. Risk Register: having a risk register helps us to understand the clear view of outcome, probability
and the mitigation strategy for each risk.
6 Records
● Risk register: Risk register will be one of key records in this project, this encompass identified risks,
description of the risk, risk probability & impact, and risk response types such as what to avoid,
reduce, what fallback measures we have, acceptance and sharing aspects. The major risks identified
for this project are COVID 19, planning permission, delay in building construction due to
contractors, builders and COVID 19, market fluctuation( price increase), lack of materials, lack of
suppliers, impact of bad weather, inexperienced project team, health & safety
measures/regulations being ignored even though many risks are identified, usage of hazardous
chemicals (in construction and also usage of plastic in creche equipments). Therefore, the risk
register is very useful in this project, so all the risks are known, and the mitigation procedures can
be taken on time and monitor the progress of the project.
● Other records will be financial records (accounts, expenditure etc), property records (Planning
permissions), construction plans, authorisation certificate for the creche, task and activities
schedule and digital records.
7 Reporting
The project risk report will include: Risk of change in cost of materials, risk of lack of resources for
specific jobs at the required time, risk of suppliers not being able to complete the work under contract
terms. The project risk report will be updated at the end of each month based on risk log records,
which documents all risks every week.
Portfolio risk reporting summarizes all portfolios and highlights key areas that need to be realized as
soon as possible. It helps the management team to control the scope and budget of the project, such as
allocating resources for individual project tasks. This report will be provided at the end of the month.
Role Responsibility
Corporate ● Provide risk management policy and guidance.
Management- ● Ensure that the implementation of the risk
Executive management framework and process is appropriate
● Managing risks is beyond the responsibility of the
project team and links with other functional
departments.
Team Manager
● Directly involved in identifying, assessing and
controlling risks
● Support the Project Manager in maintaining the
project
10 Scales
Impact
1 2 3 4 5
Very high 5 5 10 15 20 25
High 4 4 8 12 16 20
Medium 3 3 6 9 12 15
Low 2 2 4 6 8 10
11 Proximity
An appropriate response to be taken when a risk is likely to occur
● Imminent: Planning permission from the council and University Of Northampton, funding
confirmation from UoN.
1. Construction stage: Pollutions (environmental, noise, air etc), Material quality (Construction
material, equipment’s etc), interruption in supply of materials or delays with
contractors/builders.
2. Lecture/practical stage: lack of experience of Project management team and other instructors ,
not meeting the deadline, workforce/contractors hired not meeting the required standards
(Registration, certification etc), not acquiring the industry standard raw materials.
3. Support activities: health and safety regulation & policies, security facilities, staff training
facilities, volunteers.
● Within the project: Price fluctuation, Disagreements between project team/stakeholders, project
team members not meeting the deadline (sickness, leaving the project etc) project management
issues (week, dissatisfaction, in the management style etc), legislative measures not being met, lack
of experience.
● Beyond the projects: publicity, not finding customers, maintenance of the building and the facility,
vandalising, lack of staff quality and quantity, legislative measures not being met.
12 Risk Categories
The risk categories in this project are:
Strategic/commercial:
Economic/financial/market:
Legal/regulatory:
Organisational/management/human factors:
● Poor control
● Making bad decisions in the process of choosing suppliers, contractors or employees
● Unclear division of roles and responsibilities among members
● Conflicts between team members and between project team members and stakeholders/suppliers
● Inexperience contractors/team members
● Change in behaviour of customers
Political:
Environmental:
Technical/operational/infrastructure:
Avoid:
• Agreeing a contract with a fixed price with builders and other suppliers (with the
consideration of budget)
• Material used are environment friendly and within the govt guidelines,
• Executing project during the seasonal changes and viruses such as COVID19
Reduce:
• Make sure the design is accurate, as an error will lead to redesigning and will affect in the timing
and budgeting of the project
• Realistic budgeting, which will help the project team anticipate likely issues and correctly feature
these in budget
• Having more than one supplier to avoid delays, and a team on site to pre check the deliveries
before the intended start date of construction.
• Construction plan & drawing confirmation, contracts confirmation with suppliers about the
materials, expenditure, completion time etc to avoid the conflicts between different partners.
Fallback:
• Have a contingency plan, use of already made materials, if any problem occurs with raw materials
• Having a second option on the project idea i.e., leasing the facility to a charity or another business
to run and maintain the creche.
Transfer:
• Insurance cover for the construction (Building) and for the whole project including weather factors.
• Outsourcing of the construction, which allows the contractors to adverse variance on budget.
• Establish a contract between the project team and the suppliers to get discounts if there is a delay
in delivering goods, to further reduce the budget.
Accept:
• Accepting the lack of experience and continuation of the project with due care
• Accept the delays and issues cause by COVID 19 and follow the govt guidelines
Share:
• A separate contract or an inclusion within the contract that the contractors must refund some
amount if the project is not completed on the agreed time.
• Include the UoN in the contract as they are one of the major stakeholders, therefore sharing
responsibility of managing risk.
1. Knowing the importance and the feasibility of the project and the selected business case for our
CRECHE
2. Delivery date estimation of for the equipment’s and materials which are needed for the
construction of the building and for the running of the business to make sure the project is completed
within the time frame.
3. Understanding the number/quantity of the project members and the abilities the members have, is
vital
5. To measure the performance of the suppliers and contractors, we need a Log or a performance
indicator.
6. Clear and concise communication with the project team and with the stakeholders (Internal &
external)
7. Allocation of fixed budget for each task, to avoid misunderstanding and confusion, it also helps to
run the project smoothly.
15 Risk Tolerance
Time tolerance: The shorter the tolerance, the more likely the project is to deliver the project on time and
vice versa. During the time of social isolation due to the Covid-19 pandemic, the time tolerance of the
project was estimated to exceed the normal level. Discussing, planning, and negotiating with project
stakeholders such as UoN, contractors or suppliers becomes difficult and requires more time than usual. In
addition, the members of the project team are inexperienced with similar projects which also contributes
to the extension of time tolerances and may lead to delays in project submission.
Cost tolerance: The fixed budget for the project is £1,500,000 then the cost tolerance for this project is
zero. However, risk tolerances that can consume less than 20% of the risk budget are still acceptable.
16 Risk Budget
Total Budget- £1.5Million out of that the Risk Budget will be £120,000, Refer to the budget spreadsheet for
the budget breakdown.
Ref: Version:
(Scales from 1-5) (Scales from 1-5) (Scale from 1-25) Imminent to
20 Short-Term
Future
4-High 3- 4-high 3- 16 9
Moderate Moderate
● Acceptance: Deduct a part of the budget as a backup fund in case of a possible bad
situation
● Avoid: Discuss, negotiate and collaborate with suppliers that offer fixed-value
contracts
● Reduce: Regularly check and capture the budget situation as well as conduct an
analysis and prediction of the potential for adverse disparities to occur.
● Fallback: Request additional funding from the UoN in the event of circumstances that
arise beyond the control of the project team.
● Transfer: Outsourcing aims to reduce the burden of responsibility
● Share: Accepting and requiring transparency of information sharing may be
detrimental to the estimates from all parties involved.
Risk Response:
Outsourcing of budget management is not a good idea because it will lead to lack of
control and power of the project team. Therefore, Transfer is not preferred in this case.
For suppliers, all options are applicable except outsourcing due to the above reason.
Ref: Version:
20 Imminent
● Avoid: Discuss with the contractor and prepare contingency plans for all possible
injuries
● Reduce: Agreement and cooperation with the health and safety sector of University
of Northampton.
● Fallback: Contingency planning through high quality outsourcing
● Transfer: Purchase and apply health and safety insurance policies for members
● Share: All terms and conditions for health and safety regulations need to be
accepted prior to project participation by project participants
Risk Response:
All options should be applied as mandatory steps in carrying out the project.
Ref: Version:
20 Within the
stage
Pre- Post- Pre- Post- Pre- Post-
Respo Respons Respo Respons Respo Respo
nse e nse e nse nse
Threats
Avoid: hiring inexperienced contractors and builders, also avoid not agreeing a contract
with a fixed price with builders and other suppliers.
Reduce: Make sure the design is accurate, as an error will lead to redesigning and will
affect the timing and budgeting of the project.
Fallback: Have a contingency plan, use of already made materials, if any problem occurs
with raw materials, Back-up Labourers/ workforce/ Contractors. Transfer: Insurance
cover for the construction (Building) and for the whole project including weather factors.
Accept: Accept the delays and issues caused by COVID 19 and follow the govt
guidelines.
Share: A separate contract or an inclusion within the contract that the contractors must
refund some amount if the project is not completed on the agreed time.
Risk Response:
Transfer: Insurance cover for the construction (Building) and for the whole project
including weather factors.
Ref:
Version:
Threats
Avoid- Executing project during the seasonal changes and viruses such as
COVID19 (avoid Not Following the Govt Guidelines)
Reduce- Having more than one supplier to avoid delays, and a team on site to pre
check the deliveries before the intended start date of construction.
Fallback- Have a contingency plan, use of already made materials, if any problem
occurs with raw materials
Insurance cover for the construction (Building) and for the whole project including
weather factors. Also Establish a contract between the project team and the suppliers
to get discounts if there is a delay in delivering goods, to further reduce the budget.
Accept- Issues with the COVID 19 and follow the govt guidelines. Accept the weather
condition will change and adapt accordingly
Share - Include the UoN in the contract as they are one of the major stakeholders,
therefore sharing responsibility of managing risk.
Risk Response:
Chosen response
Ref:
Version:
(Scale from 1-5) (Scale from 1-5) (Scale from 1-25) Imminent
Fallback: Having a second option on the project idea i.e., leasing the facility to a charity or
another business to run and maintain the creche.
Transfer: Insurance cover for the construction (Building) and for the whole project including
weather factors.
Accept: understanding and accepting the fact that there will Risk factors.
Opportunity:
Exploit: the widow of opportunity to make profit and moreover provide the user need in
cooperation with UoN.
Risk Response:
Reduce: Hire experienced members to handle the project
Fallback: Having a second option on the project idea i.e., leasing the facility to a charity or
another business to run and maintain the creche.
Transfer: Insurance cover for the construction (Building) and for the whole project including
weather factors.
PROJECT DOCUMENTATION
COMMUNICATION MANAGEMENT STRATEGY
Release: 29/05/2020
Date: 29/05/2020
PRINCE2
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
1.4 Distribution
This document has been distributed to:
2 Table of Contents
3 Introduction
4 Communication Procedure
6 Records
7 Reporting
10 Stakeholder Analysis
3 Introduction
Purpose:
The main motive of the Communication Management Strategy document is to create
frequency and guidelines to communicate with stakeholders whether they are internal
(personnel & managers) or external (Suppliers).
The major objectives of this strategy are:
● To make sure that the communication methods are clear to understand throughout
the project Creche.
● To offer a clear understanding of the communication techniques used in
the ongoing process of the project.
● To facilitate and engage stakeholders via the establishment of a controlled and
balanced bi-directional flow of information.
Scope:
The scope of using the communication management strategy in Creche project is to
counter and avoid conflicts within not only the team members but also between the project
team members. Also, to provide proper information at a specific required time in order to
perform various methods of communications.
Responsibility:
Main responsible person is the Project Manager and Communication Assistant Manager,
but other team members are also responsible for certain protocols.
4 Communication Procedure
Definition of the communication strategies used in the major aspects of the Creche
Project are as follow:
a.Gathering information:
● Meetings with the Board (representing university): In order to clarify requirements
like returns on the investment there will be meeting arranged.
● Communication with suppliers: Communicate with the suppliers through emails/calls
for material and equipment. Once received confirmation then arranging meeting to
finalize the quantity and quality as well as time of delivery.
● For Creche Building construction, contacting architects and builders by call/emails
and after that arrange meetings to get a clear picture and confirm plan.
b. Construction:
● For getting the planning permission a form is to be filled and submitted. Track on
online portal the progress. Respond the queries of planning approver to get
permission.
● Organize meetings with the structural engineers/ contractors to finalize the structure
of the building, keep a track of progress by weekly meetings.
● Arranging group meetings with the construction contractor to finalize budget for
equipment and check its availability. This will take up every week until the
construction of the Creche building is started.
● Meetings with Project Board once in a month to keep them updated regarding the
progress.
● Live interactive communication with architects and labours and make sure they
complete their daily task and after that report the task is completed.
c. Marketing:
● Digital marketing promotions in UON website, Groups and social medians like
facebook, Instagram and twitter keep them updated if there are any updates or
offers.
● Physical promotion about Creche facility on campus by brochures, leaflets etc.
d. Support Elements:
● Regular meetings with Health and Safety department of UON on campus to find out
the formalities which need to be implement.
● Arranging group meetings with the security staff for CCTV and all security systems.
Also, complete the agreements or any paperwork face to face.
7 Reporting
● Performance reporting: To track the performance of the project in a group meeting
updated graphs, charts and tables can be used.
● Progress report: To have a general update on progress of the project that is done
weekly basis.
● Lesson Logs: Once any activity is completed, Conduct a meeting with the Project
board and draw on experience and report it.
● Internal and External reporting: The reports which are related to the information
passed between the project team regarding the completed tasks are internal reports
whereas, external report is information between project team and stakeholders.
● Financial Reports: To fix the estimated cost kept for each task meeting with
stakeholders, building contractors will be arranged. Report on each and every
transaction is made to check where and when the money is spent. Also known as
tracking the budget according to the estimated value.
10 Stakeholder Analysis
“Any individual, group, or institution who has a vested interest in the natural resources of
the project area and/or who potentially will be affected by project activities and have
something to gain or lose if conditions change or stay the same.” – Golder(2005)
Stakeholders must be taken into thought to realize venture objectives and their support is
exceptionally significant for the success of the project. The extreme aim of this
investigation is to progress an approach that expresses the connection between the
numerous stakeholders and the problems they generally care about.
Identification of Stakeholders:
Internal Stakeholders: Project associates, providers, building staff (builders etc), planning
committee of University of Northampton, development financing board of University of
Northampton are recognised as inside stakeholders in the scheme.
External Stakeholders: Government, creche users including students, teaching and non-
educating staff of the University and local public are distinguished as the outside
stakeholders.
There are four types of Stakeholder representations included in the above shown Mapping
1. Manage Closely
2. Keep Satisfied
3. Keep informed
4. Monitor
Stakeholder Mapping:
________________________________________________________________________
REFERENCES:
Golder, B. (2005). Cross-Cutting Tool Stakeholder Analysis. 1st ed: Foundations of Success, pp 1-
6.
Huber, M., & Pallas, Martina. (2006). Customising in stakeholder management strategies concepts
for long-term business success. Berlin; New York: Springer, pp 13-16.
PROJECT DOCUMENTATION
PLAN
Release: 29.05.2020
Date: 29.05.2020
PRINCE2
Author: Dinesh K C
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing
system.
1.4 Distribution
This document has been distributed to:
1 Plan History 1
1.1 Document Location 1
1.2 Revision History
1.3 Approvals
1.4 Distribution
2 Table of Contents
3 Plan Description
4 Plan Prerequisites
5 External Dependencies
6 Planning Assumptions
7 Lessons Incorporated
9 Budgets
10 Tolerances
11 Product Descriptions
12 Schedule
3 Plan Description
The overall project of building Creche service in University can be divided into
five (5) major sectors: Data Collection and Identifying stakeholder, Preparing
Project Initiation document, Designing and budgeting the whole project,
Construction of Creche Building and Practical Implication.
The roles and responsibility has been divided into all six group members as
following:
5 External Dependencies
The Creche project within the University is all about the number of children of
students and university staff. So external dependencies of the project include
stakeholders i.e. number of matured students and staff in the university.
6 Planning Assumptions
● As our project must complete within 1.5 million Pound, allocating
budget to different sectors is the primary assumption.
● Maximum staff and students will use the on-campus facility of creche
service.
● Getting approval of the location to build the creche building from
Universitymanagement team.
● Team members are proactive to work under unexpected situations
such as pandemic.
7 Lessons Incorporated
iii. Risk mitigating factors from every aspect are done so that we are ready to
cope with difficult situations and solve accordingly.
iv. Proper task division within the group member is must so that none gets
overload of work and gets frustrated.
All six project members will be responsible with their respective parts for
monitoring and controlling throughout the project. Controlling measures are
likes of budget, time frame, communication factor and unprecedented
situations.
9 Budgets
Capital for the project is provided by the university and the total amount for
the project is 1.5 million pounds. So, the project has a limited budget.
10 Tolerances
Project tolerance sets the range where a project can be over or under a bit
and does not affect the overall planned dimension on schedule, cost and
scope of the project.
There are three major type of tolerances:
i. Scheduled Tolerance: As our project has breakdown structure and has
almost 300 smaller milestones and every individual task got more than
enough time to finish. Our overall project duration has 1 week of tolerance;
either finishing early or late can be considered fine.
ii. Cost tolerance: As our total available budget is £1.5 million whereas total
estimated cost is about £660k, which means we have enough budget to
adjust as per requirement. But as a project planner, setting cost tolerance is a
good way to keep your budget in track, so for this project we decided to make
10% of tolerance in estimated budget.
iii. Scope tolerance: Unlike schedule and cost tolerance, scope tolerance is a
bit different and hard to specify. For our project, there is very minimal scope
tolerance as we can’t go out of our project scope.
11 Product Descriptions
As a team we have decided that one feature of the university that was missing
was a creche facility. Years ago, this may have been thought of as an
impossible option but as facilities for students are forever improving, a social
feature such as a creche could now be considered.
University students vary in age and as some people may feel restricted to
embark on new career prospects, training and new qualifications due to either
the expense or lack of childcare availability.
As a team, the proposal is to build an onsite creche for students and faculty
for children aged 4/5 and under. But with options for additional care for
children of all ages when school holidays and university holidays do not
overlap.
12 Schedule
- See attached file for Gantt Chart and Network Diagram
LESSONS LOG
Date: 29/05/2020
PRINCE2
Page 2
Fundamental As - UoN Creche
Project Initiation Document
Date: 25 May 2020
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
1.4 Distribution
This document has been distributed to:
Page 3
Fundamental As - UoN Creche
Project Initiation Document
Date: 25 May 2020
2 Table of Contents
Page
2 Table of Contents
3 Lesson Type
4 Lesson Detail
5 Date Logged
6 Logged By
7 Priority
Page 4
Fundamental As - UoN Creche
Project Initiation Document
Date: 25 May 2020
3 Lesson Type
● Project –UoN Creche facility
● Programme
● Programme ManagEment
4 Lesson Detail
● Covid 19
● Health and Safety
● Negative Impact, only virtual meetings, no substantial meetings held on
campus.
● Pandemic, university campus closed
● This is the first time that has occurred, no one on the team has had to deal
with this before.
● Have a contingency for web based meetings and set stricter timelines for work
completed.
● Only during the risk that we have identified it as a threat.
5 Date Logged
25/05/2020
6 Logged By
Harriet Sheppard
7 Priority
The PID.
References:
Page 5
Fundamental As - UoN Creche
Project Initiation Document
Date: 25 May 2020
Page 6