Design Head Will Withdraw Documents of The New Projects From DCC
Design Head Will Withdraw Documents of The New Projects From DCC
II DOCUMENT WITHDRAWAL CEE > DCC > Design Head Document withdrawal form
Design head will withdraw documents of the new projects from DCC.
a. Bill of Materials
b. Bid Documents
c. Proposed Datasheets
d. Scope of Works
e. Instrument List Form
d. Client existing documents
(Key plan, As-built drawings)
If changes has been made, Change Notice form must be counter signed CN Form
by the parties who have withdrawn the document.
a. Revised document will be withdrawn after the change
noticed has been signed.
IV KICK-OFF MEETING
A. Internal kick-off must be conducted AM, PM, LE, DE
a. Conduct minutes of the meeting DE MOM form
Allot 1-5 days for site Inspection/Project Stakeout depending PM, LE Gantt Chart
on the scope of the project.
a. Fill out the site inspection form DE Site inspection/project stakeout form
If scope of works includes reengineering and/or wire tracing and
multiple sites, allot a minimum of 5 days for the site inspection.
Note: The duration given above is applicable for a single site only.
1 System Architecture
Allot a minimum of 3 days for the study of the system.
B. ELECTRICAL
(1) Load Schedule LDS
(2) Single Line Diagram SLD
(3) Schematic Diagram SCH
(a) Drawing Index
(b) I/O List
(4) Abbreviations, Legends and Symbols
C. HOOK-UP DIAGRAMS
(i) Electrical
(a) Shop Drawings
(1) Panel Layout PNL
- Views and Dimensions, Materials
- Component Layout
- Component List
(2) Roughing Ins RCL
- Cable Schedule Form
- Conduit/ Cable tray Layout
(ii) Installation
- Instrument Installation
- Bracket, Support and/ or Mounting Detail
(iii) Process
Note: From time to time, the design engineer will request to return on site due to verification of particular design.
If the design head have no further comments, the design will then be
forwarded to GSB for final approval.
But if there are comments still, the designer must rectify first and
repeat the process of Self-check (See procedure 7A).
A. INTERNAL REVISION
Initial drawings are indicated as Rev. 0A, meaning no
revision has been made yet. If upon internal approval,
the design has been commented, the designer must
revised as per comment/s. To indicate the revision made
on the REV. 0A drawing, it will then become Rev. 0B.
The alphabet part of the revision number will progress
until internally approved. So once approved, the
these letter will be purposely omitted and transmitted
to the client as Rev. 0.
B. EXTERNAL REVISION
The initial design will be transmitted to the client as Rev 0.
If the client have further comments, these Rev. 0 drawing
will returned as Rev 1A. Repeat the process of internal
revision. The number will progress until the drawing has
been approved. (See procedure 8A)
Note: Only one revision history form must be complied per project and/or site.
IX DRAWING SUBMITTAL
The Design engineer will forward the internally approved drawings to the
Design Coordinator. There are two courses for these internally
approved drawings:
If changes has been made, Change Notice form must be counter signed DC > DCC CN
by the parties who have withdrawn the document.
a. Revised drawing can be withdrawn after the change DCC > PM, LE Document Withdrawal Form
noticed has been signed and surrendered the obsoleted drawing.
B. FOR CONSTRUCTION
As for clients who requires design approval, the design DC > PM Internal Transmittal Form
coordinator will transmit the design to the Project Manager
who will then submit it to the client.
1. In order to proceed to the mobilization, the design coordinator DC > DCC DRN
will release a copy for construction to the DCC. Listed
below are designs which have minimal effect on the
approval/comments of the client.
1. Panel Layout
2. Schematic Diagram
3. Loop Diagram
4. P &ID
2. The design will be withdrawn by the Project Manager and/or DCC > PM, LE Document Withdrawal Form
Lead Engineer/s and implemented.
3. When the approved/commented drawings from the client arrives, PM > DC Internal Transmittal Form
the Project manager must first transmit it to the Design
Coordinator, Design Head and/or the Lead design. This
process can be bypassed, if the designer have the direct
connection to the client and/or included in the loop.
The "For Construction" drawings on-hand is now subjected PM, LE > DCC
for control and must be surrendered to the DCC within a
week or seven (7) days after the released of Change Notice.
X AS-BUILT DRAWINGS
A. Manpower
Rate per day
Contingency for urgent works
(OT works and meals)
B. Documentation
Printing (Initial and As-Built)
Permits (if applicable)
Professional Fees
Design Initiation
a. System Architecture
This design must be the first one to be generated for this is the
overview of the project/system
Reference: 1. Bill of Materials
2. Scope of Works
3. Instrument List
b. INSTRUMENTATION
i.