(MRP)
MRP
Computer-based information system for ordering and scheduling
of dependent-demand inventories, i.e. what is needed, how much
is needed, and when is it needed
Changes
Order releases
Master
schedule Planned-order
schedules
Primary
reports Exception reports
Bill of Planning reports
materials MRP computer Secondary
Performance-
programs reports control
reports
Inventory
records Inventory
transaction
MRP Inputs
• Master Production Schedule (MPS) – States which end
items are to be produced, when they are needed, and in
what quantities
• Beginning Inventory
• Projected requirements
• Stock on hand
• Scheduled receipts (receipts)
• Planned order release
• Economic order quantity
Problem
Consider the manufacture of a toy. The master production schedule to
manufacture the toy is given in the following table.
Master Production Schedule
Week 1 2 3 4 5 6 7 8
Demand 200 - 100 175 300 200 - 250
Period 0 1 2 3 4 5 6 7 8
Projected
- 200 - 100 175 300 200 - 250
Requirement
Receipts - - - 350 - 350 350 - -
Planned order
- 350 - 350 350 - - - -
release
B (EOQ – 450, LT – 1)
Period 0 1 2 3 4 5 6 7 8
Projected
- 350 - 350 350 - - - -
Requirement
Receipts - - - 450 450 - - - -
Planned order
- - 450 450 - - - - -
release
C (EOQ – 400, LT – 1)
Period 0 1 2 3 4 5 6 7 8
Projected
- 350 - 350 350 - - - -
Requirement
Receipts - - - 400 400 - - - -
Planned order
- - 400 400 - - - - -
release
D (EOQ – 375, LT – 1)
Period 0 1 2 3 4 5 6 7 8
Projected
- - 400 400 - - - - -
Requirement
Receipts - - 375 375 - - - - -
Stock on Hand 250 250 225 200 200 200 200 200 200
Planned order
- 375 375 - - - - - -
release
E (EOQ – 400, LT – 2)
Period 0 1 2 3 4 5 6 7 8
Projected
- - 400 400 - - - -
Requirement
Receipts - - - 400 - - - -
Planned order
- 400 - - - - - - -
release
Practice problem
A firm producing fire extinguisher has the following master production schedule
(MPS).
Master Production Schedule
Week 1 2 3 4 5 6 7 8
Demand 100 - 150 140 200 140 - 300
The bill of materials structure is given in the following figure. Each fire
extinguisher has a cylinder, a valve assembly and two handle bars. Each valve
assembly requires a valve and a valve housing.
The details of Bill of Materials along with economic order quantity and stock
on hand for the final product and subassemblies are shown below.
Details of BOM
Parts Required Order No. of Lead Time Stock on
Quantity Units (Week) Hand
Fire Extinguisher 300 1 1 150
Cylinder 450 1 2 350
Valve assemblies 400 1 1 325
Valve 350 1 1 150
Valve housing 450 1 1 350
Handle bars 700 2 1 650
Complete the material requirements plan for the fire extinguisher, cylinder, valve
assembly, valve, valve housing and handle bars and show what quantities of
orders must be released and when they must be released in order to satisfy the
MPS.
Fire Extinguisher (EOQ – 300, LT – 1 week)
Period 0 1 2 3 4 5 6 7 8
Projected
- 100 - 150 140 200 140 - 300
Requirement
Receipts - - - 300 - 300 - - 300
Planned order
- - 300 - 300 - - 300 -
release
Cylinder (EOQ – 450, LT – 2 weeks)
Period 0 1 2 3 4 5 6 7 8
Projected
- - 300 - 300 - - 300 -
Requirement
Receipts - - - - 450 - - 450 -
Planned order
- - 450 - - 450 - - -
release
Valve assembly (EOQ – 400, LT – 1 week)
Period 0 1 2 3 4 5 6 7 8
Projected
- - 300 - 300 - - 300 -
Requirement
Receipts - - - - 400 - - 400 -
Planned order
- - - 400 - - 400 - -
release
Valve (EOQ – 350, LT – 1 week)
Period 0 1 2 3 4 5 6 7 8
Projected
- - - 400 - - 400 - -
Requirement
Receipts - - - 350 - - 350 - -
Planned order
- - 350 - - 350 - - -
release
Valve Housing (EOQ – 450, LT – 1 week)
Period 0 1 2 3 4 5 6 7 8
Projected
- - - 400 - - 400 - -
Requirement
Receipts - - - 450 - - - - -
Planned order
- - 450 - - - - - -
release
Handle Bar (EOQ – 700, LT – 1 week)
Period 0 1 2 3 4 5 6 7 8
Projected
- - 600 - 600 - - 600 -
Requirement
Receipts - - - - 700 - - 700 -
Planned order
- - - 700 - - 700 - -
release
MRP – Lot Sizing
• Planned order release - made by considering the relative difference between
the ordering cost per order, and carrying cost per unit per period, it may
result in minimum (total) inventory cost.
Given:
• Initial on hand = 30 units
• The Average demand/week (D) = 20.83 units/week
(Average of 12 weeks projected requirements) = 21 units/week (Approx.)
2 𝐶0 𝐷 2 ∗250∗21
𝐸𝑂𝑄 = = = 64.8 = 65 (Approx.)
𝐶𝑐 2.50
MRP Calculations as per EOQ method
Period 0 1 2 3 4 5 6 7 8 9 10 11 12
Projected
- 30 50 40 - 15 20 20 - 10 - 15 50
Requirement
Receipts - - 65 65 - - - 65 - - - - 65
Stock on
30 0 15 40 40 25 5 50 50 40 40 25 40
Hand
Planned
- 65 65 - - - 65 - - - - 65 -
order release
Period 0 1 2 3 4 5 6 7 8 9 10 11 12
Projected
- 30 50 40 - 15 20 20 - 10 - 15 50
Requirement
Receipts - - 105 - - - 50 - - - - 65 -
Stock on
30 0 55 15 15 0 30 10 10 0 0 50 0
Hand
Planned
- 105 - - - 50 - - - - 65 - -
order release