02 - Technical Specifications - Cast-In-Place Concrete
02 - Technical Specifications - Cast-In-Place Concrete
02 - Technical Specifications - Cast-In-Place Concrete
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 REFERENCES
SECTION 03 30 00 Page 1
100 Man Compound Zamboanga City
1.2 DEFINITIONS
1.3 SUBMITTALS
SECTION 03 30 00 Page 2
100 Man Compound Zamboanga City
SD-07 Certificates
Reinforcing Bars
1.5.1 Reinforcement
Sixty days minimum prior to concrete placement, submit a mix design for
each strength and type of concrete. Submit a complete list of materials
including type; brand; source and amount of cement, complementary
cementitious materials, and admixtures; and applicable reference
specifications. Submit mill test and all other test for cement,
complementary cementitious materials, aggregates, and admixtures.
Provide documentation of maximum nominal aggregate size, gradation
analysis, percentage retained and passing sieve, and a graph of percentage
retained verses sieve size. Provide mix proportion data using at least
three different water-cementitious material ratios for each type of
mixture, which produce a range of strength encompassing those required for
each type of concrete required. If source material changes, resubmit mix
proportion data using revised source material. Provide only materials
that have been proven by trial mix studies to meet the requirements of
this specification, unless otherwise approved in writing by the
Contracting Officer. Indicate clearly in the submittal where each mix
design is used when more than one mix design is submitted. Resubmit data
SECTION 03 30 00 Page 3
100 Man Compound Zamboanga City
PART 2 PRODUCTS
Provide a form tie system that does not leave mild steel after break-off
or removal any closer than 50 mm from the exposed surface. Do not use wire
alone. Form ties and accessories must not reduce the effective cover of
the reinforcement.
2.3.1.1 Footings
2.3.1.2 Slab-on-Grade
SECTION 03 30 00 Page 4
100 Man Compound Zamboanga City
Provide concrete that meets the requirements of ASTM C94/C94M or PNS 07.
2.4 MATERIALS
For exposed concrete, use one manufacturer and one source for each type of
cement, ground slag, fly ash, and pozzolan.
Provide cement that conforms to ASTM C150/C150M or PNS 07, Type II, with
tri-calcium aluminates (C3A) content less than 10 percent and a maximum
cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent.
Use one brand and type of cement for formed concrete having
exposed-to-view finished surfaces.
2.4.2 Water
SECTION 03 30 00 Page 5
100 Man Compound Zamboanga City
2.4.3 Aggregates
2.5 REINFORCEMENT
Use deformed steel. ASTM A615/A615M or PNS 49 with the bars marked A,
Grade 60; or marked A, Grade 40. Submit mill certificates for
reinforcing bars.
2.5.2 Wire
PART 3 EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
SECTION 03 30 00 Page 6
100 Man Compound Zamboanga City
3.2.1 General
3.3 FORMS
Provide forms, shoring, and scaffolding for concrete placement. Set forms
mortar-tight and true to line and grade. Chamfer above grade exposed
joints, edges, and external corners of concrete 20 mm unless otherwise
indicated. Provide formwork with clean-out openings to permit inspection
and removal of debris.
3.3.1 Reuse
SECTION 03 30 00 Page 7
100 Man Compound Zamboanga City
Provide bars, welded wire reinforcement, wire ties, supports, and other
devices necessary to install and secure reinforcement. Reinforcement must
not have rust, scale, oil, grease, clay, or foreign substances that would
reduce the bond. Rusting of reinforcement is a basis of rejection if the
effective cross-sectional area or the nominal weight per unit length has
been reduced. Remove loose rust prior to placing steel. Tack welding is
prohibited.
3.5.1 General
3.5.2 Splicing
3.5.3 Fabrication
Provide hooks and bends that are in accordance with NSCP 2015 .
Deliver reinforcing bars bundled, tagged, and marked. Tags must be metal
with bar size, length, mark, and other information pressed in by machine.
Marks must correspond with those used on the placing drawings.
SECTION 03 30 00 Page 8
100 Man Compound Zamboanga City
For slabs on grade (over earth or over capillary water barrier) and for
footing reinforcement, support bars or welded wire reinforcement on
precast concrete blocks, spaced at intervals required by size of
reinforcement, to keep reinforcement the minimum height specified above
the underside of slab or footing.
3.6.1 Measuring
3.6.2 Mixing
Machine mix concrete. Begin mixing within 30 minutes after the cement
has been added to the aggregates. Additional water may be added,
provided that both the specified maximum slump and water-cementitious
material ratio are not exceeded and the required concrete strength is
still met. When additional water is added, an additional 30 revolutions
of the mixer at mixing speed is required. Dissolve admixtures in the
mixing water and mix in the drum to uniformly distribute the admixture
throughout the batch. Do not reconstitute concrete that has begun to
solidify.
3.6.3 Transporting
SECTION 03 30 00 Page 9
100 Man Compound Zamboanga City
thoroughly before each batch. Do not use aluminum pipe or chutes. Remove
concrete which has segregated in transporting and dispose of as directed.
3.7.2 Bonding
Provide cement grout that consists of equal parts of portland cement and
fine aggregate by weight with not more than 22.5 liters of water per
sack of cement. Apply cement grout with a stiff broom or brush to a
minimum thickness of 1.6 mm. Deposit fresh concrete before cement
grout has attained its initial set.
Before concrete pours, designate for cleaning out concrete mixing trucks.
Minimize water used to wash equipment.
SECTION 03 30 00 Page 10
100 Man Compound Zamboanga City
3.9.1 Finish
3.9.1.1 Scratched
3.9.1.2 Broomed
3.9.1.3 Pavement
3.10 JOINTS
Make and locate joints not indicated so as not to impair strength and
appearance of the structure, as approved. Joints must be perpendicular to
main reinforcement. Reinforcement must be continued and developed across
construction joints. Locate construction joints as follows:
SECTION 03 30 00 Page 11
100 Man Compound Zamboanga City
NSCP 2015, except 10 days for pavement . Begin curing immediately after
placement. Protect concrete from premature drying, excessively hot
temperatures, and mechanical injury; and maintain minimal moisture loss at
a relatively constant temperature for the period necessary for hydration
of the cement and hardening of the concrete. The materials and methods of
curing are subject to approval by the Contracting Officer.
3.12.1 Sampling
SECTION 03 30 00 Page 12
100 Man Compound Zamboanga City
3.12.2 Testing
ASTM C39/C39M. Make six test cylinders for each set of tests in
accordance with ASTM C31/C31M, ASTM C172/C172M and applicable requirements .
Take precautions to prevent evaporation and loss of water from the
specimen. Test two cylinders at 7 days, two cylinders at 28 days, two
cylinders at 56 days and hold two cylinder in reserve. Take samples for
strength tests of each mix design of concrete placed each day not less
than once a day, nor less than once for each 75 cubic meters of concrete
for the first 380 cubic meters, then every 380 cubic meters thereafter,
nor less than once for each 500 square meters of surface area for slabs or
walls. For the entire project, take no less than five sets of samples and
perform strength tests for each mix design of concrete placed. Each
strength test result must be the average of two cylinders from the same
concrete sample tested at 28 days. Concrete compressive tests must meet
the requirements of NSCP 2015. Retest locations represented by erratic
core strengths. Where retest does not meet concrete compressive strength
requirements submit a mitigation or remediation plan for review and
approval by the contracting officer. Repair core holes with nonshrink
grout. Match color and finish of adjacent concrete.
Factors that indicate that there are non-conforming materials include (but
SECTION 03 30 00 Page 13
100 Man Compound Zamboanga City
Air dry cores, (16 to 27 degrees C with relative humidity less than 60
percent) for 7 days before test and test dry if concrete they
represent is dry under service conditions.
Fill core holes solid with patching mortar and finished to match adjacent
concrete surfaces.
Before the Contracting Officer accepts the structure the Contractor must
inspect the structure for cracks, damage and substandard concrete
placements that may adversely affect the service life of the structure. A
report documenting these defects must be prepared which includes
recommendations for repair, removal or remediation must be submitted to
the Contracting Officer for approval before any corrective work is
accomplished.
SECTION 03 30 00 Page 14
100 Man Compound Zamboanga City
-- End of Section --
SECTION 03 30 00 Page 15