3.method Statement Backfilling and Compaction
3.method Statement Backfilling and Compaction
2. Location of Activity
outside of the building.
3. Scope of Work.
The method statement covers all activities related to the Backfilling and Compaction works.
General Description
The purpose of this Method Statement is to give a general outline of the methodology that will be used
for Backfilling and Compaction works at, The WTC to identify the risk associated during the Backfilling
and Compaction works and to identify the quality control system to ensure full compliance with the
client’s requirements and as per the project specification.
The works shall be executed in accordance with the following methodology and sequence;
1. Backfilling
Before installing the facilities where required (Piping, Cables etc.,) necessary bedding shall be
made as required to avoid damage to the facilities as specified in project specifications or by
specification of concerned authority.
All the back fill materials should be tested and evaluated for the applicable grade and suitability.
The source details of the borrow materials shall be submitted to the Employer's Representative
for approval. No material shall be brought to the site until the material is approved by the
Employer's Representative.
Backfilling shall be placed in uniform layers of the specified thickness and wetting operations, if
required, shall be carried out in a way so that uniform moisture content is assured throughout
each layer.
2. Compaction
Materials shall be moistened or aerated as necessary to provide the moisture content required to
obtain the specified compaction.
The field Density Test shall be conducted and recorded as directed by the Employer's
Representative and as specified in the project specification and ITP.
Note that particular specification shall be applied to compaction around and above district
cooling pipe work and these will be issued by the concerned authority in the near future
.
3.Structural Backfilling
Trenches shall not be backfilled until all required tests and inspection are performed and the
service therein approved by Employer's Representative and concerned authority.
Trenches shall be backfilled to the finished grade with suitable material for the specified degree
of compaction as applicable to the particular area.
Trenches improperly backfilled shall be reopened to the depth required for the proper degree of
compaction and then refilled and compacted.
Special care shall be taken to provide a firm sand bedding / suitable material to the bottom of the
pipe and fittings or any services for the full length of the pipe. Where the pipe is coated or
insulated, great care shall be exercised in padding and backfilling to prevent damages to the
coating or insulation.
After the pipe has been thoroughly bedded and covered and provide suitable caution tape or
concrete slab etc, and the trench shall be backfilled with suitable excavated material.
Backfilling material shall be evenly spread for the full width of the trench in layers not exceeding
150 mm in compacted thickness.
Each layer shall be compacted to the specified density as applicable to the particular area crossed
by the trench.
The protective concrete tiles, as shown in the drawings, shall be placed after the services have
been covered with sand or suitable material and layers compacted and remainder of trench shall
be backfilled.
2
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
The various type of fill including common fill, selected structural fill, clean sand, sand and all
type of road base shall be compacted as per contract specification or requirements.
Common fill material shall be compacted to at least 98% for Roads & other structure, 95% for
general fill. The dry density to be obtained by the Modified Proctor Test, ASTM D-1577.
Granular fill material shall be compacted to at least 95% and 98% respectively of the maximum
dry density obtained by the Modified Proctor Test, ASTM D-1577.
Clean sand and sand shall be compacted to at least 95% and 90% respectively of the maximum
dry density obtained by the Modified Proctor Test, ASTM D-1577.
3
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
4. Responsibility
Project Engineer:
The Project Manager and the Construction Manager have the responsibility for the overall operations of
this statement. The Project Manager and Construction Manager have the responsibility to implement the
Method statement and to delegate the responsibility to a Site Engineer and the QC Engineer to directly
supervise the work on site. The site Engineer is responsible for ensuring that all the works are executed
in accordance with the specified requirements.
The Project Manager will be responsible for the following.
Plan and schedule the jobs, determine priorities, control workload, inspect projects and keep sufficient time
records for workflow and outputs.
Performs technical responsibilities and make decisions to a substantial extent.
Reviews and interprets proposed designs, drawings, and specifications for appropriateness to required
function and/or standard and initiates revisions.
Ensure that project operations are in compliance with design specifications
To provide all the necessary information to the site team.
Engineer/Supervisor in charge to conduct a toolbox meeting and communicate both the Method Statement
& Risk Assessment to the workers before commencement of the activity.
All safety precautions shall be followed as per established project safety procedure.
Only experienced and skilled labour shall be engaged for carrying out screed work.
People involved in the construction work shall wear PPE such as safety helmets, safety shoes, safety harness,
gloves safety glass, mask etc.as required.
All Hose pipe joints are properly connected and tied with clips.
Safety officer shall check and ensure that all safety precautions are followed.
All the safety equipment’s shall be periodically inspected and checked for its durability before using them to
labor.
Manual handling procedures to be followed
Any incident or near miss incident shall be reported immediately to the concerned safety officer.
Site Supervisor:
4
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC
Foreman:
To provide the Site supervisor with daily progress reports and discuss with him planned works for the next
day.
To ensure that all safety measures are maintained at site and workers have proper training for following all
current safety guidelines and housekeeping in accordance with the Main Contractors Safety Officer.
To ensure good housekeeping is practiced and proper tools are being used by the site team.
To ensure that all persons involved in the works are aware of their duties, and that they have enough
understanding of safety procedures.
To conduct frequent toolbox meeting on safety awareness and to maintain a log of all meetings for
inspection.
To keep a record of all toolbox talks.
Liaises with the required personnel at the site for the required inspections with regards to safety.
Attends all the safety coordination meetings.
Ensure that the basic and activity specific PPE is worn regularly by the site working team.
5. Equipment Requirements
The requirements that will be engaged for Backfilling and Excavation work will be as follows:
Site In-charge.
Charge Hand.
Surveyor.
Operator.
Skilled Labour.
Unskilled Labour.
Backhoe excavator JCB
Shovel.
Dump Truck.
Compactor