SCS Climbing System
SCS Climbing System
SCS Climbing System
Issue 06 | 2019
Publisher
PERI GmbH
Formwork Scaffolding Engineering
Rudolf-Diesel-Strasse 19
89264 Weissenhorn
Germany
Tel. +49 (0)7309.950-0
Fax +49 (0)7309.951-0
info@peri.com
www.peri.com
Project Examples
26 The SCS Climbing System
in use
Important information
All current safety regulations and guidelines appli- installations which have possibly not been shown
cable in those countries where our products are in these detailed descriptions must nevertheless
used must be observed. still be available. The systems or items shown
might not be available in every country.
The images shown in this brochure feature con-
struction sites in progress. For this reason, safety Safety instructions and load specifications are to be
and anchor details in particular cannot always be strictly observed at all times. Separate structural
considered conclusive or final. These are subject to calculations are required for any deviations from
the risk assessment carried out by the contractor. the standard design data.
In addition, computer graphics are used which The information contained herein is subject to
are to be understood as system representations. technical changes in the interests of progress.
To ensure a better understanding, these and the Errors and typographical mistakes reserved.
detailed illustrations shown have been partially
reduced to show certain aspects. The safety
3
4
SCS Climbing System
5
6
System Advantages
The Climbing System SCS is pre- The Climbing System SCS is character-
dominantly used for single-sided ised by a high level of cost-effectiveness: Optimised use of crane time
applications, i.e. with non-tied wall on the one hand, the well-thought-out
formwork. The loads resulting from modular concept with multi-part Brack- thanks to large, craneable climbing
the fresh concrete pressure are ets facilitates easy and simple adapta- units – also with large formwork
thereby transferred via the Brackets tion to suit project-specific require- heights and circular structures
into the previous concreting section ments and geometries. On the other,
by the Climbing Anchors. Typical are- the high load-bearing capacity of the
as of application for the Climbing Brackets allows wide climbing units
System SCS are dams, locks, cooling which, in turn, reduces material re-
towers, bunkers and strongroom quirements and workload respectively.
vaults, pier heads and tunnels. With
only a minimum of additional com- The wider SCS 250 version is equipped
ponents, the system can also be with a formwork carriage for retracting Material-optimised solution
used extremely cost-effectively for the formwork. This carriage can also be
two-sided applications. used on circular structures; thereby, an with the same formwork and
adapter ensures that the Brackets are components for the starter and
With the System SCS, two bracket units always arranged in a parallel position. subsequent standard cycles
together with one PERI Wall Formwork
section form a crane-movable platform Thanks to its modular design, the SCS
unit. Optionally, VARIO GT 24 Girder can be delivered pre-assembled to the
Wall Formwork as well as TRIO or construction site with subsequent fast
MAXIMO Panel Formwork can be used. final assembly.
With the SCS, full consideration is also
The Climbing System SCS has been given to safety issues: if inclined com-
optimised for a concreting height of ponents are formed, the inclination of Safe, horizontal working areas
3.00 m (vertical applications) or 2.50 m the working platforms can be adjusted
(forward-inclined applications). If separately; in addition, the concreting due to the horizontal alignment
required, a finishing platform can be and finishing platforms can be tilted by of the platforms also for inclined
added. With only a minimum of additional ± 15° and ± 30° respectively. Ladders working operations
components, use with anchored form- with hatches ensure safe access to
work is also possible for walls up to working levels; end-to-end side protec-
6.00 m high. tion can be attached to all platforms.
7
System Advantages
1,90 m 2,50 m
Bracket Bracket
8
System Advantages
For the first casting segment, a Starter Brace Frame is used With only a minimum of additional components, the SCS
while diagonal anchoring transfers the loads into the bottom Climbing Bracket can also be used for anchored wall form-
slab. work up to 6.00 m high. This ensures increased material
utilisation of the system components and thus enhanced
The SCS Starter Brace Frame is designed in such a way that cost-effectiveness of the investment.
the Strongback, Spindle and Formwork can also be used in
the next casting segments with the Climbing Bracket.
Concreting
Platform
Intermediate
Platform
6,00 m
Arbeitsbühne
Bracket
Intermediate
Finishing Platform
Concreting Platform
Finishing Platform
9
System Advantages
For moving the Climbing Units by crane, the formwork The Climbing Unit is then released and removed from
is tilted backwards slightly. the mounting rings or mounting bolts, and then lifted.
10
System Advantages
The Cross Beam is subsequently mounted on the next high- After this, the crane lifting gear can be released. Following
est mounting rings or mounting bolts, and then secured. this, the Leading Anchor for the next casting segment is
fixed to the formwork.
11
System Advantages
■■ Mounting Bolt SCS for high Cimbing Cone M30 / DW 20 Mounting Ring SCS M30
tensile forces
■■ Mounting Ring SCS for high
vertical loads
■■ Climbing Cone M30 / DW 20
Cimbing Cone M36 / DW 26 Mounting Bolt SCS M36 Mounting Ring SCS M36
12
System Advantages
Advantages of the
Angle Adapter SCS on circular structures
The Angle Adapter is attached to the Head Plate of the max. β= ± 15º max. β= ± 15º
Cross Beam Unit. The Adapter can be pivoted by 15° so
that there is a parallel arrangement of the brackets. The
Swivel-Mounted Pressure Point is used on the vertical
strut.
13
System Advantages
Material-optimised solution
Same formwork and components for the starter
and subsequent standard cycles
With the so-called starter cycle, the The Starter Bar transfers the loads from Thus, for example, the Climbing Bracket
loads are transferred into the bottom the first concreting section into the consists of multiple parts so that most
slab. This cycle frequently has to be bottom slab. For subsequent cycles, of the same components are used for
carried out with varying heights, e.g. Strongbacks, Spindles and the formwork both the SCS 190 and SCS 250.
on uneven terrain. Only one addi- are simply mounted on the brackets The Adjusting Unit as well as the sepa-
tional component is required for the and reused without requiring any modi- rate vertical and diagonal struts are
SCS: the Starter Bar SCS. fications. In general, the SCS Climbing used in both system versions. Last but
System follows a modular concept; in not least, the SCS 190 and SCS 250
addition, all system components are utilise identical system components for
consistently designed to accommodate the formwork support and for the finish-
a system grid of 125 mm – as with the ing and concreting platforms.
VARIOKIT Engineering Construction Kit.
This ensures maximum utilisation of the
components and therefore a high level
of cost-effectiveness.
14
System Advantages
For anchoring the Starter Brace Frames, an SRU The alternative anchoring solution consists of With SCS, inclined Starters can also be realised as
Waler together with Tie Rods and Wingnut Pivot Tie Yokes and Wingnuts. the inclination of the wall is adapted to suit using
Plates can be used. the Heavy-Duty Spindle.
15
System Advantages
SCS is very flexible and safe to use. For dams and other similar structures
The platforms themselves can be which are realised using single-sided
aligned horizontally even during in- forming operations, inclined areas very
clined working operations. In addi- frequently need to be constructed. The
tion, 1.50-m-high Guardrails in- SCS Climbing System also provides
stalled on the working platforms the flexibility needed to form these
provide a high level of work safety. surfaces efficiently and safely.
16
System Advantages
Execution featuring a component with a forward Execution featuring a component with a rear
inclination of up to 30°. inclination of up to 30°.
17
System Advantages
18
System Advantages
While the Climbing Bracket is being fixed to the Accessing the finishing platform via the ladder is
wall, the finishing platform is mounted on it. When safe at all times – even with retracted formwork.
moving the unit, the finishing platform then For descending from the working platform to the
swings into a vertical position. This means that re- finishing platform, a cantilevered ladder platform
maining under suspended loads is not necessary can be integrated.
at any time.
19
System Overview
20
System Overview
21
System Overview
The first casting segment is constructed For the second casting segment, the Striking is carried out with the help of
using the Starter Brace Frame. In the Climbing Bracket is used without a fin- the Heavy-Duty Spindle, Adjusting Unit
process, the horizontal Starter Bar is ishing platform. Formwork, Strongback and Formwork Carriage. To do so, first
anchored in the bottom slab and, and spindle of the Starter are mounted release the mounting for the leading
together with the formwork, comple- on the Bracket. anchor after the concrete has hard-
ments the Strongback and the Heavy- ened. The Mounting Ring must subse-
Duty Spindle. The latter components quently be fixed to the embedded
can be re-used during subsequent use Leading Anchor to which the climbing
with the Climbing Bracket. unit is later attached. Any wind safety
devices are to be detached, while
anchors which are no longer required
must be removed and anchor holes
must be sealed with plugs.
22
System Overview
After striking, the climbing unit is pre- The climbing unit is lifted using the The formwork must be cleaned before
pared for the moving procedure. Crane crane and attached to the next highest each subsequent concreting cycle while
hooks are to be attached to the Strong- anchoring. The Locking Pins secure the the Leading Anchors are attached to
backs of the climbing unit, and the Lock- Brackets against lift-off; if necessary, a the formwork. The formwork is set up
ing Pins of the Bracket are released. wind safety device can be installed. in the concreting position by means of
The finishing platform is subsequently the Formwork Carriage and Adjusting
mounted. Unit, and then adjusted using the
Height Adjustment Unit and Spindle.
The first standard cycle is then concreted.
23
System Overview
Execution details
By turning the Heavy-Duty Spindle, the required The formwork is vertically aligned by means of the After opening the Waler Fixation, the formwork
formwork inclination can be adjusted in each Adjusting Bolt on the Height Adjusting Unit. can be horizontally aligned.
case.
The Adjusting Unit is operated quickly and easily The Adjusting Unit is used for the SCS 190 ver-
with the ratchet wrench. sion as well as for the SCS 250 with Formwork
Carriage. This helps to minimise the number of
different system components.
24
System Overview
25
Project Examples
The Panama Canal has connected From 2011 onwards, PERI delivered
the Atlantic and Pacific Oceans since more than 1,100 containers filled with
1914 and is one of the most impor- formwork and scaffolding materials to
tant waterways in the world: a total the construction sites. The Climbing
of 6 % of the cargo shipped world- System SCS played a major role in the
wide is transported through the overall solution.
Panama Canal. From 2011 to 2014, Due to its size and complexity, the pro-
the waterway was expanded to ac- ject entailed major challenges in terms
commodate larger container ships. of know-how, logistics and construction
Key measures were the construction site support. The transnational and in-
of two new locks on the Atlantic and tercontinental cooperation involving the
Pacific sides. international team of PERI engineers,
logistics experts and other specialist
engineers was an essential key to the
success of the project.
26
Project Examples
27
Project Examples
For the largest-ever individual contract in the company's history, PERI supplied PERI supported the construction of the impressive dam near the Portuguese
a comprehensive overall concept and innovative climbing technology as well town of Alijó, among other things, with an extensive range of engineering
as delivering a very impressive performance. services.
Panama Canal Lock Facilities, Panama Foz Tua Dam, Alijó / Vila Real, Portugal
PERI Spain and PERI Panama were responsible for the form- For the construction of the Foz Tua Dam and the nearby
work planning, logistics and on-site assistance for the ex- pumped-storage power plant, PERI developed and supplied
pansion of the Panama Canal – competently supported by an optimised and safe formwork and scaffolding solution.
PERI headquarters in Weissenhorn. PERI delivered more With a comprehensive concept as well as logistical and
than 1,100 containers to the construction site. technical services, PERI specialists supported the contrac-
tors – Barragem de Foz Tua, ACE – in ensuring dimensional-
To ensure that the tight schedule could be maintained, a ly-accurate construction work along with on-schedule com-
total of 4,200 personnel on both jobsites processed around pletion. The close cooperation between the PERI engineers
6,300 m³ of concrete on a daily basis in two shifts. Within and all project participants, as well as continuous coordina-
the construction period of three years, the construction site tion provided by PERI project managers on the jobsite, en-
team formed an area of about 2.2 million square metres; the sured the success of the project.
material used amounted to approx. 6.6 million cubic metres
of concrete and 337,500 tonnes of steel. The construction The dam wall in northern Portugal reaches a total height of
site facilities included 70 cranes and 30 concrete pumping 108 m while the length of the dam's crest measures 275 m.
stations. These boundary conditions required an immense Regarding formwork considerations, the complex form of
outlay of formwork and scaffolding materials along with a the double-curved reinforced concrete construction with a
comprehensive overall concept. 5-m-wide dam crest was especially challenging.
An essential element of the PERI solution was the SCS PERI engineers developed a formwork concept using the
Climbing System for single-sided applications, which was Climbing System SCS and VARIO GT 24 Girder Wall Form-
used for the first time on this construction site. Depending work. This combination was the ideal solution for the massive
on the project requirements in the respective areas of the dam wall as it allowed single-sided transfer of loads and met
site, PERI engineers combined the brackets with either VARIO the high surface requirements.
Girder Wall Formwork or TRIO Panel Formwork. Different
shoring systems taken from the PERI product portfolio
ensured efficient transfer of loads under the slab formwork,
which was carried out in part with pre-assembled slab tables.
In particular, PERI UP Flex Modular Scaffolding was extremely
versatile in its application as it was used for the shoring as
well as realisation of safe access means.
28
Project Examples
Important dam upgrade project: as part of a hydroelectric power plant expan- The massive power plant walls were formed in a single-sided process and
sion in Alaska, the height of the dam wall was to be increased. concreted using the Climbing System SCS.
Blue Lake Dam, Sitka / Alaska, United States of America Smithland Hydroelectric Power Plant, Smithland /
Kentucky, United States of America
The Blue Lake Dam Project in Alaska centred on expanding
the existing dam. The dam supplies electricity to the city of For the Smithland hydroelectric power plant, PERI supplied
Sitka in the north-west of the United States. Among other a customised formwork and shoring solution. The extremely
things, new intake structures and penstocks along with lock tight construction time, massive structural elements and in
gates were realised. In addition, the height of the existing part multi-curved shapes required not only large quantities
arch dam wall was to be increased by around 27 m. After of system equipment but also countless, specially designed
completion of the project, the hydroelectric power plant 3D formwork units. With a comprehensive concept, the
now generates 27 % more electricity, boosting the city's PERI specialists supported the construction company in en-
energy independence. suring that the efficient and dimensionally accurate execution
was carried out on schedule. These included close, transna-
Different PERI systems were used to construct the various tional cooperation between PERI engineers, prefabrication
structures of this large-scale project – for example, the of the formwork elements, as well as on-going coordination
Climbing System SCS was used to realise the massive arch by a PERI project manager on the construction site.
of the new dam crest. The project-specific planning solution
combined the brackets with VARIO GT 24 Girder Wall Form- A large part of the massive walls were realised with the
work. Climbing System SCS – as a result, no anchors were required.
As this formwork solution avoided any costly sealing work,
large savings could be made regarding the time and costs
required for the construction work. Thanks to the particularly
high load-bearing brackets and best utilisation of the anchor-
ing, large climbing units were also possible, further acceler-
ating construction progress.
29
Project Examples
The high flexibility of the Climbing System SCS allowed an easy adaptation to Comprehensive formwork solutions and a high degree of prefabrication also
suit all geometries in this dam project. helped to deal with complex building geometries at a depth of 15 m - easily,
accurately and on schedule.
Around 30 km to the east of the provincial capital, Xayaburi, A new 216-m-long, 12.60-m-wide and 12.70-m-high lock
a dam complete with a hydroelectric power station was built chamber was constructed parallel to the existing Moselle
on the Mekong river in northern Laos. It is the first structure Lock located south of Trier. As the 15-m-deep structure re-
of a total of 11 dams which have been planned for the lower quired a very high degree of reinforcement, PERI delivered
Mekong Basin. With a nominal output of 1,260 megawatts, prefabricated formwork units on the basis of VARIO GT 24
the Xayaburi hydroelectric power station is, in this respect, Girder Wall Formwork just-in-time to this major construction
the third largest project in the overall planning. A shipping site, which were specifically adapted to match project re-
lock and two fishways were also planned. quirements, and ensured that material quantities and sched-
uling exactly suited the technology of the jobsite.
The dam wall is 820 m long and has a total height of 49 m,
whereby the water level has been raised by 32 m. For realising Clearly marked elements were manufactured with very
the reinforced concrete work, PERI designed and supplied a small tolerances and could be immediately allocated to the
formwork solution based on the SCS Climbing System. In respective place of installation. The design of the formwork
particular, the flexibility of the system was very important to carriage for constructing the longitudinal channels was also
ensure the smooth execution of the construction work so as well thought-out down to the smallest detail and likewise
to form the variable geometry. In addition to the straight pre-assembled at the company's assembly hall using PERI
dividing walls, there were also many areas of the dam to be system components.
constructed with rounded shapes. Along with the planning
solution, providing training to the construction team also Moreover, it proved to be advantageous that the PERI prefab-
formed a large part of the PERI support to ensure success- rication operations were used to realise - in addition to the
ful execution. formwork elements - all recess units and timber formers
used, e.g. for intake funnels, gate recesses and floating bol-
lards- which were designed with a focus on providing efficient
striking operations as well as ensuring reusability. The SCS
Climbing System, used as scaffolding for the 7.80-m-high
VARIO GT 24 Girder Wall Formwork, guaranteed optimal
workflows. A PERI project coordinator supported the site
management team with the coordination and control of the
planning and assembly processes. In addition, PERI supervi-
sors briefed the construction team on the correct handling
and assembly of the various formwork and scaffolding solu-
tions.
30
Project Examples
Free-form formwork on SCS Climbing Brackets for a large concrete funnel. Special suspension points ensured that the formwork elements could easily
be lifted into the respective final position with the crane.
The Bagatelle dam project has improved the water supply Ø 27,00
31
Project Examples
32
Project Examples
33
PERI International
RU
CA
KZ
US AZ
TR
KR JP
TN LB
MA IL IR
JO KW
DZ
EG QA
MX SA AE IN
HK
OM
TH
PH
PA VN
NG
CO MY
SG
ID
TZ
PE BR
AO MZ
NA
CL AU
ZA
AR
MX Mexico DZ
Algeria AZ
Azerbaijan LB
Lebanon
PERI Cimbras y Andamios, S.A. de C.V. S.A.R.L. PERI PERI Repesentative Office PERI Lebanon Sarl
www.peri.com.mx www.peri.dz www.peri.com.tr lebanon@peri.de
PA
Panama EG
Egypt HK
Hong Kong MY
Malaysia
PERI Panama Inc. Egypt Branch Office PERI (Hong Kong) Limited PERI Formwork Malaysia Sdn. Bhd.
www.peri.com.pa www.peri.com.eg www.perihk.com www.perimalaysia.com
US
USA MA
Morocco ID
Indonesia OM
Oman
PERI Formwork Systems, Inc. PERI S.A. PT Beton Perkasa Wijaksana PERI (L.L.C.)
www.peri-usa.com www.peri.ma www.betonperkasa.com www.peri.ae
MZ
Mozambique IL
Israel PH
Philippines
PERI (Pty.) Ltd. PERI F.E. Ltd. PERI-Asia Philippines, INC.
South America www.peri.co.mz www.peri.co.il www.peri.com.ph
AR
Argentina NA
Namibia IN
India QA
Qatar
PERI S.A. PERI (Pty.) Ltd. PERI (India) Pvt Ltd PERI Qatar LLC
www.peri.com.ar www.peri.na www.peri.in www.peri.qa
BR
Brazil NG
Nigeria IR
Iran SA Saudi Arabia
PERI Formas e Escoramentos Ltda. PERI Nigeria Ltd. PERI Pars. Ltd. PERI Saudi Arabia Ltd.
www.peribrasil.com.br www.peri.ng www.peri.ir www.peri.com.sa
CL
Chile TN
Tunisia JO
Jordan SG
Singapore
PERI Chile Ltda. PERI S.A.U. PERI GmbH – Jordan PERI Asia Pte Ltd
www.peri.cl www.peri.es www.peri.com www.periasia.com
CO
Colombia TZ
Tanzania JP
Japan TH
Thailand
PERI S.A.S. PERI Formwork and Scaffolding Ltd PERI Japan K.K. Peri (Thailand) Co., Ltd.
www.peri.com.co www.peri.co.tz www.peri.co.jp www.peri.co.th
PE
Peru ZA South Africa KR
Korea TR
Turkey
PERI Peruana S.A.C. PERI Formwork Scaffolding (Pty) Ltd PERI (Korea) Ltd. PERI Kalıp ve İskeleleri
www.peri.com.pe www.peri.co.za www.perikorea.com www.peri.com.tr
KW
Kuwait VN
Vietnam
PERI Kuwait W.L.L. PERI ASIA PTE LTD
www.peri.com.kw www.peri.com.vn
IS
FI
NO
SE EE
RU
LV
DK
LT
IR GB BY
NL PL
BE DE
LU CZ UA
SK
PERI GmbH
Formwork Scaffolding Engineering AT
CH HU
Rudolf-Diesel-Strasse 19 FR SI RO
89264 Weissenhorn HR
Germany
Tel. +49 (0)7309.950-0 BA RS
Fax +49 (0)7309.951-0 IT
BG
info@peri.com
www.peri.com
AL
ES
PT GR
TR
Oceania
AU
Australia DK
Denmark IT
Italy SE
Sweden
PERI Australia Pty. Ltd. PERI Danmark A/S PERI S.r.l. PERI Sverige AB
www.periaus.com.au www.peri.dk www.peri.it www.peri.se
EE
Estonia LT
Lithuania SI
Slovania
PERI AS PERI UAB PERI oplate i skele d.o.o
Europe www.peri.ee www.peri.lt www.peri.com.hr
AL
Albania ES
Spain LU
Luxembourg SK
Slovakia
PERI Kalıp ve İskeleleri PERI S.A.U. N.V. PERI S.A. PERI spol. s. r.o.
www.peri.com.tr www.peri.es www.peri.lu www.peri.sk
AT
Austria FI
Finland LV
Latvia UA
Ukraine
PERI Ges.mbH PERI Suomi Ltd. Oy PERI SIA TOW PERI
www.peri.at www.perisuomi.fi www.peri-latvija.lv www.peri.ua
BE
Belgium GB United Kingdom NO
Norway
PERI N.V. PERI Ltd. PERI Norge AS
www.peri.be www.peri.ltd.uk www.peri.no
BG
Bulgaria GR
Greece PL
Poland
PERI Bulgaria EOOD PERI Hellas Ltd. PERI Polska Sp. z o.o.
www.peri.bg www.perihellas.gr www.peri.com.pl
BY
Belorussia HR
Croatia PT
Portugal
IOOO PERI PERI oplate i skele d.o.o. Pericofragens Lda.
www.peri.by www.peri.com.hr www.peri.pt
CH
Switzerland HU
Hungary RO
Romania
PERI AG PERI Kft. PERI România SRL
www.peri.ch www.peri.hu www.peri.ro
CZ Czech Republic IR
Ireland RS
Serbia
PERI spol. s r.o. Siteserv Access & Formwork PERI oplate d.o.o.
www.peri.cz www.siteservaccess.ie www.peri.rs
DE
Germany IS
Iceland RU
Russia
PERI GmbH Armar ehf. OOO PERI
www.peri.de www.armar.is www.peri.ru
The optimal System
for every Project and
every Requirement
PERI GmbH
Formwork Scaffolding Engineering
Rudolf-Diesel-Strasse 19
89264 Weissenhorn
Germany
Tel. +49 (0)7309.950-0
Fax +49 (0)7309.951-0
info@peri.com
www.peri.com