2005-4100-0R-0011 - Rev0 - ITP For Jacket and Deck Installation (JRM Scope) - Approved Printed
2005-4100-0R-0011 - Rev0 - ITP For Jacket and Deck Installation (JRM Scope) - Approved Printed
2005-4100-0R-0011 - Rev0 - ITP For Jacket and Deck Installation (JRM Scope) - Approved Printed
MSuTuDen
NorthEast
SU TU DEVELOPMENT
SU TU DEN NORTHEAST
Wellhead Platform, Submarine Cable
And Pipelines
PTSC
MECHANICAL & CONSTRUCTION CO. LTO.
G)
I P lse
JRMFEI PROJECT NO: R2891
DISTRIBUTION LIST
(Document No: 2005-4100·0R·0011)
1. The Custodian is responsible for review and reissue of this document and ensuring for its
compliance with the contents.
2. It is the responsibility of all distributed persons to ensure the most current revision of this
document is available at the work place and that the documents referenced in it are applied to all
aspects of the project.
3. This document will be sUbject to regular review and will be updated to reflect any necessary
changes.
4. The Recipient of this document is responsible to distribute the procedure to other parlies
working under his / her supervision to ensure this procedure is implemented by all parlies
involved.
Inspection and Test Plan for Jacket and Deck PAGE 3 OF 24
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
TABLE OF CONTENTS
1. REFERENCES 5
3. NOMENCLATURE 6
5. NDT PLAN 24
Inspection and Test Plan for Jacket and Deck PAGE 5 OF 24
: ". Installation (JRM Scope)
Su Tu Den Northeast Project REVISION 0
•
_....:::::=--_~J!.:..~R~ayl..'!M'-"c~D~erC!!m!!.!o~tt!..!FlJa!!:r-"E'!!a~st"-.!.'l n"-"c:..... -.!:DJ!l:AJ.!TE=--_: 20.04.2009
1. REFERENCES
1.1 Project Specifications and Procedures
2005-4100-0R-000l Overall Project Execution Manual
2005-4100-0L-0004 General Quality Requirements Specification
2005-4191-6L-0001 Specification for Structural Materials
2005-4191-6L-0002 Specification for Structural Fabrication and Welding
2005-4102-1 L-0001 Painting and Protective Coating Specification
2005-41 OO-OL- 0008 Welding Procedure and Performance Qualification
Specification
2005-4191-1 L-0003 Specification for Load-out, Transportation and Installation
2005-4100-0Q-0005 Structural Welder Certification Records
2005-4100-0P-0009 Structural Welding Procedures
2005-4100-0P-0022 NOT Personnel. CV's and Certification Records
(Structural)
2005-4100-0P-0024 Structural NOT Procedure
2005-4100-0P-0022 NOT Personnel. CV's and Certification Records
(Structural)
2005-4100-0P-8001 Offshore Structural Blasting and Painting Procedure
Hold Point (H) - an activity identified in the ITP beyond which further work shall not proceed
without the attendance of the nominated inspector. In case of a "Hold Point" of the Company, the
Contractor shall not proceed with the WORK without the Company or its representative being
present, except where the Company has notified the Contractor in writing that it may proceed.
Witness Point (W) an activity identified in the ITP required to be witnessed by the
nominated inspector. In the case of a 'Witness Point" of the Company, the Contractor may proceed
with the inspection and / or testing activity if the Company or its representative is not present after
being provided with the required written notice. Note :for visual inspection of weld ,verbal notice will
be given to the client.
20.04.2009
Monitoring Point (M) - random check by direct or indirect inspection of the conformance of the
item or activity known as patrol inspection
3. NOMENCLATURE
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
Contract MDR
1.3 HSE Procedure Approval HSE Manager Singapore HSE Deliverables R R R R
Agreement
MDR
Operation Contract
1.4 Engineering Documents Approval Singapore JRMIEH/OFF-004 R R R R
Manager Agreement
20054191-6L-
Valid Welders
Welding 0002 Para.7.0 WQT Certificates, Welders List
2.3 Welders Qualification Approval Batam Qualification R/H R H RIW
Engineer QP-027 Clause (see note 2)
Certificates
4.0, AWS Dl.l
3.0 MATERIALS,TOOLS AND EQUIPMENT
Inspection and Test Plan for Jacket and Deck PAGE 8 OF 24
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East. Inc. DATE 20.04.2009
3.1.1 Check availability of required Survey/ROV Offshore JRMIEH/OFF·OO5 Su bcontract List of available Equipments
M M M M
survey/ROV Subcontractor Site Para.2.0 Agreement (see note 1)
History of Calibralfon,
3.1.2 Check Survey/ROV equipment Survey/ROV Offshore JRM/EH/OFF-005 Su bcontract
maintenance M M M M
operational status. Subcontractor Site Para.2.0 Agreement
(see note 1)
QC 2004-4000·0L·
3.1.3 Review of Calibration and Offshore Su bcontract Calibration Certificate
Coord inator, 0001 Para.5.10 R/H R R R
Testing Certificate Site Agreement (see note 1)
Field Engineer
3.2 NOT and Welding EqUipment
List of available NOT
3.2.1 Availability of required NOT NOT & QC Offshore 2005-4191-6L· Subcontract
equipments/Checklist Register W/M R R R
equipment. Supv. Site 0002 Para 11.0 Agreement
(see note 2)
NOT & QC Offshore Calibration Certificate
3.2.1 Calibration of NOT equipments QP-032 Valid Certificate R/H R W R
Supv. Site (see note 1)
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
Field Engr/ QC
5.1.6 Check the required detailed Inspector Fabrication 2005-4191-6L- As required by the Inspection Checklist
M R R M
procedure for plan load-out Yard 0003 Para 5.6 procedure
Field Engr/ QC JRM/EH/OFF-005,
5.1.7 Ensure that all barges to be used Inspector 006, Loadout
Pre-approved Transportation
are compatible in all aspects to the Fabrication Coordination Approved
Arrangement Documents M R R R
load-out facilities and arrangement of Yard Manual Documents
fabrication yard. 2005-4191-6L-
0003 Para6.6.2
5.2 During Load-Out Activity
All the items
5.2.1 Check the marine requirements JRMIEH/OFF-G05,
Fabrication required are
for the transportation barge, i.e. Field Engineer 006, Loadout Checklist
Loadout available and in M M M M
mooring bol1ards, navigation lights, / QC Inspector 2005-4191-6L- (see note 2}
Area good/working
ballast condition etc. 0003 Para 5.6 condition.
Inspection and Test Plan for Jacket and Deck PAGE 11 OF 24
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
24
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION
---0----
J. Ray McDermott Far East, Inc. DATE 20.04.2009
•
Installation (JRM Scope)
Su Tu Den Northeast Project REVISION o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
Notes:
1. these documents wili be approved prior to commencement of the activity and will be included in the final MDR
2, These document will be available on request for verification at barge QC office. Copies of all reports/records/data to be made available for CLJOC
3. these document will be part of the final document submission to the cHent
Inspection and Test Plan for Jacket and Deck PAGE 24 OF 24
Installation (JRM Scope)
Su Tu Den Northeast Project REVISiON o
J. Ray McDermott Far East, Inc. DATE 20.04.2009
5. NOT PLAN
Misc. Fabrication
Structural fillet 10% MT
Arc strikes 100"10 MT
Weld repairs (Note 6) 100% RT, MT ,0rUT
1) Based on percent of total weld length. Company to designate welds inspected to less than 100%.
2} All welds (structu ral and non structural) and structural steel are subjectto 100% Visual Test (VT) at all times VT may include
Penetrant Test (PT).
3) Projection ofthe brace onto the joint can plus an additional 150mm (6 in.) radius around the circumference of the projection.
4) Projection of the pad eye or pedestal plus an additional segment equal to 5times the pad eye thickness.
5) Although conventional techniques are generally limited to these dimensions. smaller members may require examination ff they
are designated primary welds.
6) NDE should be the same as the original inspection and performed by the same party.
7) For jackets with skirt piles.
8) Visual examination of each pass and Magnetic Testing (MTl upon completion of welding.
9) Primary structural pad eyes utilized by Contractor during the construction phase shall be subject to the applicable 100% NDE
both before and after use.