Vertical Drain: Works Method & Commercial Aspect

Download as pdf or txt
Download as pdf or txt
You are on page 1of 33

VERTICAL DRAIN

WORKS METHOD & COMMERCIAL ASPECT


BARCHART OF PVD WORK
MONTHLY SCHEDULE
NO WORK ITEMS
1 2 3 4 5 . . . N

1 PVD MATERIAL DELIVERY

2 MOBILIZATION

3 ERECTION OF PVD EQUIPMENT

4 TRIAL OF PVD INSTALLATION

5 INSTALLATION OF PVD

6 DEERECTION OF PVD EQUIPMENT

7 DEMOBILIZATION
ESTIMATE OF PRODUCTION CAPACTY
1. WORK DATA
 Depth : 15 – 20 lin.m
 Spacing : 1,0 – 2,0 lin.m
 Pattern : triangular / square
 Work hour : 10 hours / day

2. PRODUCTION CAPACITY
 Prod. cap. : 300 – 400 point / day / unit
 Prod. cap. : 4,500 – 6,000 lin.m / day / unit
SUM OF EQUIPMENT REQUIRED
( EXAMPLE )

1. WORK DATA
 Depth = 15 lin.m
 Spacing = 1.25 lin.m
 Pattern = triangular
 Quantity = 2,000,000 lin.m
 Time Work = 3.0 month

2. EQUIPMENT REQUIRED
 Day work = 25 day / month
 Prod. capacity = 6,000 lin.m / day / unit
= 150,000 lin.m / month / unit
 Time work = 2,000,000 : 150,000 = 13.3 month
 Equipment = 13.3 : 3 = 4.4 unit
= 5.0 unit
PVD WORK DATA REQUIRED
1. MATERIAL SUPPLY DATA
 Material specification
 Manufacture capacity

2. INSTALLATION WORK DATA


 Depth
 Spacing
 Pattern
 Installation method
 Time periode
DECISION OF PVD MATERIAL
1. MATERIAL SPECIFICATION
 equivalent diameter
 discharge capacity
 jacket filter characteristics & permeability
 material strength, flexibility and durability

2. MATERIAL SUPPLY
 brand, trade-mark, project reference
 production capacity of manufacture
 delivery time
ESTIMATE QUANTITY OF PVD WORK

- EFFECTIVE QUANTITY : Qe
- WASTE QUANTITY : Qw

- TOTAL QUANTITY : Qt
: lin.m
: rolls
: CFL
ESTIMATE QUANTITY OF PVD WORK
TOP – WASTE QUANTITY

EFFECTIVE
MIDDLE – WASTE QUANTITY
QUANTITY

BOTTOM – WASTE QUANTITY


EFFECTIVE QUANTITY OF PVD WORK
- Work area : A sq.m
- Spacing : s lin.m
- Depth : L lin.m
- Area per point : Ap
:  / 4 (1.05 s)2 – triangular
:  / 4 (1.13 s)2 – square
- Sum of point :N
: A / Ap point
- Sum of material : Qe
: N . L lin.m
WASTE QUANTITY OF PVD WORK
1. TOP – WASTE QUANTITY ( = Qt )
- Sum of point :N point
- Length of top end :t lin.m
- Top waste quantity :N.t lin.m
2. MIDDLE – WASTE QUANTITY ( = Qm )
- Sum of material : Qe lin.m
- Roll length of PVD :R lin.m
- Length of overlapping :O lin.m
- Middle waste quantity : O . Qe / R lin.m
3. BOTTOM – WASTE QUANTITY ( = Qb )
- Sum of point :N point
- Length of bottom end : b lin.m
- Bottom waste quantity : N . b lin.m
ADDITIONAL
WASTE QUANTITY OF PVD WORK
1. HANDLING IN SITE
2. TRIAL INSTALLATION
3. DIFFICULT INSTALLATION
4. EQUIPMENT BROKEN DOWN
5. ETC
ESTIMATE REAL COST OF PVD WORK
A. MOBILIZATION / DEMOBILIZATION
B. SUPLLY 0F PVD MATERIAL
C. INSTALL OF PVD MATERIAL
1. Material
2. Equipment
3. Labor
4. Others
5. Supplier / Sub-contractor
6. Overhead Cost (OHC)
C. PREBORING / PREDRILLING
ORGANIZATION CHART
OWNER OWNER

CONSULTANT OF CM PLANNER SUPERVISOR

PLANNER SUPERVISOR MAIN CONTRACTOR

SPECIALIST SUB
CONTRACTOR CONTRACTOR
OF OF
PV DRAIN PV DRAIN

CM SYSTEM CONVENSIONAL SYSTEM


FAST TRACK ORGANIZATION CHART
OWNER

CONSULTANT OF CM

PLANNER SUPERVISOR

SPECIALIST SPECIALIST SPECIALIST


CONTRACTOR CONTRACTOR CONTRACTOR
OF OF OF
EARTH WORK PV DRAIN INST & MONITORING
PROGRES REPORT OF PVD WORK
1. QUANTITY REPORT
- Sum of length
- Sum of point
- Sum of area

2. REPORT PERIODE
- Daily
- Weekly
- Monthly
QUANTITY REPORT OF PVD WORK

SUM
SUMOF
OFLENGTH
AREA
POINT
METHOD OF PVD WORK RECORDING
1. MANUAL METHOD
- PVD number
- Installation depth
- Quantity of PVD
- Date and time
- Location of PVD
2. COMPUTERIZED METHOD
- PVD number
- Installation depth
- Quantity of PVD
- Date and time
- Location of PVD
- Installation force
MANUAL RECORDING

DEPTH OF PVD

DEPTH OF PVD
MANUAL RECORDING
MANUAL RECORDING
ABSIS

ORDINAT

19.5 20.0 19.5 20.0

19.5 20.0 19.5

20.0 20.0 20.0 20.0

20.0 20.0 20.0 2


MANUAL RECORDING
SUBTOTAL SUBTOTAL
POINT LENGTH

20.0 19.5 20.0 10 200.0

19.5 20.0 19.5 10 199.5

20.0 20.0 20.0 10 199.0

20.0 20.0 20.0 10 200.0


COMPUTERIZED RECORDING

- PVD number
- Installation depth
- Quantity of PVD
- Date and time
- Location of PVD
- Installation force
COMPUTERIZED RECORDING
PAYMENT UNIT OF PVD WORK
NO WORK ITEM UNIT

1. MOB / DEMOBILIZATION Lump Sum

2. SUPPLY OF PVD Lin. Meter

3. INSTALLATION OF PVD Lin. Meter

4. PRE BORING / PRE DRILLING Lin. Meter


PROPOSAL FOR PVD WORK
• ORGANIZATION CHART
• LIST OF PERSONNEL
• BRAND & TYPE OF PV DRAIN
• INSTALLATION METHOD OF PV DRAIN
• VISIT TO PV DRAIN FACTORY
• VISIT TO PV DRAIN WORK SITE
ORGANIZATION CHART
PROJECT MANAGER

PLANNING & CONTROLLING TECHNICAL ADVISOR

SITE MANAGER

ADM & FINANCE GENERAL AFFAIR

SITE ENGINEER SENIOR SUPERVISOR MECH & ELECTRICAL

SUPERVISOR RIG #3 SUPERVISOR RIG #1 SUPERVISOR RIG #2


LIST OF PERSONNEL
Project Manager : Ir. WAHYU P. KUSWANDA

Site Manager : AHMAD SUHAIMI SHUEB, Dipl.Mech.

Technical Advisor : Prof. Dr. Ir. HERMAN WAHYUDI, DEA


BRAND & TYPE OF PV DRAIN
BRAND : MEBRADRAIN

TYPE : MD7007

COUNTRY OF ORIGIN : MALAYSIA

FACTORY NAME : CAPITAL ENVOY (M)


SDN. BHD.
INSTALLATION METHOD

STATIC METHOD
VISIT TO FACTORY
CAPITAL ENVOY (M) SDN. BHD.
No. 27, Jalan Utama 2/30, Taman Perindustrian Puchong Utama
Sekyen 2, Batu 14, 47100 Puchong, Selangor Darul Ehsan
MALAYSIA

FOR :
OWNER :5
PLANNER :1
CM :1
CONTRACTOR :1
TECH. ADVISOR :1
VISIT TO PVD WORK SITE
LAGUNA INDAH HOUSING PROJECT
Desa Kejawan Keputih Tambak, Kelurahan Keputih
Kecamatan Sukolilo
SURABAYA

FOR :
OWNER :5
PLANNER :1
CM :1
CONTRACTOR :1
TECH. ADVISOR :1
THE END
THANKS YOU
FOR
ATTENTION
TECHNIQUES GEOSYSTEMS SDN. BHD.
TECHNIQUES GEOSYSTEMS SDN. BHD.
MAIN OFFICE :
No. 65 & 67, Jalan SS22/23, Damansara Jaya, 47400 Petaling Jaya
Selangor Darul Ehsan
MALAYSIA
INDONESIA REPRESENTATIVE OFFICE :
Wisma SIER Building, 1st Floor, Jl. Rungkut Industri Raya 10
SURABAYA
www.techgeosys.com

You might also like