Concrete Repair
Concrete Repair
Concrete Repair
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE1 OF 13
REPAIR/1
Contract Package KNPCC-10 :- Construction of Residential, Non-Residential and Institutional buildings at Polytechnic College
Campus, Gurudev Chauraha, GT Road, Kanpur and Multi Storied Officer's Colony of Uttar Pradesh Metro Rail Corporation inside
Kanpur Metro Depot, GT Road, Kanpur including Architectural finishes, Plumbing Drainage, External Development and E&M
Works"
APPROVED BY
REV DATE PREPARED BY CHECKED BY UPMRC
REPRESENTATIVE
Anshul Mr. Rajesh
Bipin Singh Keshav Chaturvedi
Katiyar Singh
20-08-
R-0
2022
Page 1 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE2 OF 13
REPAIR/1
CONTENTS:
1 PURPOSE 3
2 SCOPE 3
3 RESPONSIBILITY 3-4
4 REFERENCE DOCUMENT 4
6 MATERIAL 5
7 METHODOLOGY 5-12
10 ENVIRONMENTAL REQUIREMENT 13
Page 2 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE3 OF 13
REPAIR/1
1) PURPOSE:
This method statement describes methodology for defect identification and repair in the concrete
structures for contract KNPCC-10 project. The objective of this method statement is to clearly
understand the job and procedures of execution along with safety precautions, which are
necessary to avoid any kind of injuries / accidents to personnel or any damage to any
equipment’s or property and maintaining the quality of works.
2) SCOPE:
The purpose of this statement is to identify the defects in the concrete structures and to repair the
same.
3) Responsibility
Page 3 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE4 OF 13
REPAIR/1
Project Environmental Shall be responsible for Identifying significant aspects of the activity and
Manager ensuring the mitigation Measure with the support of Site Team.\
Shall be responsible to monitor environmental general requirement.
4) REFRENCEDOCUMENTS:
Contract Specifications
Project SHE Plan
Material Data Sheet
4.1 Equipment’s:
Page 4 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE5 OF 13
REPAIR/1
6) MATERIALS:
Sl.
Name of Work Brand / Source
No.
BASF,FOSROC, SIKA, and any
1 High Strength low viscous grouts approved brand
BASF,FOSROC, SIKA, and any
2 Bonding Agent approved brand
BASF,FOSROC, SIKA, and any
3 Filler Materials approved brand
BASF,FOSROC, SIKA, and any
4 Epoxy Resins
approved brand
BASF,FOSROC, SIKA, and any
5 Non-Shrinkage Grouts
approved brand
Note-
Vishnu Saran & Co. /GC Approved material only shall be used for repairing work.
Material Storage Shall be as Per Manufacturer Guidance.
MTC to be Submitted Prior to using the Chemicals.
7) METHODOLOGY:
The following are the possible defects that could be encountered in the concrete structures.
Bulged concrete
Grout loss
Honeycomb
Exposed Reinforcement bars
Air bubbles on concrete surface
Cracks on concrete
Broken Edges & Surface damages
7.1 Bulged Concrete: Bulging in concrete takes place due to displacement of formwork.
Identification: Site engineer will inspect the exposed concrete after striking off of formwork or
exposure of the surface by excavation. Site engineer will mark such defect on the plan and at
site.
Page 5 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE6 OF 13
REPAIR/1
Surface preparation: The bulged area on concrete surface shall be hacked with chisel to
required line, level. All dirt, dust shall be cleaned with brush and water.
Repairing: Hacked area will be patched up with cement: sand mortar of proportion 1:4. On the
completion of patch up work, the exposed area shall be thoroughly cured. After completion of
repairing work, Line and Plumb/Level to be checked as per Concrete Outline drawing.
7.2 Grout Loss: Exposed aggregate surface created by exits of cement slurry/grout mortar from
the gaps off formwork due to excessive vibration, unsealed joint off formwork during pouring of
concrete. Grout loss is such defect in which segregation of aggregates from mortar takes place but
sufficient bonded to still exist.
Identification: Site Engineer will inspect the exposed concrete surface immediately after striking
off of work or exposure of the surface by excavation, if surface is intact by gently tampering by
steel object and it found aggregates can’t be loosed off the surface easily and its spreads within
the cover of reinforcement bar. Site engineer will mark such defects on the plan and at site.
Surface preparation: The concrete surface is cleaned and free from dust/oil/grease etc.by using
broom or wire mesh by scrubbing vigorously.
After removal of loose particles surface is washed with water.
Repairing: Patch up is done at cleaned surface with non-shrink Grout conbextra GP2 (Fosroc)
/SikaGrout-214 or equivalent. The material mixing shall be as per manufacturer recommendation.
On the completion of patch up work exposed area shall be thoroughly cured.
7.3 Honeycomb: It is due segregation of aggregates and mortar into the concrete. Honeycomb
creates in structures due to mainly improper compaction in terms of excessive/insufficient
vibration at the time of placing of concrete or several grout loss. Honeycomb creates in to two
types.
a) Minor Honeycomb: Minor honeycomb is those which create small void within the cover of
reinforcement.
b) Major Honeycomb: Major honeycomb is those defects which extend beyond the
reinforcement bar and create big void on the surface.
Identification: Site/Qc Engineer will inspect the exposed concrete surface immediately after
striking off of work or exposure of the surface by excavation, if surface found voids, segregation
of aggregate in concrete, easily removal of aggregate by gently tampering the surface by metal
Page 6 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE7 OF 13
REPAIR/1
object. Site/QC engineer will mark such defects on the plan and at site.
Surface Preparation:
a) Minor Honeycomb: All loose particles from exposed surface shall be removed by gently
tapping on it. After removal of all loose aggregate, dust, dirt etc. by wire/Soft brush then surface
will be cleaned with Water.
b) Major Honey comb: The loose aggregate that are exposed shall be removed by gently
tapping on it. After removal of all loose aggregate, dust, dirt etc. by wire/Soft brush then surface
will be cleaned with Water.
Repairing:
a) Minor Honeycomb: Patch up is done by using conbextra GP2 (Fosroc) / SikaGrout-214 or
equivalent on the cleaned surface. The material mixing shall be as per manufacturer
recommendation. On completion of the patch up work, exposed area is thoroughly cured.
b) Major honeycombing: All loose material shall be removed & cleaned thoroughly. Then a
coat of Epoxy Resin Bonding Agent such as “Sikadur 32 LP” of SIKA or “Nitobond EP” of
FOSROC shall be applied on the old concrete. Then the area shall be rebuilt by using same
concrete mix. On completion of the repairing operation, exposed areas is thoroughly cured.
In case, depth of treated area is more than 30 mm, nozzle shall be left in fresh concrete for
injection of grout, in future. Cement grout shall be used for this purpose.
7.4 Exposed Reinforcement Bars: Reinforcement bars exposed is mainly due to improper /
insufficient cover block placement at the time of fixing of reinforcement bars, loose formwork
erection (Mortar flows through the gap off formwork).
Identification: Site/QC Engineer will inspect immediately after removal of formwork or exposure
of surface by excavation if any exposed reinforcement bars found in to the structures they will
mark such defect on plan and at site.
Surface Preparation: Concrete is chipped off up-to 25mm behind the reinforcement for the area
where there is exposure of reinforcement bars takes place. Remove all loose particle, dust etc.
with clean water.
Page 7 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE8 OF 13
REPAIR/1
Repairing: The exposed rebar is treated by coating with cement slurry. The patch up work is
carried out using non shrink grout conbextra GP2 (Fosroc) / SikaGrout-214 or equivalent. The
material mixing shall be as per manufacturer recommendation. The finishing of surface is beyond
the reinforcement forming a smooth curvature. On the completion of patch work, the repaired
area is thoroughly cured.
7.5 Air bubbles on concrete surface: The inner face of elements, especially at the bottom slab
(covered by Inner Form) concentration of air bubbles is likely to be more. These spots shall be
filled up by a homogeneous mix of Cement, sand (passing through 1.18 mm sieve), a bonding
agent namely “Sika Latex” of SIKA or equivalent shall be used. Proportion of Cement &Sand
shall be 1:2 to 1:3. Sika Latex & water will be added at 1:6 ratios by volume. This shall be added
to the mix to form a paste. This paste shall be applied on air bubbles by trowel.
7.6 Cracks: Any crack noticed shall be investigated and will be repaired after it is confirmed that
it is not a structural crack. In case of structural cracks, separate methodology will be adopted for
repair / rehabilitation after approval from Vishnu saran & co.
Surface cracks: Despite taking utmost care during curing, the concrete surface may develop
certain Cracks. This cracks being very fine in nature, cannot be filled up by any kind of grout
material. To prevent these types of cracks delayed finishing shall be done. To prevent ingression
of water, moisture this can be covered by a thin layer of Cement slurry with bonding agent
(Sika Latex” of SIKA or equivalent shall be used).
Cracks less than 0.2 mm width: Cracks shall be marked. A groove of 10 mm shall be made
along with the crack and same shall be coated with bonding agent (Sika Latex” of SIKA or
equivalent shall be used). After application of bonding agent, groove shall be filled by using non
shrink grout conbextra GP2 (Fosroc) / SikaGrout-214 or equivalent.
Cracks More than 0.2 mm width: Such Cracks shall be repaired using Epoxy grouting ie.
Sikadur 52, Sikadur 53 or equivalent by fixing nozzle at regular intervals depends up on site
Page 8 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE9 OF 13
REPAIR/1
condition.
Grouting Procedure:-
a. Surface Preparation :- Crack location shall be identified and marking shall be done. Remove
all grease, oil, dust, residual curing compound, Mould release agent or other contaminant
that could impair adhesion of the injection ports. Clean the area of all loose particles and
dust by means of oil free compressed air or wire brush.
b. Drilling of Holes:-Nozzle holes shall be drilled at 45° angle to the concrete surface, at
appropriate spacing (as per condition) along the length of the crack . Holes will be drilled
next to the crack with a diameter of about 10 to 14mm (depending on injection port to be
used) and depth ranging from 40mm~50mm, where injection port will be inserted .Holes
will be provided on both the sides of crack in a staggered pattern and distance of one hole
to the crack shall be about 15 mm.
c. Fixing of Nozzles:- NRV (Non returning Valve) Nozzle of MS, 100mm length & 10-12 mm
diameter shall be fixed in Hole as given in Fig-1 and tightened and Epoxy based material
( Sikadur-31 or Equivalent) shall be used for packing of nozzles. Allow the Mix to cure before
injecting. Grouting shall be done after 24 hours of Nozzle Fixing. Nozzle projection length
shall be 30-40 mm from Concrete Surface.
Page 9 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE10 OF 13
REPAIR/1
Fig-1
Fixing of
Nozzle
Crack
300-900 MM
Nozzle
20-30 MM
Page 10 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE11 OF 13
REPAIR/1
Grouting shall be carried out typically around 5 bar pressure, depending of the viscosity
of the epoxy resin.
After Grouting excess chemical shall be wiped off and surface shall be clean.
After Grouting, Grouting Pump shall be cleaned with the use of thinner or Equivalent.
The similar process will be carried out for all the ports installed.
After curing time (as mentioned in technical data sheet) of grouting, Nozzle shall be cut
using grinding Machine and surface of structure shall be cleaned & smoothly finished.
Surface shall be matched as per approved concrete outline drawing to avoid offset
&bulging.
7.7 Broken Edge & Surface damage: During de-molding or handling the elements
sometimes the edges & surface may get damaged & thus its aesthetics gets affected.
For rebuilding the broken edge or damaged surface ,the affected area is to be cleaned
throughly and then 3
–component Epoxy Resin Mortar, namely “Sikadur 41” of SIKA or equivalent product of
different make shall be applied by trowel. Before application of this the surface may be
primed by a coat of “Sikadur 31”. However, this product can be used only after concrete
attains an age of 6 weeks or more. In case of early requirement, a cohesive mix of
Cement, Sand, a bonding agent namely “Sika Latex” of SIKA or equivalent product of
other manufacturer & water shall be used. Proportion of Cement & Sand will be 1:4 and
that of Cement &Sika Latex will be 5:1. In case of depth of treatment / repairing is more
than 10 mm, stone aggregates of smaller size (passing through 6.3 mm sieve) shall be
used along with sand. Before application of the mix, the area should be thoroughly
cleaned. Mix application shall be done by trowel.
Note: Prior permission shall be obtained from respective Vishnu Saran & Co /GC in-
charge/ executive before rectification works and suitability of repair materials/ chemicals
& their application methodology may be discussed case to case.
Curing of any type of repair shall be done by using curing compound. If the Crack width
is more than 0.2 mm prior to apply the works, Designer Concurrence shall be required.
All defect shall be listed and mapped include crack and all defect should be checked and
repaired by Contractor at present Vishnu Saran & Co /GC, especially crack developing
should be monitored as a record.
Page 11 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE12 OF 13
REPAIR/1
Cube shall be casted as and when required. Cube size will be as following-
With agg mix 100*100 mm size cube mould shall be use
Page 12 of 13
METHOD STATEMENT FOR
CONCRETE REPAIR WORK
DOCUMENT No :
KNPCC-10/CONCRETE REV. No: R0 DATE: 20-08-2022 PAGE13 OF 13
REPAIR/1
MSDS of all the chemicals related to plastering should be attached with the document.
No welding activity shall be allowed in wet condition.
Good housekeeping to be maintained in & around the work location.
All the electrical safety measures should be checked and maintained on regular basis.
Sufficient illumination should be ensured while working in dark hours.
All the environment norms and precautions shall be taken as per condition of contract on Safety,
Health and Environment Vol. 7 Part IV for each activity before commencing.
Vehicles / tracks shall be kept moist to prevent flying of dust particles with the vehicle movement.
Environmental Monitoring for fugitive dust emission and its control measures.
Waste oils/waste lubricants /spent oil /waste grease /paints and thinners will be collected in
separated labelled containers and sent to the collection agency.
Solid waste generated by various process during the construction phase will be segregated such that
no hazardous toxic waste will mix with solid waste.
The wastewater from construction area / P&M workshop /runoff from approach road storm water
will be collected in a collection pit and its will be disposed of local bodies.
All vehicle and machineries will be maintained to ensure that that exhaust is in compliances with
vehicular pollution standards.
Use PPE (Noise plug, N-95 mask etc).
Water sprinkling shall be practice minimizing particulate emission.
Carry out environmental training based on ongoing work priorities to train employees and
workforce.
Identify the significant environment aspect and its control measure shall be monitored.
C&D waste management and its record for audit purpose.
3 Drawings N/A
4 ITP Annexure - 2
Page 13 of 13