Ms-001 Installation of Site Offices

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

DUBAI CREEK HARBOUR DEVELOPMENT

ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

CLIENT : EMAAR
CONSULTANT : PARSONS
CONTRACTOR : WADE ADAMS CONTRACTING CO. (LLC)-
NATIONAL WHEEL J & P (LLC).

METHOD STATEMENT
FOR
INSTALLATION OF SITE OFFICES

WAC/724-MS-0001 Rev 02

Prepared By Reviewed By Approved By


Rev Date Comments Project Project
Site Agent
Engineer Manager

02 15/07/2017 Issued for Approval


Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

CONTENTS

1. SCOPE
2. REFERENCE
3. RESPONSIBILITY
4. RESOURCES
5. HEALTH & SAFETY
6. WORK PROCEDURE
7. QUALITY CHECK
8. ATTACHMENTS

1.0) SCOPE

Page 2 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

The scope of this method statement is to outline the procedures for installation of site
offices for Dubai Creek Harbour Island District Infrastructure Project.

2.0) REFERENCE

 General and Particular Specifications.


 Project Quality Plan.
 Health, safety and Environmental Plan.
 DM Construction Code of Safety Practices.

3.0) RESPONSIBILITY

3.1) Project Manager

 Organize the site so that work is carried out to the required specifications with a
minimum risk to men, equipment and materials.
 Adhere to the project specific quality management program and the approved
method statements for the various construction activities involved
 Directly supervise the Project personnel. Ensure correct procedures are followed,
and necessary permits are obtained in advance.
 Coordinate safety & quality matters between the construction personnel and
HSE/quality personal.

3.2) Project /Site Engineer

 Responsible for the work’s entire quality assurance, quality control & inspection
programs.
 Works directly at site with the foreman to ensure that all the required information has
been provide to proceed with the works, and that the works comply with project
specification and method statements.
 He liaises with the consultant with respect to inspections and approvals. He reports
to the Project Manager/ Site Agent.

3.3) Construction Foreman


 Directly supervises the work activity on the site and has full control over the use of the
labor, plant and equipment.
 Adheres to the project specific method statements, inspection program & HSE
instruction to get the activities performed with full coordination with Project/ Site
Engineer when the work is complete and ready for inspection.

3.3) Project Safety Lead/Safety Officer

Page 3 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

 The safety officer shall be responsible for ensuring the implementation of all safety
aspects during the construction and shall report to Project manager & HSE Manager.

4.0) RESOURCES

4.1) Manpower

 Project/Site engineer/Safety Officer.


 Foreman/Carpenter/Mason/Pipe fitter/Electrician
 Surveyor/Chainman/ Labors

4.2) Equipment/ Tools/Materials

 Prefabs/Survey Equipment/Cement Blocks/Pipes


 Hand Tools/ Steel rods/Electrical & Sanitary items
 Crane/Trailers/Bob cat/Bus

5.0) HEALTH & SAFETY

5.1) Induction and Training

 Prior to start activity, personnel will undergo project HSE induction. All visitors and
suppliers shall be inducted and accompanied by the respective department
representative if they want to visit to site. An induction sticker will be issued to all
attendees identifying that they have satisfactorily completed their training requirements
and shall be used on site.
 Personnel will undergo site HSE induction prior to deploy to site and their participation
in relevant HSE trainings in accordance with the Project HSE training matrix.
 Both contractor and subcontractor will follow contractor HSE plan and manual
procedures as applicable during execution. All above mentioned plan and procedures
will be referred during the preparation of method statement and risk assessment. HSE
plan shall be available on site.
 The activity risk assessment attached with the method statement will be communicated
with the workforce on site prior to start each job and need to be recorded and
documented.

5.2) Safe Work method Statements (SWMS)

 Safe work method statements will be developed and reviewed in a consultative


process with the work team prior to the commencement of the work activity. Both
method statement and risk assessment will be consulted with the team and recorded
prior to work commencement. Any subsequent changes to the safe work method

Page 4 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

statements will also be approved and consulted with the workforce. Only approved
MS shall be used at site.

 The arrangements to manage and facilitate safe evacuation of work force during an
emergency shall be arranged at site as per the Project Emergency Response Plan.

5.3) Tool Box Talks

 Too box talks will be held on daily basis by the HSE Coordinator. This daily safety
briefing is to address project HSE issues, compliance with HSE plan/PTW ,
accidents/near misses and lessons learned, changes to conditions on site whether
due to construction activities or by weather etc.

5.4) Training in proper use of PPE

 PPE relevant to the project in accordance with site work rules. The basic PPE
requirement includes helmets, safety shoes, safety glasses and safety jacket.
Subcontractor will keep relevant stock of PPE on site and will be replaced as
required. Personnel will be trained on the use of PPE’s relevant to their work.

5.5) Reporting of accidents/Incidents/Near-misses

 In case of any accident/incident occur at work will be reported to Consultant as per


Client incident reporting protocol. An initial written notification with in four (4) hours
following the incident using a prescribed accident/incident report format and a written
detailed incident investigation report with in twenty four (24) hours.

5.6) Plant and Equipment

 All plant and equipment shall be inspected, color coded prior to introduce to site and
properly maintained and in good condition prior to allow working on site and shall be
equipped with fire extinguisher. Any plant / Equipment shall not be deployed to site
without inspection.

5.7) Operators

 All operators will have valid UAE license and be properly trained on the type of
equipment they are operating. Operators should conduct daily check and recorded on
daily inspection check list.

5.8) Banksman

Page 5 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

 Qualified and trained banksman should be with all moving plant and equipment and
with heavy vehicles while reversing.

5.9) Safe Driving

 Drivers will be instructed to follow safe driving measures detailed in the attached Risk
Assessment. Drivers will be inducted on the same and recorded.

5.10) Daily HSE Monitoring

 Daily HSE inspection shall be carried out at site as per the monitoring chart and
recorded. HSE observation card system to be followed by the site supervisor.

5.11) Welfare Facilities

 Welfare facilities as required shall be arranged on site and maintained properly. Rest
area, Toilets, sufficient drinking water shall be provided for site crew. The crew shall
be made aware of the signs and symptoms of heat related illnesses and early warning
indications via heat stress training and awareness. The front line Supervisor should
be notified of any early indications and corrective action taken. Heat rate is a good
indicator of the degree of heat stress that a person is experiencing.

 Male Nurse and First aider shall be available at site during the working hours with
proper first aid facilities.

5.12) Emergency response

 Emergency response will be in accordance with the project emergency response plan
and HSE plan. Emergency contact number will be posted at site. Emergency contact
numbers are available with the HSE plan.

5.13) Abbreviations

 HSE: - Health, safety & Environment.

 PPE: - Personal Protective Equipment.

 PTW:- Permit to Work

 TBT:- Tool Box Talk

Page 6 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

 TPC: - Third Party Certificate.

 PQP: - Project Quality Plan.

 ITP:- Inspection Test Plan

6.0) WORK PROCEDURE

 Obtain all necessary NOC/ Appd. Shop drawings/ Approvals from DM/ Consultant
before the commencement of work.

 Tool box talk shall be conducted to all work force related with this task.

 The prefabs shall be arranged as per the layout approved by the Employer/Engineer
together with necessary prefabs for the contractor/Sub contractor.

 Area for fixing the cabins shall be levelled and compacted. Concrete blocks shall be
placed at the locations of cabin legs.

 Cabins shall be transported using trailers / crane form its storage location to the site
after obtaining necessary police/authority permissions during night (12.00am to 3.00
am).

 Cabins shall be unloaded and fixed on site upon arrival (3.00am to 6.00am).

 Necessary lighting arrangement shall be made available.

 Responsible persons like Sr. Foreman; safety officer etc. shall be available full time
during these operations.

 The cabins shall be levelled/adjusted during next morning.

 Sanitary, electricity, telephone system shall be installed during subsequent days.

 Sanitary connection shall be done to small chambers connected by pipes which will
lead to a main chamber and then to septic tank or nearby sewer manhole (subjected
to approval from concerned authority).

 Furniture and fixtures shall be provided as specified in the contract.

 A generator with suitable capacity shall be erected until power connection made
available.

Page 7 of 8
Method Statement for Installation of Site Offices Ref. WAC-724/MS-0001 Rev.02

CLIENT CONSULTANT CONTRACTOR


DUBAI CREEK HARBOUR DEVELOPMENT
ISLAND DISTRICT
SITE WIDE INFRASTRUCTURE

 Potable water shall be supplied with water tanker until water connection made
available.

 Telephone, internet, fax etc. shall be installed as specified in the contract.

 The area in front of cabins shall be graded and road base/ gravel spread.

 Steps shall be made for all the doors.

 Car parks shall be installed as shown in the approved drawings.

7.0) QUALITY CHECK

 All quality checks to be performed as per project quality plan.

8.0) ATTACHMENT

 Risk Assessment

 Lifting Plan

Page 8 of 8