1.method Statement - INSTALLATION OF GRP WATER TANKS
1.method Statement - INSTALLATION OF GRP WATER TANKS
1.method Statement - INSTALLATION OF GRP WATER TANKS
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
Table of contents
1. Scope/Objectives
2. Reference
4. OHS Requirement
6. Definitions
7. Responsibilities/Supervision
8. Sequence/Method to be employed
9. Notification of Inspection
11. Records
13. Distribution
15. Attachments
CONSULTANT
CONTRACTOR MEP CONTRACTOR
1. Scope/Objectives
Installation of GRP water storage tanks in accordance with the requirements specified in
the relevant specifications, procedures and drawings, considering safety and quality of the
work activities at palace beach residence by M/s Thermoset technologies & M/s Bilt Middle
East.
2. Reference
2.1. Contract Drawings
2.2. Specifications
2.3. Project Quality Plan Ref:
2.4. HSE Plan Ref:
2.5. Environmental Plan Ref: Shop drawings
2.6. Material Submittals
4. OHS Requirements
4.1. HSE legal and contractual references
Dubai Municipality Code of Construction Safety Practice.
UAE Fire and Life Safety Code of Practice.
ABM HSE Management System.
Emaar- Project Health, Safety, Environment & Security Guidelines.
4.2. HSE Procedures/ Requirements specific to the activity.
Lift Plan based on the Lifting Operations Management Plan.
Job specific work permit system shall be followed as per scope of work prior to
the commencement of the activity.
Daily basic task briefing shall be carried out as per work permit system,
CONSULTANT
CONTRACTOR MEP CONTRACTOR
CONSULTANT
CONTRACTOR MEP CONTRACTOR
7. Responsibilities/Supervision
CONSULTANT
CONTRACTOR MEP CONTRACTOR
Shall direct responsible to carry out the works as per approved Method Statement
and Risk Assessment.
Responsible to prepare method statement and risk assessment for all critical
operation in the project and the same is approved, communicated and followed.
Directly responsible for ensuring the completion of works as per approved MSRA.
Ensure welfare arrangements are provided and maintained as per the
requirements.
7.2. Project Engineer:
Shall be responsible to organize required machinery, material, manpower to
engineers& foreman for effectively executing the work in a safe manner.
To clarify any discrepancies in the work.
7.3. Foreman:
To execute the work as per Project Engineers instructions with the right
methodology & in a safe manner.
Make sure that all the works are completed prior to offering for inspections.
To execute the works as per approved method statements.
To ensure all equipments inspection by third party and certificate is displayed.
To attend all the comments made by Consultant at the time of inspection.
Ensure the workers PPE, sufficient lighting.
7.4. QA / QC Engineer:
To check the work is carried out as per the approved method statement.
To ensure all approved materials are being used.
Verify whether suitability of ambient temperature for casting concrete.
7.5. HSE Staff Responsibilities:
To advice Project Manager, Construction Manager, Engineers & Supervisor/ Foreman
regarding the Safety precautions to be taken and monitor for the safety implementations to
execute the work.
Monitor the lifting plan and work permits procedure is complied with and the safe
conditions are in place.
CONSULTANT
CONTRACTOR MEP CONTRACTOR
All employees involved in the activity should be Safety Inducted by safety department
before allowing working at site.
Monitor HSE safe working procedures and cross check control measures mentioned in
Risk assessment is implemented for the activity.
Monitor the use of task based PPE for the activity.
CONSULTANT
CONTRACTOR MEP CONTRACTOR
8. Sequence/Method to be Employed
8.1. Material
8.1.1. Insulated panels
8.1.2. Upvc fittings
8.1.3. Stainless steel ties rod, nut bolt & washer.
8.1.4. Ladder
8.1.5. Tube level gauge
8.1.6. Hot dipped galvanized skid base
8.1.7. Internal roof support
8.2. Tools for GRP water storage tanks installation and testing.
CONSULTANT
CONTRACTOR MEP CONTRACTOR
The following stages are applicable for the Installation of GRP water storage tank.
8.3.2.1. Approved Builders work drawing and approved shop drawing to be checked for setting
out dimensions for the concrete base to be made for installation of GRP water tanks. Any
deviations to be brought to consultant’s notice for approval.
8.3.2.2. GRP panels shall be assembled by the specialist supplier / contractor with gaskets and
stainless steel bolts as per sizes indicated on the approved shop drawings. Torque
CONSULTANT
CONTRACTOR MEP CONTRACTOR
CONSULTANT
CONTRACTOR MEP CONTRACTOR
8.4.1. The water tanks as assembled above are filled with water to its full capacity upto the over
flow outlet. All outlets from the tanks are closed by closing the gate valves.
8.4.2. Allow water to stand for at least 24 hours and inspect the tank thoroughly for leaks.
8.4.3. Rectify leaks if any, and check again after 24 hours.
8.4.4. Repeat this exercise until no leak is observed in any part of the tank and the water tank is
scheduled for inspection by the Consultant.
8.4.5. Once the inspection is approved, the water tank is covered with tarpaulin till the handing
over of the project/commissioning of the system so that it is not damaged.
9. Notification of Inspection
9.1. Engineer to inspect delivered material / installations at site as per attached check
lists, prior to notifying consultant for inspection.
9.2. Bilt shall notify the Consultant with relevant transmittal form for all material
inspection (Material Inspection Check list attached)
11. Records:
11.1. Prepare work inspection request (WIR) along with check list and have them signed
by Consultant.
12. SUPPORTING DOCUMENTATION
This MS to be read in conjunction with the below referenced documents
Contract Drawings and specifications
Project Quality Plan
Project HSE Plan
13. DISTRIBUTION
DOCUMENT NUMBER ISSUE PAGE NUMBER DATE
CONSULTANT
CONTRACTOR MEP CONTRACTOR
Copies of this MS will be circulated to the following for Information & action
Project Manager
Construction Manager
Site Engineer
QA/QC Engineer
HSE Engineer
Subcontractor Engineer
14. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved
with Site in Charge.
15. ATTACHMENTS
Risk Assessment
Checklist
ITP