Method Statement For Installation of VAV Box
Method Statement For Installation of VAV Box
Method Statement For Installation of VAV Box
Contents:
1. Introduction
2. Packing list
3. Tools
4. Procedures
1. Introduction
The following procedure has been prepared for the installation of the Variable Air Volume Boxes at
DIAL
2. Packing list
5. Loose thermostat
3. Tools.
Calibrated multi-meters
4. Installation Checklist.
4.5 Location – avoid areas with excessive vibration and electrical noise
4.7 Check the provision of the DDC controller in each of the VAV boxes.
Procedures
5.1 Ensure sufficient space for access to the controller while installation
5.2 Ensure there is 4 Duct diameters straight inlet Duct, same size as inlet between the unit inlet and
transition take offs or fittings
5.3 The inlet of VAV Box is fixed with flexible or rigid circular duct of the same diameter of the VAV box and
is connected to the main supply duct
5.4 Circular Clip is used to fasten the flexible duct to the VAV box.
5.5 The outlet of the VAV box is rectangular in shape and is to be connected to the Duct by means of nut
bolt or slip joint to the distribution duct.
5.6 VAV Box has an arrow marking for direction of air flow as well as the vertical position, it is strictly
recommended that the direction of the arrow is followed for correct installation .
5.7 The thermostat is to be located in the zone served by the VAV box.
5.8 Cat-5/Cat-6 cable with RJ45 terminals at both ends is used to connect the thermostat to the box.
5.9 The temperature required is set on the thermostat. This temperature along with the sensed zone
temperature is send to the DDC controller of the VAV box, to regulate the desired amount of air to be
delivered into the room.
6.1 The VAV boxes may be stored in a dry place away from direct sunlight.
6.2 Do not handle the VAV box by the cross flow velocity sensor.