Itp Installation of Fcu
Itp Installation of Fcu
Itp Installation of Fcu
Inspection of Materials upon receipt as per approved Material Project Engineer After Receiving Material
at site. Submittal & project QC Inspection
1.2 specification ( SECTION Engineer Request H H I
23 82 19)
Proper storage on the site. as per approved Material Project Engineer After Receiving Material
Submittal & project QC Inspection
1.3 specification ( SECTION Engineer Request S S S
23 82 19)
2 Drawings
Aprroved Drawings to be used as per approved Shop Project During Approved
Drawing & Project Engineer QC Installatio Shop Drawing
2.1 Specification ( SECTION 23 Engineer n H W R
82 19)
3 Installation
approved
Approved Method shop drawings
Statement , Aprroved Installation
Installation of FCU is coordinated Project During
3.1 Shop Drawing & Checklist H H S
with other services. Engineer QC Installation
Approved equipment Engineer
schedule
3
approved shop
drawings
Approved Method Statement Project Engineer During Installation
3.2 Installation of support and hanger. H H S
& Aprroved Shop Drawing QC Engineer Installation Checklist
3
Inspection & Test plan - Installation of fan coil units
4 Inspection
Approved shop drawings, Work
approved method statement, Inspection
Equipment schedule and Air Request,
balancing as per Project Engineer Installation
4.1 Final installation inspection of FCU specification ( SECTION 23 After Installation Checklist H H I
QC Engineer
82 19)
LEGEND: H- Hold Point (WIR to be issued but work cannot proceed without approval of concerned authority
) W- Witness Point (WIR to be issued but work can proceed without approval of concerned authority
) S- Survelliance (No WIR required, activity subject to monitering)
R - Review(Record/Document Review)
3
I - Inspection