1.SRO-QPITP - Mechanical Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

THE EMPLOYER: THE ENGINEER: THE CONTRACTOR: Project No.

: S08139

Railway Tunnel Leading to King Abdul


ITP Ref. No.: HHR-T-ITP-ME-0005-R00
Aziz International Airport Station
Date Issued:

INSPECTION AND TEST PLAN FOR


INSTALLATION OF FUEL OIL PIPING SYSTEM
Survey, Test Action
Item Activity Acceptance Specification and/or Verification Verifying
or Inspection Frequency
No. Description Criteria Drawing No. Personnel A E C Document
Method
1 DOCUMENTATION

Documents are
Verify the availability of approved IFC Drawing,Method Document and latest revision and Proj. Specifications Sec Start of Shop Drawing and technical document
1.1 Engineer/ AGC QC H R R
Statement (Wherever Applicable). Drawing Submittal approved by 10.5/Quality Control Manual submittal submittal
Authority

2 Materials

Conform with
Proj. Specifications / Proj. Inspection of Material delivered to
2.1 Check materials delivery approved material Every Delivery Engineer/ AGC QC H W R
Quality Plan /Material Approval Site(MD)
approval request

3 Installation Work

As indicated in the Proj. Specification Sec.10.02 Request for Inspection (RFI),


3.1 Verify pipe type and size Visual Inspection Every Pipe Engineer/ AGC QC H W R
approved drawing &10.03/ Approved Drawing Form QC-ME-013

Dimension as
Proj. Specification Sec.10.02 Request for Inspection (RFI),
3.2 Verify installation of main fuel tank and daily fuel tank. Visual Inspection indicated in the Every Tank Engineer/ AGC QC H W R
&10.03/ Approved Drawing Form QC-ME-015
approved drawing

Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) A - Contractor (Almabani General Contractors)

W - Witness (attendance expected, signature on check sheet) R - Record review E - Engineer (Dar Al-handasah)

C - Employer (Saudi Railways Organization)

Form: QC-ITP-05
Issuance: 01
AGC/SRO_HHR-T/QCF 1 of 2 Revision: 00
THE EMPLOYER: THE ENGINEER: THE CONTRACTOR: Project No.: S08139

Railway Tunnel Leading to King Abdul


ITP Ref. No.: HHR-T-ITP-ME-0005-R00
Aziz International Airport Station
Date Issued:

INSPECTION AND TEST PLAN FOR


INSTALLATION OF FUEL OIL PIPING SYSTEM
Survey, Test Action
Item Activity Acceptance Specification and/or Verification Verifying
or Inspection Frequency
No. Description Criteria Drawing No. Personnel A E C Document
Method

As per joint details in Proj. Specification Sec.10.02


3.3 Fit-up inspection Visual Inspection Before Welding Engineer/ AGC QC H S R
approved drawing &10.03/ Approved Drawing Form QC-ME-015

Visual Inspection As indicated in the Proj. Specification Sec.10.02 Request for Inspection (RFI),
3.4 Check pipe penetration through walls or floor
and Survey approved drawing &10.03/ Approved Drawing
Every Location Engineer/ AGC QC H W R
Form QC-ME-015

Dimension as
Check valves, gaskets, bolts tightening, free closing and Proj. Specification Sec.10.02 Request for Inspection (RFI),
3.5
opening and direction of flow
Visual Inspection indicated in the
&10.03/ Approved Drawing
Every Location Engineer/ AGC QC H S R
Form QC-ME-015
approved drawing

Dimension as
Visual Inspection Proj. Specification Sec.10.02 Request for Inspection (RFI),
3.6 Check hangers and supports spacing and installation
and Survey
indicated in the
&10.03/ Approved Drawing
Every Supports Engineer/ AGC QC H S R
Form QC-ME-015
approved drawing

No leak at pressure Proj. Specification Sec.10.02 Each Segment Request for Inspection (RFI),
3.7 Piping Pressure Test Visual Inspection Engineer/ AGC QC H H S
test &10.03/ Approved Drawing of piping Form QC-ME-005

As per manufacturer Proj. Specification Sec. 10.03/ Request for Inspection (RFI),
3.8 Insulation for underground pipes Visual Inspection Each Pipe Engineer/ AGC QC H W R
recommendations Approved Drawing Form QC-ME-015

Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) A - Contractor (Almabani General Contractors)

W - Witness (attendance expected, signature on check sheet) R - Record review E - Engineer (Dar Al-handasah)

C - Employer (Saudi Railways Organization)

Form: QC-ITP-05
Issuance: 01
AGC/SRO_HHR-T/QCF 2 of 2 Revision: 00