METHOD STATEMENT FOR PVC - Upvc-Cpvc
METHOD STATEMENT FOR PVC - Upvc-Cpvc
METHOD STATEMENT FOR PVC - Upvc-Cpvc
OWNER: MARAFIQ
P.O. # 7200040907
OWNER: MARAFIQ
TABLE OF CONTENTS
SECTION DESCRIPTION PAGE
1.0 PROJECT DESCRIPTION 3
11.0 TRAINING 16
OWNER: MARAFIQ
The Expansion project contract is based on a Design, Build and Operate (DBO) concept broken down into an
Engineering, Procurement and Construction (EPC) part and an Operation and Maintenance (O&M) part. The EPC project
duration will be for 36 months from Commencement Date, while the O&M period of the contract will be for 5 years from
Initial Acceptance of the Works from MARAFIQ.
For further details, refer Document No. MSCF-1-PC-057 Attachment D EPC Scope of Work of Contract
The SSEM will provide design and construction drawings, supervision of work, labor, construction plant and equipment,
materials, tools, Quality control and coordination to execute the works in accordance with the relevant design drawings,
Standards and specifications.
The main purpose of this documents is to elaborate the common practice for the installation and joining of CPVC &
PVC/uPVC PIPES underground and above ground piping. This method of statement is applicable to all CPVC and
PVC/uPVC pipe diameters. The purpose of this method statement is to describe the procedure and methodology to be
adopted as a part of UPVC Underground and above ground drainage pipes & fittings installation for the Construction of
Expansion of IWTP-8 Stage-4 DBO. This document should be read in conjunction with the Project Quality Plan and
Contract Specifications
All work done in the scope of contractor will be executed in accordance, but not limited, with the following documents.
Where specifications are not clear or covered by these documents the client will be informed and applicable documents will
be provided by the client in order to have clarity on requirements that should be achieved.
OWNER: MARAFIQ
SSEM Saudi Services for Electro Mechanic Works Co. (Closed Joint Stock Company)
PMC Project Management Consultant
ISO International Organization for Standardization
OEM Original Equipment Manufacturer
EPC Engineering, Procurement and Construction
O&M Operation & Maintenance
IFC Issue for Construction
PM Project Manager
CM Construction Manager
QMS Quality Management System
QA Quality Assurance
QC Quality Control
Contractor The main Contractor of Project
Sub-contractor Construction Sub-Contractor
ITP Inspection & Test Plan
RFI Request for Inspection
NCR Non-Conformance Report
HSE Health Safety and Environment
MSDS Material Safety Data Sheets
PPE Personal Protective Equipment
PTW Permit to Work
DN / PN Design Pressure / Nominal Pressure
MEP MECHANICAL, ELECTRICAL & PLUMBING
The team members in all key positions, which require approval from the client, has been submitted
to the client for pre-approval or in approval stage. Positions not requiring approval from the client
will have the required qualified and experienced needed for their position in order to complete
their responsibilities successfully.
Should there is need to accelerate the progress and catch-up the project schedule SSEM sub-
contractors may be employed any time but would function as part of SSEM’s team. List of SSEM
sub contractors will be made available once their qualification is approved by the client and
mobilized to site.
OWNER: MARAFIQ
Organization Chart
SSEM PM – Wael
Fathy
CONSTRUCTION MANAGER
AHMED IBRAHEEM
QA/QC MANAGER
MOHAMMED ISMAIL ELDEEB SAFETY MANAGER
NADJME
PTW COORDINATOR
TBA
OWNER: MARAFIQ
All actionable responsibilities mentioned in this section for each position will be responsible for
the tasks briefly state against each position.
OWNER: MARAFIQ
5.6 COORDINATOR
Responsible for taking all necessary steps to prepare, authorize, and issue the Permit to
Work after assessing the work and work site and/or area hazards and the controls to
address these hazards.
OWNER: MARAFIQ
3in bearing width at spacing not greater than 2ft. centers for pipe sizes 160mm and above should be placed
beneath the pipes and at 1.5m centers at the side, if the stacks are rectangular.
• For temporary storage in the field, where racks are not provided, the ground should be level and free from
loose stones. Pipes should not exceed three layer high and should be stacked to prevent.
• Stack heights should be reduced if pipe are nested, etc. .. pipes stored inside pipes of larger diameter.
Reduction in height should be proportional to the weight of the nested pipe compared to the weight of the
pipes normally contained in such stowage.
• Any primer, solvent cement, or adhesive that is beyond the stamped expiration date shall be discarded.
Solvent cement that has gelled or thickened shall be discarded. Leaking or opened containers shall also be
discarded.
Each operator performing fusion joining shall be qualified in the use of the manufacturer's recommended fusion
procedure(s) by the following:
1. Making a sample joint according to the procedure that passes the following inspections and tests:
a) The joint shall be visually examined during and after joining and found to have the same appearance as a photograph
or sample of an acceptable joint that was joined in accordance with the procedure; and
2. Each operator shall be re-qualified under the procedure if during any 12month period:
a) Operator has not made any joints under the procedure; or
b) Operator has 3 points or 3% of the joints made, whichever is greater, that are found unacceptable by testing
according to same procedure.
Installation of Thermoplastic Pipes i.e All PVC/uPVC/ CPVC pipe shall be assembled, and installed in accordance with
ASTM code, manufacturer's recommendations, and this procedure. Joints shall be made in accordance with ASTM 02855
for PVC and ASTM F493 for CPVC. Solvent cement shall conform to the following ASTM Designations:
OWNER: MARAFIQ
ASTM 02564 for joining PVC to PVC, and ASTM F493 for joining CPVC to CPVC or PVC. Primer and solvent cement shall
be handled in accordance with the safety precautions in ASTM F402 for restrained type joints.
Solvent cement shall not be used past the manufacturer's expiry date on the label or one year past the date of
manufacture if there is no expiry date specified.
Note: These temperatures are pipe surface temperatures and are not air temperature limitations.
- Insert pipe into the socket without seal ring in place and mark pipe when it is fully inserted.
- Place seal in groove of socket ensuring that seal is correct way round. Rubber seal rings should be fitted with tapered
section facing the outside of the socket
- Apply jointing lubricant to the chamfer and the end of the spigot of the pipe or fitting only. Push the pipe firmly into
the socket up to the insertion mark previously made. If an expansion gap is requiring the pipe is then pulled back by
desired amount according the size.
OWNER: MARAFIQ
OWNER: MARAFIQ
Trench walls should be supported with sheet piles if the natural ground soil is unstable.
the minimum trench width from the bottom to 300 mm above the top of the pipe shall be as shown in below
Table.
TYPE OF PIPES NOMINAL PIPE SIZE (mm) MIN WIDTH OF TRENCH (mm)
Trench bedding should be fattened, levelled and compacted all along the trench. Under unstable soil conditions, trench
depth and bedding thickness can be increased. After trench excavation, bedding should be prepared to provide durable
and stable support for pipe. Pipe bedding should not be less than 15cm in height and should be prepared with
compacted granular material at minimum 90% Standard Proctor Density or any other suitable bedding material at
minimum %95 Standard Proctor Density. Bedding depth should be increased if there are unstable, lose or soft soil
conditions. If bedding material is sandy, bedding material should be moisturized and should be compacted with
vibrating compactors. Bedding should always be flat and levelled with the trench bottom. A non-woven geotextile with a
unit weight of at least 100 g/m2 must be placed between the crushed stone and the sand bedding layer to prevent
filtration of the sand bedding into the crushed stone matrix. The trench bottom shall be continuous, smooth, free of
rocks, and to the line and grade shown on the installation drawings. Bedding material characteristics are very important
for a proper support for the pipes. Generally bedding and backfilling materials are preferred to have the same
characteristics. if the excavated material is preferred to be used as backfilling material, characteristics of the excavated
soil should be analyzed for suitability. Another critical point to be taken into consideration is the possibility of
experiencing different soil characteristics along the pipeline.
After completion of trench excavation and bedding, installation can start in line with the project. Pipes and fittings
should be stored along the pipeline next to the trench according to the daily installation program for a faster and easier
installation. Stored goods should not block the working path of the construction machines such as crane, excavator,
bulldozer, etc lifting straps should be tied around the pipe from the appropriate lifting points. While lifting fittings,
special lifting and alignment requirements should be taken into consideration. (For instance, the arm angle of the Tee
part). lifting can be performed with a crane or with the excavator arm and pipe should be lowered onto the bedding
slowly. During lifting and lowering inside the trench, field teams instruct directions to the excavator operator to make
sure that pipe will be placed at the right location. Pipe should be lowered closer to the previously installed pipe and
should be carefully aligned.
During installation of multiple pipes in a single trench, distance between any of the 2 pipes is determined with the
formula (r1+ r2) /2 whereas r1: radius of the first pipe and r2: radius of the second pipe. Complying with the formula or
Manufacturer recommendation for the distance of pipes in the same trench.
OWNER: MARAFIQ
- Work execution inspection and test shall be monitored and witnessed as per SSEM ITP and recorded in the
SSEM Inspection checklist and QC forms available in the ITP as applicable.
- Request for Inspection (RFI)QC inspector shall issue a RFI 24 hour and 48 hours for weekend inspection and
remote area location as per Schedule Q in advance of test I inspection to CLIENT PMT to verify the readiness of
the test I Inspection and to inform MARAFIQ/ILF QC inspection in advance.
. Visual inspection.
All installed PVC/uPVC pipe and fittings shall be visually inspected for scratches, damaged ends, cracks,
delamination, crushing, weathering. Each piece of PVC/CPVC/uPVC pipe and fitting shall be examined for cuts,
scratches. gouges, kinks, buckles, and ultra-violet (sun) damage. Damaged lengths of pipe shall be cut out and
discarded. Damaged fittings shall be discarded as well.
6.7 BACKFILLING
When the pipe installation and leak testing is completed and successful, backfilling of the pipe will follow.
However, partial backfilling prior to hydro -testing is permitted provided that the coupling joints or lamination
joints are exposed. During backfilling the following are to be followed:
o Proper selection, placement and compaction of the pipe zone backfill are important for controlling
the vertical deflection and are critical to the pipe performance.
o Attention must be paid so that the backfilling material is not contaminated with debris or other
foreign materials that could damage the pipe or cause loss of side support.
o During backfilling, the granular material should flow completely under the pipe to provide full
support.
o A blunt tool maybe used to push and compact the backfill under the pipe.
o Provide warning tape 300 mm above the top of pipe in burried services. ( Refer RC Section 02085 )
o Proper backfilling should be done in 150 mm to 300mm lifts depending on the backfill material and
compaction material. 300 mm lifts will be adequate for gravel because it is easy to compact.
OWNER: MARAFIQ
o Compaction of sandy backfill is most easily accomplished when the material is near to its optimum
moisture content. When backfilling reaches pipe spring line, all compaction shall be done first near the
trench sides and proceeds towards the pipe.
o It is recommended that placing and compacting of the pipe zone backfill is done in such a way as to
cause the pipe to ovalize slightly in the vertical direction.
The clean sand bedding shall be compacted to 70% Relative Density (ASTM D4253/ASTM D4254). The clean sand
from the bottom of the pipe to 300 mm above the top of the pipe (sand cover) shall be compacted by water
flooding and hand tamping only. No compaction testing is required in this section of the trench. Within 300 mm
of the top of the pipe, backfill shall be hand tamped, or a board shall be used to protect the pipe from damage
from vibratory plate compactors
Backfill above 300 mm sand cover in non-Traffic area shall be on site excavation or borrowed materials that meet
the following conditions:
• Hand Saw
• Measuring Tape
• Chalk line & Powder
• Wire Cutter
• Solvent Cement
• Lubricant
• Drilling Machine
• Grinding Machine
• Right Angle
• Ladder or Scaffolding with Platform
• Extension wire for Electrical Power etc.
• PVC/CPVC/uPVC pipe and Fittings
OWNER: MARAFIQ
. Starting instructions will be given by the supervisors at the start of each activity to explain
the methodology of works and to communicate safe working procedures to the operatives.
These talks are structured in a way to highlight to major risks involved in the activity and
the various control measures required in order to minimize the risk. It is delivered in a
manner such as the key points will be remembered by the operatives receiving it.
. Toolbox talk meetings will be held for each crew, on group or employees, regarding more
general topics of the Project HSE Policy; in example lesson learned, near miss reports,
implementation of the requirements and message from the LBS management or
Employers HSE personnel.
OWNER: MARAFIQ
All workers will be issued and trained in use of the required PPE equipment to comply with contract procedures and
local regulations and will be supplemented with PPE as required by MSDS & Risk Assessments. This will include but will
not be limited to;
Hard Hats
Safety Boots with ankle support and steel toe caps
Safety Goggles
High Visibility Vests / Overalls with integrated reflective strips
Hand gloves
Face Masks
A variety of mechanisms, such as method statement briefings and toolbox talks will be
implemented to ensure all relevant personnel are appropriately informed.
In addition to their safety induction received at their arrival on site, all the workers will have a
toolbox meeting in order to be briefed about the risks of their specific work task, prior to start of works.
7. 3 ENVIRONMENTAL ISSUES
Toolbox talks and care shall be taken to use plenty of water during high humidity weather.
General housekeeping rules for all operatives shall be observed.
Stationary equipment e.g. lighting towers, gensets etc. will have containment trays beneath.
Maintaining good housekeeping minimizes hazardous waste production by increasing the
likelihood that chemicals will be used before they expire and reducing the need to clean up
chemical spills.
Hazardous substances shall be stored as per manufacturer’s recommendation or as
mentioned in safety data sheet.
Hazardous waste shall be collected and disposed in hazardous waste skip.
Spill kits shall be made available on site.
Dip tray with a capacity of 110% shall be provided to control the chemical spill.
OWNER: MARAFIQ
Work will be performed in accordance with the APPROVED documents; IFC Drawing for Building, Tanks,
Foundation and other structural elements, planning schedule will be updated for delivery and shifting of
material. All lead mechanical engineer site mechanical engineer and material engineer shall have a 3-
weeks look ahead schedule of GRP stock inventory.
SSEM will provide necessary tools and machinery, manual and torquing tool throughout the project which is depending
upon its requirements. Quantities will be determined by actual site/Store demand. Equipment will be inspected prior
utilizing.
11.0 TRAINING
OWNER: MARAFIQ