FIRE FIGHTING DESCRIPTION AND WMS 2020
AIPL/AJQ/QC/WMS/01 Page 2
FIRE FIGHTING DESCRIPTION AND WMS 2020
removed, pipe ends will be reamed or filed out size of bore, and all
chips will be removed.
AIPL/AJQ/QC/WMS/01 Page 4
FIRE FIGHTING DESCRIPTION AND WMS 2020
All pipes will be cleaned inside and outside for removal of dust and
debris before painting.
One coat of Approved Red-oxide Primer will be applied of 35 Microns
film thickness
After drying, one coat of Approved Enamel Paint will be applied of 35
Microns film thickness before installation of pipe.
Finally one coat of Approved Enamel Paint of 35 Microns will be applied
after hydraulic test and in the final stages.
Flushing: Cleaning of Piping and Equipment
After piping is erected, all piping systems including main header line and
branch line will be cleaned to remove all mill, welding scale, oil,
corrosion, and other construction debris.
System will be flush cleaned and filled ready for service immediately
after cleaning.
Do not operate pumps or equipment until debris has been removed from
the respective system has been flushed out.
Flushing of the system can be done from a pumping source with
minimum flow rate to provide a velocity of 3 m/ sec.
Flush the piping system until all debris is removed and clean water
comes out.
Automatic devices which can become clogged during the cleaning
process will be disconnected and will not be connected permanently
until the cleaning process is complete.
AIPL/AJQ/QC/WMS/01 Page 5