1.method Statement - Aboveground Drainage Pipe
1.method Statement - Aboveground Drainage Pipe
1.method Statement - Aboveground Drainage Pipe
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
Table of contents
1. Scope/Objectives
2. Reference
4. OHS Requirement
6. Definitions
7. Responsibilities/Supervision
8. Sequence/Method to be employed
9. Notification of Inspection
11. Records
13. Distribution
15. Attachments
Rev - 00 1 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
1. Scope/Objectives
Installation of above ground drainage pipes and fittings in accordance with the
requirements specified in the relevant specifications, procedures and drawings, considering
safety and quality of the work activities.
2. Reference
2.1. Contract Drawings
2.2. Specifications
2.3. Project Quality Plan Ref:
2.4. HSE Plan Ref:
2.5. Environmental Plan Ref: Shop drawings
2.6. Material Submittals
4. OHS Requirements
4.1. HSE legal and contractual references
Dubai Municipality Code of Construction Safety Practice.
UAE Fire and Life Safety Code of Practice.
ABM HSE Management System.
Emaar- Project Health, Safety, Environment & Security Guidelines.
Rev - 00 2 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
Rev - 00 3 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
Mandatory PPE include coverall (Workers), Hard Hat, Visibility Vest, Safety
Shoes and Goggles.
Task specific PPE includes Hand Gloves, Safety Harness, fall arrestors, etc.
The Supervisor shall ensure his team wears PPE in 100% compliance to project
requirements and to Safe guard themselves.
4.7. Night work and loan working
Night work shall be carried out with approved DDA night work permit, loan work
is prohibited in palace beach residence.
7. Responsibilities/Supervision
7.1. Project Manager:
Shall direct responsible to carry out the works as per approved Method Statement
and Risk Assessment.
Rev - 00 4 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
Responsible to prepare method statement and risk assessment for all critical
operation in the project and the same is approved, communicated and followed.
Directly responsible for ensuring the completion of works as per approved MSRA.
Ensure welfare arrangements are provided and maintained as per the
requirements.
7.2. Project Engineer:
Shall be responsible to organize required machinery, material, manpower to
engineers & foreman for effectively executing the work in a safe manner.
To clarify any discrepancies in the work.
7.3. Foreman:
To execute the work as per Project Engineers instructions with the right
methodology & in a safe manner.
Make sure that all the works are completed prior to offering for inspections.
To execute the works as per approved method statements.
To attend all the comments made by Consultant at the time of inspection.
To ensure all equipments inspection by third party and certificate is displayed.
To ensure workers PPE, sufficient lighting.
7.4. QA / QC Engineer:
To check the work is carried out as per the approved method statement.
To ensure all approved materials are being used.
Verify whether suitability of ambient temperature for casting concrete.
7.5. HSE Staff Responsibilities:
To advice Project Manager, Construction Manager, Engineers & Supervisor/ Foreman
regarding the Safety precautions to be taken and monitor for the safety implementations to
execute the work.
Monitor the lifting plan and work permits procedure is complied with and the safe
conditions are in place.
All employees involved in the activity should be Safety Inducted by safety department
before allowing working at site.
Rev - 00 5 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
Monitor HSE safe working procedures and cross check control measures mentioned in
Risk assessment is implemented for the activity.
Monitor the use of task based PPE for the activity.
Rev - 00 6 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
8. Sequence/Method to be Employed
8.1. Material
8.1.1. uPVC to BS EN 1329-1 (BS 4514) for pipe sizes 80mm dia and above, ABS to BS EN
1455 for pipe sizes 55mm and below, associated fittings, cleaner, solvent.
8.2. Tools for above ground drainage pipes and fittings installation and testing.
8.2.1. Plumber Hand Tools, Portable Power Drill Machine / Cutting Machine, Test plug for drain
pipes testing, PPE.
8.3. Installation Procedure
The following stages are applicable for Installation and testing of above Ground drainage
pipes and fittings.
Pre-Installation Check:
8.3.1. Approved Builders work drawing and approved shop drawing to be checked by supervisor.
8.3.2. Prior to commencement of work, work area should be checked for cleanliness and safety to
start the work
8.3.3. Engineer to check physical verification of material will be carried out for any damages prior
to taking from store.
8.3.4. Site supervisors will ensure that all gridlines and datum lines are marked by main
contractor’s surveyor and all the route and marking are based on datum line provided by
surveyor.
8.3.5. Site supervisor will ensure necessary clearance documents received from safety and other
authorities.
Rev - 00 7 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
8.3.1. Approved shop drawing for drainage layout to be checked for routing of pipes and setting
out dimensions.
8.3.2. During execution of Builder’s work for all wet areas (Bathrooms/ Kitchen/ Toilets), Bilt
surveyor will mark the setting out location as per approved builders work shop drawing in
coordination with main contractor surveyor.
8.3.3. Routing of pipe to be identified as per approved shop drawing and marking of the route to
be done on ceiling or on the wall.
8.3.4. All the horizontal pipes should run to proper slope requirement as per Authority and slopes
as mentioned in shop drawing.
8.3.5. Invert level of pipes to be checked by Supervisor from approved shop drawings and pipe
supports to be installed as per approved shop drawings.
8.3.6. Ensure post tension cable zone are avoidable to route pipe marking. (if applicable)
8.3.7. Marking for Post Tension to be provided by the main contractor. (if applicable)
8.3.8. The approved pipe hangers to be installed from ceiling / wall as per the routing marked
prior to installation of pipe. Pipes to be supported at a distance as specified in approved
shop drawings / manufacturer’s recommendation
8.3.9. Required number of pipes and fittings as per sizes required from approved shop drawings
to be kept ready for installation.
8.3.10. Pipes and fittings to be thoroughly cleaned on surface and any foreign material to be
removed from inside.
8.3.11. Cut the pipe at right angle using appropriate cutter or saw.
8.3.12. Chamfer the pipe and remove burrs and filings.
8.3.13. Clean the pipe and fitting with dry cloth and apply approved cleaner Parabond C-70 outside
the surface of the pipe and inside the surface of fitting, this removes all dirt and machine
release agents, and softens the surface ready for the chemical solvent weld. Failure to do
this can result in joint failure.
8.3.14. The Pipe and socket to be jointed should be carefully examined for any damage, which
would impair the jointing procedure.
8.3.15. The Pipe insertion depth should be measured as the depth from the mouth to the shoulder
of
DOCUMENT NUMBER ISSUE PAGE NUMBER DATE
Rev - 00 8 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
the socket. The insertion depth should then be marked on the Pipe using an indelible
crayon
8.3.16. Using a brush, apply an even layer of approved solvent cement Parabond P-14 to the
mating surface of the Pipe and socket. The cement should be applied in a lengthwise
direction and not in a circular motion. For joints of nominal diameter of 3 and above, the
cement should be applied simultaneously to the pipe and socket by two people
8.3.17. While solvent cement is still wet insert the pipe inside the socket fitting until it reaches
socket end, it is recommended to twist the pipe ¼ turn while inserting it inside the fitting for
better distribution of solvent cement.
8.3.18. Wipe the access solvent cement and leave the joint to dry.
8.3.19. Cleanout will be installed as indicated on approved drawings and to have effective rodding
of main lines in case of clogging. Cleanout shall be located so that there is a clearance for
the purpose rodding / cleaning.
8.3.20. Pipes to be identified as per approved identification scheme.
8.4.1. System to be checked visually for the correctness of installation as per approved shop
drawings.
8.4.2. Pipes to be tested are plugged by drainage test plugs so that air can be vented out through
the screw caps.
8.4.3. Install vertical pipe length to the drainage line to provide necessary testing water head.
8.4.4. Fill the drainage system with water to a height of 1.5m.
8.4.5. The pipe work should be inspected for any leakage and all defected installation should be
repaired and tested again. After testing all pipe ends have to be kept closed at all times
with proper PVC end caps.
9. Notification of Inspection
Rev - 00 9 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
9.1. Engineer to inspect delivered material / installations at site as per attached check
lists, prior to notifying consultant for inspection.
9.2. Bilt shall notify the Consultant with relevant transmittal form for all material
inspection (Material Inspection Check list attached)
11. Records:
11.1. Prepare work inspection request (WIR) along with check list and have them signed
by Consultant.
12. SUPPORTING DOCUMENTATION
This MS to be read in conjunction with the below referenced documents
Contract Drawings and specifications
Project Quality Plan
Project HSE Plan
13. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
Project Manager
Construction Manager
Site Engineer
QA/QC Engineer
HSE Engineer
Subcontractor Engineer
14. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved
with Site in Charge.
Rev - 00 10 of 11
CLIENT
CONSULTANT
CONTRACTOR MEP CONTRACTOR
METHOD STATEMENT FOR INSTALLATION OF ABOVE GROUND DRAINAGE PIPES & FITTINGS
15. ATTACHMENTS
Risk Assessment
Checklist
ITP
Rev - 00 11 of 11