Block Work MS
Block Work MS
Block Work MS
INDEX:
REVISION STATUS
1. PURPOSE
2. WORK LOCATION AND WORK HOURS
3. PROGRAMME
4. RESPONSIBILITIES
4.1 PROJRCT MANAGER
4.2 PROJECT ENGINEER
4.3 HSE OFFICER
4.4 FIRST AIDER
4.5 SITE SUPERVISOR
4.6 OPERATOR
4.7 BANKSMAN
5. MATERIALS
6. PLANT AND EQUIPMENT
7. HSE REQUIREMENT
8. METHODOLOGY
9. INSPECTION AND TEST PLAN
10.RISK ASSESSMENT
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
REVISION STATUS:
1. PURPOSE:
The method is prepared to ensure that construction of warehouse for the project shall comply on plans specifications
and all relevant standard and code requirements in the execution of different work activities to be performed in the
construction of warehouse and other relevant structures associated with the project. In addition this will serve as a tool to
guide all technical personnel and layman execute proper construction procedures complied with the quality and safety plan
for the projects.
3. PROGRAMME:
4. RESPONSIBILITIES:
4.1PROJECT MANAGETR:
Implementing the work program / tracking day-to-day Electrical Work and associated activities as per the
program scheduled.
Ensuring that personnel involved in the specified activity and associated works meets the minimum
qualifications for their assignment and are properly trained.
In-charge of maintaining the safety standards by all staff and ensuring that they have required HSE
Training.
4.2PROJECT ENGINEER:
Responsible for the entire activities of Electrical work and associated work complying with the safety
standard requirements.
To ensure that the team engineers and foreman are aware of the Method statement and all resource area
available to carry out the work as planned.
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
To liaise with the CMCS to ensure timely approval of WIR, Shop drawing etc.
Responsible for the supervision of the work activity and associated work as per approved method statement
and drawings.
To ensure that all equipment’s required for the works are available and in good condition.
To ensure that all the technical matters and changes in the plan are discussed with the foremen.
4.3HSE OFFICER:
HSE officer shall ensure implementation of all safety Procedure while formwork and Performing the
electrical wire installation activity.
He shall ensure that all controls listed in the Risk Assessment are in place.
Necessary safety instructions are to be provided to the crew based on the site live condition.
He shall maintain continuous inspection of the site activities and advice site crew to prevent accidents,
personnel injury and property damage.
In case of emergencies, he shall initiate all recovery measures as per the emergency procedures.
First Aider is responsible for maintaining first aid facilities while formwork and performing the demolition
activity.
He shall administer first aid, monitor and report risks and incidents.
To provide first aid to crew working on the electrical cable laying activity, in the event of any injury.
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
He shall undertake quarterly checks of the office first aid kit to ensure it is compliant with the checklist
issued by HSE staff.
Assist the HSE Officer to carry out quarterly facility inspections.
Assist with any incident investigations and unresolved issues connected with the use of first aid supplies, or
action by the HSE Officer at the site.
Promote good safety practice within the site.
He will coordinate with the Site Engineer on a daily basis and will ensure proper distribution of the
workforce and equipment at required locations.
He will be aware of the possible risk hazards involved with the works and comply with all safety
requirements prior to start of the activity.
He should give proper Tool Box Talk to his crew for safe handling of work.
4.6 OPERATOR:
Will be responsible for safe operation of tale-handler which support the cable drum for laying.
4.7BANKSMAN:
He will be responsible for guiding the Tale- handler for the safe operation.
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
5. MATERIALS:
Tale-handler.
Hand shovel.
Hand tools.
7. HSE Requirements:
The crew must complete the compulsory HSE training like HSE Induction, Initial Fire Response (IFR),
dealing with Hazard and Risks (DHR) and to possess a valid PDO Passport as a minimum to work in this
project.
Site HSE induction will be completed for the crew prior to entering the site with a sticker labelled ”HSE
INDUCTED” affixed on to their helmet.
All Crew will wear Helmet, Safety Shoe & High Visibility Jacket and will use need based PPE like Hand
Gloves, Dust mask and Goggles etc.
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
The supervisor to make an assessment of the hazards & risks with respect to the Demolition works and to
fill the Risk Assessment communication form.
The site Supervisor/ Forman will conduct Tool Box Talk (TBT) and will obtain attendance of the crew.
Supervisor will ensure that all control measures for the specific task are in place as per Risk Assessment.
Barricade must be done around the area of the demolition to be carried out.
Proper access to the work areas will be maintained throughout the working period for easy working. In case
of emergency and the crew should gather at assembly point located nearby.
Equipment’s like wheel loader will be provided with Banks man for giving directions.
All operators & banks man should be trained and must have the DDA Approved 3rd party certificate’s
inspection/ training will be verified for all the plant/ equipment / vehicle operators / drivers prior to
commencement of work.
Right type of machinery / tools for the work will be used.
First Aider, First aid box will be available at site.
Drinking water facility will be provided by the company management.
The crew members will make use of the welfare facilities and the first aid arrangements and must have a
valid 3rd party certificate.
The Crew will work only if the climatic conditions are favourable for the tasks.
An emergency Vehicle will be made available at site.
If hazards are found, the operator will refer to supervisor and establish a safe working method before
commencement of work.
All the rebar edges will be covered with padding protection.
All scaffolding will be fitted with guard rails and toe boards.
LOYAL BUILDING CONTRACTING LLC
ELECTRICAL WORK - METHOD STATEMENT, ITP AND RISK ASSESSMENT
All scaffolding more than the height of 9 M should be inspected by approved 3rd party.
Person working at height will wear Safety harness.
TBT will be conducted regularly prior to start of work.
Open excavations will be barricaded at least one meter away from the opening.
All necessary sign boards & barricades should be placed in position in all required places.
Contractor
Premises of
Consultant Review point - Representative of indicated party to review
Inspection / Site R
Approval submitted documents, result of test etc..
Work Area
Coordinates
Consultant Owner
Contractor
Acceptance
Criteria Specific
Activity Description of Inspection Drawing N" of
(Controlling Quality
NO & Test Activity reference Contractor CEC Punchlist
Procedure, Report
Signature Signature Item N"
Specifications, Code (If
Standars etc..) H W R H W R H W R any)
SAFETY MEASURES
1 TAKEN BEFORE
DEMOLITION WORK
2
Main Contractor: LOYAL BUILDING CONTRACTING LLC. Project: : PROPOSED G-OLY OFFICE, G+M WORKERS Risk Assessor:
Client: SILVERLINE CONSTRUCTION AND MACHINERY RENTAL LLC FACILITY, G-ONLY SHED, OPENSHED & OPEN WASH AREA Mr. JAMES NEEL (SO)
Consultant: DESIGN HOUSE ENGINEERING ON PLOT NO. 5337865 @ SAIH SHUAIB 4, DUBAI
Date : 05-02-2020 Date Next Review: 05-08-2020 Approved By: Reviewed By:
Mr. MUTHUKUMAR (PM) Mr. JOSHUA PRAVIN (SR.SO)
Recommended PPE: Hard Hat, Safety shoes, Safety Harness, coveralls, dust mask,
Equipment Required: Excavator
goggles, gloves
Remarks
Legal compliance
Risk
Consequences
Residual
Control E/I/R
Rating/
Risk
be Harm/
/Potential Hazards
Job steps/ Activities
Hazard identified
Risk level
Sl no
4 Preparation of the Major/ Minor injury Accident due to not Yes 3 5 H R Site engineer together with safety officer 1 5 L
workers. due to unprotected following the safety will conduct a tool box talk, with the
unprotected procedures. involved group before commencing the
job.
MS and RA must be communicated to the
site operatives and is recorded.
demolition area. Only competent person shall be permitted
to carry out the demolition activity.
Full time supervisor to facilitate and look
over and monitor the whole operation.
6 Gas cutting and DEATH, FIRE, Injury to the No 3 3 M R Eye protection, gloves and suitable 2 2
EXPLOSION OR workers involved in clothing to be worn.
burning L
BURNS and ILL the activity. Ensure all staff who undertake cutting/
burning duties are competent to do so.
Hot work to be supervised closely and
undertaken only under A Hot Work
Permit issued by Safety officer.
EFFECTS ON HEALTH Flashback arresters and non-return
valves must be fitted to gas hoses and
bottles.
Hose lengths should be kept to a
minimum
Make sure that the area is isolated
Keep the area clean such that no
machines or materials are stored in the
area
Major Injury to
Collapse of block wall Keep adequate signboards 2 4 M
7 Block Wall person, or property Yes 4 4 H R
on material or Person The Excavators and its operator to be 3rd
damage
party certified
Spray water periodically to avoid dust
pollution
Remove the concrete waste periodically
1. Identify Hazards
2. List Hazard Event
3. Calculate Risk Factor with Initial Risk Rating. I.E. Probability x Severity
4. Detail Controls
5. Calculate Residual Risk Rating with Final Risk Rating
4 16 12 8 4 6 Medium Risk
2 8 6 4 2
Severity
4. Catastrophic – Imminent danger exists, hazard capable of causing death or illness on a wide scale
3. Critical – Hazard can result in serious illness, severe injury, and property and equipment damage
2. Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious
1. Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first aid case
Probability
4. Probable – Likely to occur immediately or shortly