BUILD UP RATE Concrete Work Question
BUILD UP RATE Concrete Work Question
BUILD UP RATE Concrete Work Question
CONCRETING WORKS
Table 1 shows relevant information for mixing/preparation of reinforced concrete (1:2:4 with
25 mm aggregate) for pad foundation using concrete mixer with 7/8 capacity. Calculate build-
up rate for one (1) metre cubic of the concrete.
Table 1
1 Material Cost
2 Labour Cost
3 Machine Cost
TOTAL OVERALL COST FOR ONE (1) METER CUBIC (M3) _______