Risk Assessment For Elevator Shaft Slab Demolition (C01, S10)
Risk Assessment For Elevator Shaft Slab Demolition (C01, S10)
Risk Assessment For Elevator Shaft Slab Demolition (C01, S10)
DESCRIPTION OF TASK ELEVATOR SHAFT SLAB DEMOLITION WORKS (S10) DATE: 04-Jan-17
CONSEQUENCES
STEP 1: Using the matrix, carry out an initial assessment to
determine the risk rating of hazard(s) of the work activity (note: Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
this is without any control measures).
STEP 2: Using the matrix result from step 1 if the risk rating is
tragic or critical then the hazard must be eliminated or work Likely (4) 4 8 12 16 20
activity prohibited and an alternative method found. If the risk
rating is medium then Safety control measures are required to
LIKELIHOOD
STEP 3: Re-assess step 2 if the risk rating remains medium then Unlikely (2) 2 4 6 8 10
you must provide alternatives and or additional Safety controls
until the risk rating enters into the low category and work
activity can be proceed. Rare (1) 1 2 3 4 5