Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Risk Assessment For Elevator Shaft Slab Demolition (C01, S10)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

RISK ASSESSMENT

PROJECT NAME JABAL OMAR DEVELOPMENT PROJECT PHASE IV REF NO:

DESCRIPTION OF TASK ELEVATOR SHAFT SLAB DEMOLITION WORKS (S10) DATE: 04-Jan-17

CONSEQUENCES
STEP 1: Using the matrix, carry out an initial assessment to
determine the risk rating of hazard(s) of the work activity (note: Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
this is without any control measures).

Almost Certain (5) 5 10 15 20 25

STEP 2: Using the matrix result from step 1 if the risk rating is
tragic or critical then the hazard must be eliminated or work Likely (4) 4 8 12 16 20
activity prohibited and an alternative method found. If the risk
rating is medium then Safety control measures are required to
LIKELIHOOD

carry out the activity.


Possible (3) 3 6 9 12 15

STEP 3: Re-assess step 2 if the risk rating remains medium then Unlikely (2) 2 4 6 8 10
you must provide alternatives and or additional Safety controls
until the risk rating enters into the low category and work
activity can be proceed. Rare (1) 1 2 3 4 5

SCORE PRIORITY FACTOR RATING


10 to 25 ACTION NEEDED IMMEDIATELY HIGH (H)
5 to 9 ACTION TO BE TAKEN WITHIN 12 HOURS MEDIUM (M)
1 to 4 ACTION TO BE TAKEN WITHIN 48 HOURS LOW (L)
ABBREVIATIONS:

RIV Risk Index Value C Consequences


MIV Mitigated Index Value L Likelihood

You might also like