Inspection and Test Plan: PT. People Mec
Inspection and Test Plan: PT. People Mec
Inspection and Test Plan: PT. People Mec
ITP-PR-001
Project Name
Rev. No. 0
INSPECTION AND TEST PLAN
PT. People Mec Page 1/3
W M
1) Marking WITHIN
2 Related dwg & SPEC. W M Report
2) Cutting TOLERANCE
W M
3) Beveling
Doc. No. ITP-PR-002
Project Name
Rev. No. 0
INSPECTION AND TEST PLAN
PT. People Mec Page 2/3
INSPECTED BY
APPLICABLE SPEC. OR ACCPTANCE
NO. DESCRIPTION OF INSPECTION / TEST OWNE REMARK
PROCEDURE CRITERIA PM
R
Final Inspection
1) Dimension W W
See inspection Standard
3 2) Visual W W Report
AISC Manual
3) Member ID Mark W M
Related DWG & Spec
4) Project Color Mark W M
INSPECTION STANDARD
NO. DESCRIPTION REFERENCE INSPECTION / ACCEPTANCE CRITERIA
AISC MANUAL
MATERIAL RECEIVING
1 ASTM A6 - Check the materias is the same as the Related spec
INSPECTION
Technical Spec.
Beveling of straight section using the Automatic bevel machine, if non straight section using the semi automatic machine
-.The Inspector waits near the CNC Auto cutting machine and inspects at all times
AISC MANUAL
1) MARKING /CUTTING -.Before Cutting checking the CNC Program
2 AWS D1.1
-.Check whether the size of the steel plate is the same as the Related spec
& Beveling
Related spec. -.After cutting check the Tolerance Dimension and Surface condition
-.If is out of the tolerance, it will repair Grinding or Gouging after welding and Grinding smooth and Liquid Penetrant
Testing.