Bamu Proj
Bamu Proj
Bamu Proj
1|Page
4.2.6 Construction Plan and process ...................................................................... 16
4.3 Utilities ................................................................................................................ 17
5 Engineering and civil works .................................................................................... 188
5.1 Land, Building and Civil Works ....................................................................... 188
5.2 Manpower and training requirement ................... Error! Bookmark not defined.
5.2.1 Manpower requirement................................. Error! Bookmark not defined.
Labor Availability.................................................................................................. 21
Project implementation ............................................................................................. 21
Organizational Structure ........................................................................................... 22
Organization and management .................................................................................. 22
6 Financial analysis ..................................................................................................... 311
6.1 Repair and Maintenance Cost ........................................................................... 322
6.2 Depreciation and Amortization ......................................................................... 322
6.3 Total Revenue ................................................................................................... 322
6.4 Discounted Payback Period ............................................................................... 333
6.5 Cash flow........................................................................................................... 334
6.6 Benefit cost ratio ............................................................................................... 344
6.7 Internal Rate of Return ...................................................................................... 355
6.8 Net present value ............................................................................................... 367
7 Conclusions and Recommendations ........................................................................ 399
Conclusion............................................................................................................... 399
Recommendations ................................................................................................... 400
References ................................................................................................................... 411
2|Page
1. Executive Summary
KEY INFORMATION HIGHLIGHTS
PRODUCTS TO BE MANUFACTURED
RENTAL ROOMS
MARKET DOMESTIC AND INTERNATIONAL
3|Page
2 .Introduction
The current fast and dynamic economic growth of Ethiopia especially in Adama necessitates equivalent
growth of building and construction sector. The sector should expand rapidly to support the overall
economic development sustainable.
In the building sector of the economy, the multi- purpose in the one becoming rapidly expanding in
Adama since dynamic economic development of urban economy requires the construction of these
buildings in the city to support the growing of business service sectors like supermarkets, Beauty salon,
shops, offices cinemas, Computer Center, Cafeterias, restaurant, assembly hall, apartments and other
activities. In this regard, mixed used building expands in the all parts of the city.
Investment and property development play an important role in any emerging markets or economies.
Property generally comprises residential houses and commercial real estate property (mainly mixed us
building) developed for rental business and sale. The property investment market in Ethiopia remained
under developed for several years. As a consequence, the supply of residential houses and non-
residential real estate that can be used for residence, office space, shopping malls and catering services
in the urban centers of the country is disproportionately low to cope with the growing demand in the
country spinning from the average growth in GDP of 9.8% over the last ten years and population
increase. The relatively good performance of the macro-economy (real growth in GDP, low inflation
rate and growth in investment and export sector) has stimulated unprecedented investment growth in the
property sector over the last five years. The growth of investment in the property market over the last
five years in consistent with the global experience suggesting that investment in the residential and
commercial property is greatly influenced by the performance of the macroeconomic conditions. In
general, a stable macroeconomic condition leads to economic and business growth and develops
investors’ confidence. This certainly spurs large demand in the property market for office space,
shopping malls, catering services, apartment and residential houses. Following growing demand trends,
and with the expectation of high return on their investment capital, large number of land developers
pooled their financial resources and invested in the property market.
4|Page
To this effect, the partners of the envisioned Mixed Use Building EBDY who has been living for long
time in this city, planned to construct in Aba Geda Sub-city and undertaken this project study to check
the market, technical and financial feasibility of this project. The promoters are very ambitious and
committed to realize the project. Hence, they expect to get the necessary support from the city
administration to make the project to be operational.
Besides, the government policies and incentives for the private sector investment are very promising that
motivates the promoter to engaged in mixed use building business.
2. Project Objectives
The major goal of this project is to contribute towards the growth of the trade sector in Adama. Its
specific objectives include the following.
2.1.1Specific objective
To construct and develop modern shops, offices, and restaurant& cafeteria facilities that enable to
provide standard services to customers.
To undertake trading and other refuted business activities that enable to generate a reasonable to the
invested capital.
To develop modern business center that would provide full services on city standard.
To create employment opportunities.
Contribute towards the beautification of the city through the construction of modern building
infrastructure and facilities.
To establish economically viable, socially acceptable and environmentally friend mixed use
Apartment.
5|Page
2.3 Project description
The long-term goal of the project is become the best choice trade center in the city. The proposed project
will have a total area of 574m2, designed to reader a multipurpose giving business, which will in turn
plays significant role towards solving shortage of business center in Adama.
The historical nature of the city as business unique location in one of the most attractive center in
Ethiopia (80% urban center).The owners plan the project to render banking and insurance, shopping
facility, offices and cafeteria services to create high quality class to satisfy the interest of customers in
the city. Based on environmental and other considerations, the entrepreneur has determined the type and
size of the building which is already determined by the site; conceptual planning and preliminary
analysis have been carried out by analysts. In order to attract its clients to the service, the project will
develop high standard shop & banking rooms and office of best choices and will also save best quality
apartments, restaurant and café.
The existing promising investment opportunities, the demands of service needs along with relatively
sound investment support made by the government in such kinds of feasible projects, compelled the
project promoter to initiate the multipurpose oriented business project to be established. Despite the
promising business opportunities of the city, the trend on such kinds of investment found to not enough.
The mismatch between the demand for and supply of such kind of services in easily observed in the city.
Therefore, the existing shortage or absence in the supply of these services, along with its commercial
and administrative access, better location and infrastructure access, escalating trend of urbanization and
business activities, thus it is with such reason that this project is identified and proposed and assumed to
be more profitable.
In general, the country’s privatized and free market economy; good governance creates a favorable
environment for the development of investment for private investors.
6|Page
2.5 The significance of the project
The envisaged project deemed to add to the economic development of the city in general in specific with
following ways:
A. Source of Revenue
As public policy of any nation, the government collects different forms of taxes from different business
organizations and individuals. Among the different forms of taxes, business income taxes, payroll
income tax and VAT are collected from undertaking business activities. Therefore, the building will
serve as sources of revenue for the city.
B. Employment opportunity
One of the problems that our country faced is unemployment. Therefore, the current objective of the
government is working on tackling the problem of unemployment and fostering the development
process either through creating self-employment or employment in other organization. Hence, this
project will hire 20 individuals and more than 30 individual during construction.
The license area is located in Adama City Administration, Aba Geda sub-city, Woreda 06, locally
named as" mebrat hayil" . The total area of the project is 574 m2. . It is surrounded by main asphalt road
at west part, south east by resident, south west resident, and mixed use building at North part.
7|Page
3 .The market Study
There are a number of factors which affects the demand of standardized mixed use building. Of these
factors, the most important to have influence is population growth and the level of income. The currently
expanding service industry in Adama and from every corner of the country the city has been inviting
skilled and unskilled labor forces to the center; in addition, the number of both national and international
offices has been increasing. Above all the increase in the number of population increases for the
provision of different services. Nowadays, most of the private business organizations need their own
small-medium offices in order to give their services and provide their products, and they prefer the place
that found in the center or close to the road.
As clearly indicated in the introductory part of this proposal, Adama is the dynamically growing urban
center of Ethiopia. Though the market demand gap for mixed use building is not clearly understand
there is wider gap for such demand as many merchants, organizations are flouring to the city every day.
From prior business experiences, the demand of mixed use building is very high and hence the demand
and the supply gap is very wide.
There has been a significant growth in the number of local and international trades across the country.
This increase is mainly associated with the stimulation of economic activist and partly due to an increase
in the flow of international and local traders in to the Adama. Since Adama is an important commercial
center in addition there is a significant increase in business activates and hence increasing the number of
traders. Even though there is a lack of quantitative estimates that depict the actual demand and also the
annual growth rate commercial facilities are scarce in the city. As a result there is a large gap between
the developed and that of the supply for modern Bank and cafeteria accommodation hence this project
would not face any problem of demand scarcity for it business center and it would provide good service
to customers.
8|Page
3.3 Current supply of mixed use building
Commercial building/office sector has shown a dynamic change in the past few years. The reason for
this could be rapid economic growth and a supporting public infrastructural development. Other factors
relevant in the specific case of commercial buildings are the large increases in national and international
businesses, particularly firms in the services sector.
The business of multipurpose buildings in Adama is booming highly due to the recent rapid growth
experienced in Ethiopia.
As a result, a good number of local and international organizational are coming in place. Government
offices which used to operate in limited spaces all over the city are also concentrating on leasing new
and modern buildings. Increasing numbers of international organization which in the past had typically
converted residences into office space are now moving towards renting whole floors or even multiple
floors in modern city-center commercial buildings.
The demand for office space is a derived demand because firms rent space as an input to the production
of services or goods they provide to businesses and households in the local or national economy.
Following our survey of office space users in several areas are mainly firms providing banking, offices,
cafeteria and restaurants, supermarkets, computer center service.
Future demand for office space is actually driven from growth in number of offices in the city which in
turn is influenced by the macro-economic growth in the country.
Assuming that demand for office space is directly related to the growth in the economy, the forecast for
office space demand is shown in the following table;
9|Page
Table 1: Office Space Demand Forecast
Office space demand under base Office space demand under high
case economic case economic
10 | P a g e
3.5 Target customers
1. Business Community
2. Business organization
3. The government bureau
4. Non-governmental organizations
In order to penetrate and gain considerable market share, one of the major marketing strategies for the
project is consistently rendering quality service to its tenants. Due emphasis must be placed on
improving quality of service and facilities. The major marketing strategies to promote the project and
gain considerable market share include:
Advertising through different means focusing on the existing service and facilities
Promote in association to the key location and nearby business
Working on sustained promotional work.
Working on public relations to reach and influence key personas and organization with a
capacity of making decision.
Keeping the quality of its service/ facilities and consistently improving with changing situations.
Seasonal discount pricing different others customer centric marketing strategies will be used by
the company.
3.7 Competition
There are different forms of competition that may face the envisaged mixed use building. These are
price and non-price based competition. Moreover, there are different competitors that will compete with
the project either directly or indirectly. But the mixed use building under discussion has diversified
marketing strategies that could enable it Cope up with the different competitors in the market. Moreover
it will frequently conduct competitors research which focuses on, the strength and the weaknesses, the
different competitors’ strategies, the techniques they use in rendering the service, their customer
handling methods, and others. Generally the project has many other projects all over oromia villages
which compete with it.
11 | P a g e
3.8 The project facilities and Services plan
In order to provide mixed use business center building services of a high standard, it has been planned to
construct and develop the infrastructure and facilities that would viable to meet the requirements of an
international standard business center. Accordingly, various buildings and facilities will be constructed
phase by phase starting with the most needed ones that are essential to commence the operation of its
business activities. With the completion of construction, the building will provide a combined service
such as shops, offices, restaurant and café service as well as modern business center that primarily serve
its guests and major clients.
Table 2: The plan is that the ground will be partitioned in to different rooms:
12 | P a g e
Since the project will be engaged in mixed building the main sources of its annual revenue would be
from the rental of building spaces such as shops, offices, and banking, café and restaurant. Therefore,
the sources of revenue have been classified in to one category namely the rental of banking and
supermarket, offices, shops, bedrooms restaurant and café based on these classifications. Based on the
market price of similar mixed use building in the area, the envisioned buildings set the following fair
price (Before VAT) for its service, hence when the building construction fully get operational it is
assumed to generate a yearly income of ETB 6,089,493.6.
4. Technical Studies
The envisioned mixed purpose building will provide different rental services to the different customer
groups for different purpose. The building will have ground and four floors. The purpose of the building
explained as follows;
The ground floor, first floor second floor and third floor designed for different business centers
like banks, supermarket, beauty salon(man and women), Computer center, pharmacy, internet
café, boutiques, different shops and other business activities,
The total land required for the envisioned project is estimated to be 574m2. The total area for the
construction of the building will be 500m2, as revealed below.
13 | P a g e
Table 3: land utilization Plan
No Description Land M2
1 Building (G+4)
1.1
Total 500
The construction project is proposed to be started on June 2020/2021, and is expected to be finished on
July 2022/2023. As seen in the abbreviated construction schedule above, a majority of the schedule’s
time is made up of five major activities; concrete, building Enclosure, masonry, mechanical and
Electrical install. Concrete activities include processes such as placing foundations and slab on deck.
The Building Enclosure Phase includes erecting the scaffolding that will allow for exterior sheathing
installation and bricklaying.
Mechanical and Electrical install coincide with each other due to the need for coordination between the
two divisions. There are several periods of construction during the schedule in which there are multiple
construction activities occurring at the same time.
The construction site must be organized accordingly as these processes take place. As with any
construction project, the goal of the schedule will to complete all construction activities before the
required Date of completion.
This date of completion is practical based on the time of year in which the building will be completed.
The team allowed a two week contingency for any setbacks. Typically, winter construction tends to
14 | P a g e
cause unforeseen delays that negatively impact a construction project. These conditions can and will
almost undoubtedly impact the project schedule by causing unforeseen delays and project inefficiency.
Although functional spaces for the project were laid out in significant detail, the rest of the building had
designated spaces but set layouts. It was at the discretion of the project promoter to devise typical
layouts for the non-detailed commercial and office spaces. To make sure that the building’s layouts were
practical, the project owner researched typical architectural layouts for laboratory and executive office
spaces. The walls and partitions throughout the floor will congruent with the structural frame and
column locations.
One of principle deliverables of the project is the structural design of the building. The structural bays
were coordinated with the layout of the building adjustments will be made to the bays if specific layouts
are necessary. The frame will be made up of a grid with repeating standard structural bays. Included in
the structural system are bay sizes, shape and size of structural members, floor compositions and curtain
walls. These elements were established to resist gravity ad lateral loads as appropriate.
The gravity load design will completed for two frames; one of structural steel and one of reinforced
concrete. The structural steel frame will chosen for further design based on cost per square foot, local
availability of material and constructability considerations, such as erection and fabrication. The steel
system will then designed for lateral loading with necessary adjustment being made to framing.
The project group prepared hand structural design calculations for a typical bay of a reinforced concrete
frame. In all reinforced concrete bay designs, a superimposed dead load of 8 pounds per square foot will
be assumed for mechanical equipment, floor coverings and ceilings.
Similarly, the design of the typical bay accounted for the use of different commercial space, in which a
live load of 1000 pounds per square was assumed. Loads will be calculated based on the requirements of
the minimum Design loads for Buildings and other Structures.
15 | P a g e
4.2.5 Foundation Design
The design of a superstructure may be accurate, have considered all possibilities and still fail because
the substructure is incapable of distributing the applied loads to the supporting soil.
Foundation design takes more into consideration than merely the loading from the columns. While the
main part of the project focused on the structural frame and its alternate designs, a preliminary
foundation plan was designed based upon maximum load carried from the superstructure through the
columns. The foundation design conducted by the project team consisted of the selection of foundation
type, determination of the bearing capacity and the design for typical interior and exterior spread
footings.
The construction process for this project is normally a disjointed three mages development by which the
conceptualized need of the promoter of this project is translated into a functional facility that will meet
their needs in terms of time, cost and quality.
Based on a general program of the project owners the consultant who is going to be hired makes site
studies, develops structural designs, prepares drawings and specifications, determines quantities
involved and estimated the resultants costs. All these activities will be done in the first phase of the
project which is the design stage after the document are produced by the designers have been received,
and the works secured the project is supposed to enter the tendering stage. At this stage contractors study
the project document analyze and subsequently determine the construction methods, built up their unit
rates and submit their bids for the works. The promoter of this project intends to compare the bids and
award the contract for the lowest responsible bidder. This, is of course, presupposes that the favorable
proposal does not exceed the allocated budget.
After the award is made and the contract signed between this project owners and the contractor, the
project constructor is expected to prepare and submits a detailed construction program which includes
material schedule, manpower requirement and cash flow forecast.
16 | P a g e
4.3 Utilities
A number of utilities world be put in place in order to ensure smooth functioning of the project. These
utilities include:
Table 4: Utilities
Telephone and
3 Internet
Broadband 20,000
Total 1,200,000
17 | P a g e
5. Engineering and civil works
The Mixed use building has a total site area of 574 m2. The building floor area has
covered 74 m2 and the remaining 500 m2 is left for construction. The type of buildings
and its corresponding civil construction cost is given on Table 5.
A.SUB-STRACTURE
1 excavation and earth
works 139,785.335
2 Block work 275,767.2
18 | P a g e
As shown on Table 5, the total cost of building and civil work is estimated at Birr
13,576,479.2 and out of which the proponent has worked more than birr 11.8 million.
The list of manpower and the annual cost of labor is indicated in Table 6.
SN
19 | P a g e
8 Marketer 1 Diploma in 5,000 60,000
marketing
100,800 1,209,600
Grand Total
20 | P a g e
5.2.2 Labor Availability
Workers for this type of plant are available throughout the year. No foreseeable problems are
expected as most of the work requires no previous skills.
The project’s implementation is expected to take 24 months. The major activities include Bank
loan processing construction of the building, cleaning the area around the building, Procurement
of equipment and start rendering services. The time schedule for major activities is presented
below:
SN Activities Date
21 | P a g e
5.4 Organizational Structure
Organizational Structure
The organizational structure of the project is designed by including all the necessary personnel
under the right division. At the top of the organizational structure, there will be manager with the
responsibility of supervising the overall activity of the building. Depending up on the nature of
the center and the amount of work to be performs; there exist auxiliary units under the general
manager.
Employees under each unit will be supervised by the department head that is accountable for the
general manager. General Manager is appointed by the owners
As clearly shown in the organizational structure, the center organization has one general manager
and three main sections. Under the general manager there are the, Marketing Department,
Maintenance and Building administration department. Under building admin dept there exist two
sections i.e., HRM & finance and general service. Further sub sections are also organized under
technical and maintenance manager. The following section deals with the duties and
responsibilities of each department.
He/she will plan, organize, direct and control the overall activities of the building.
He/she will devise policies and strategies that will enable the center to be profitable.
He/she will incorporate modern technological innovation that will facilitate the service
delivery of the building to increase customer’s satisfaction.
He/she will plan, organize, direct and control the human and non-human resources of the
building so as to achieve the short and long run objectives of the organization.
22 | P a g e
B. Building Administration Department
The building Administration Department of the multipurpose building has two main sections
(HRM and Finance and General Service section). It has responsible for undertaking the
following activities;
Well non-human resources of the project, which include; effective handling of the
different resources of the building, and devise strategies of controlling against fraud and
damage.
Will provide the right material or inventory to the center with right price at the right time.
Will plan, organize direct and control the financial transaction of the building by using all
the necessary documents.
Accountant and casher that will collect money from the customers.
Will develop sound financial control system by developing modern financial control
systems.
Will prepare the annual financial statements and prepare condensed reports for both the
General Manager and other concerned government body.
Follow the overall status of the business and provide maintenance and repair services
Will handle the overall marketing activities of the organization which include planning,
organizing, directing, and controlling.
Will develop the marketing strategies for future multipurpose building development
23 | P a g e
D. Technical and maintenance manager
Works in collaboration with general service to make sure tenants are well serve
Partners
General Manager
Personnel Promotion
Finance
&Property
Officers
IT, Supervisors
Electricity
24 | P a g e
5.5 Financial Requirement and Analysis
The financial resource is a prime resource for undertaking any activities. Hence for
implementing this mixed use building a total of 16,605,630.5 ETB is required.
From this 30% (4,981,689.15) birr will be covered by the promoter of the project while the rest
70% (11,623,941.3) will be covered through loan from bank at the prevailing interest rate.
Therefore the said amount of finance is needed for undertaking the following.
Total 13,872,799.2
25 | P a g e
B. Building Machineries and Equipment’s
SN Description Measure Qty Unit cost in Total cost in
ment Birr Birr.
(Security Equipment)
C, Vehicle
SN Description UOM Qty Unit Cost in Total cost in Birr Remark
Fr.
Total 300,000.00
26 | P a g e
D .Office Equipment’s
Total 101,800.00
27 | P a g e
Working Capital
Operating Expenses
6 Uniforms 6,000.00
Total 256,513.5
28 | P a g e
Pre-service Expenses
Total 100,000.00
3 Vehicle 150,000.00
29 | P a g e
Year 1 Year 2 Year 3 Year 4 Year 5
Description
30 | P a g e
6 .Financial analysis
The financial analysis of this mixed use project is based on the data presented in the previous
chapters and the following assumptions: -
31 | P a g e
6.1 Repair and Maintenance Cost
The annual repair and maintenance cost of the plant is estimated based on the following
rates.
Item Rate
Machinery and equipment 5 % of the total cost or Book value
Building and civil works 2% of the total cost or Book value
Utilities 5% of the total cost or Book value
The following depreciation rates are applied to depreciate the assets of the project:
Buildings and associated civil works and Machinery and Equipment’s and utilities are 20%
depreciation rate.
Based on the projected profit and loss statement, the project will generate a profit throughout
its operation life. Annual net profit after tax increases from Birr 4,158,941.3at the beginning of
the project to Birr 8,123,447.01 during the last year of operation year. The detail is presented in
Annex.
32 | P a g e
6.4 Discounted Payback Period
The payback period, also called pay–off period is defined as the period required recovering the
original investment outlay through the accumulated net cash flows earned by the project.
Accordingly, based on the projected cash flow it is estimated that the project’s initial
investment will be fully recovered within 3 year 2 months. A project, which has an initial
cash outlay of Birr 16,605,630.5 and a variable annual cash inflow has a payable period
of 5 years
The table below shows payback period determination using cash flow of a hypothetical
project.
If 7,618,944.5 = 12 month
It indicated that the original investment costs would be recovered after a little less than 3.
299 years, without including the construction period.
A single project proposal may be accepted if the payback period is smaller than or
equal to an acceptable time period (a firms Maximum desired payback period.
33 | P a g e
6.5 Cash flow
The projected cash flow of the envisaged project shows that the project would generate
positive net cash flows throughout the operation years. Cumulative cash flow generated by the
project towards the end of the first operation year will amount to Birr 4,696,100.59. At the end
of the project life, this amount will rise to Birr 8,660,608.71.
Cash flow = cash in flow (net sales revenue) – cash outflow (operating cost + income
tax)
The BCR is defined as the ratio of the sum of the project’s discounted benefits to the sum of its
discounted investment and operating costs.
(1
B n
t
t
r)
BCR t 0
(1
C n
t
t
r) t 0
NBCR = BCR – 1
The two benefits – cost ratio measures give the same signals because the difference
between them is simply unity.
Since benefit – cost ratio measures net present value per Birr of outlay, it can
discriminate better between large and small investments.
34 | P a g e
The Decision rule for BCR
A project is accepted b/c its BCR is greater than 1 (i.e. if its discounted benefits
exceed its discounted costs).
BCR is 1.34 and positive this indicates this project would return 1.34 birr in benefits for
each birr spent.
The internal rate of return (IRR) is an indicator of the efficiency or quality of an investment. A
project is a good investment proposition if its IRR is greater than the rate of return that could be
earned by alternate investments or putting the money in a bank account. Accordingly, the IRR of
the project after tax is computed to be 14.1% indicating the viability of the project.
To illustrate the calculation of internal rate of return, consider the cash flows of the
following hypothetical project
YEAR 0 1 2 3 4 5
The IRR is the value of r, which satisfies the said condition Let us, begin with,
say, r = 10 percent. The right – hand side of the above equation becomes:
∑
( )
35 | P a g e
( ) ( ) ( ) ( )
( )
22,253,550.1………..Q1
Since this value is higher than the target value of 100,000, we have to try still a higher
value of r. Now let us try r = 20 percent. This makes the right – hand side equal to:
( ) ( ) ( ) ( ) ( )
……..Q2
This value is still higher than our target value, 16,605,630.5 so we increase the value of r
from 20 percent to 21 percent
( ) ( ) ( ) ( ) ( )
……..Q3
Now this value is less than , we conclude that the value of r lies between
20 percent and 21 percent.
For most of the purposes this information is sufficient. However, if a single value is
required, we have to resort to interpolation
For that purpose we can use the following procedures
The project is accepted because the IRR is greater than the interest rate in the market. That is, all
projects with an IRR greater than some target rate of return should be accepted.
The target rate is usually the same rate used as the discount rate employed in the
computation of the projects net present value.
36 | P a g e
6.8 Net present value
Net present value (NPV) is defined as the total present (discounted) value of a time series of
cash flows. NPV aggregates cash flows that occur during different periods of time during the
life of a project into a common measuring unit i.e. present value. It is a standard method for
using the time value of money to asses’ long-term projects. NPV is an indicator of how much
value an investment or project adds to the capital invested. In principle a project is accepted if
the NPV is non-negative. Accordingly, the net present value of the project at 10% discount rate
is found to be Birr 5,647,919.6 which is acceptable.
∑
( )
( )
( ) ( ) ( ) ( )
( ) ( )
The decision rule is that the project is accepted because the NPV of the project is positive and
greater than zero.
37 | P a g e
6.9 The feasibility study
The IRR is positive and greater than the interest of fund in the market.
The payback period in the financial study is somewhere between the second and third
year.
The IRR ratio is equal to 20.99% which is higher than the interest rate present in the
market.
38 | P a g e
7 .Conclusions and Recommendations
Conclusion
The objective of this proposed feasibility study is primarily to facilitate the entrepreneur with the
investment information and provide an overview about project. The proposed feasibility may
form the basis of an important investment decision and in order to serve this objective, the
document covers various aspects of Concept Development, Start-up, Production, Marketing,
Finance and Business Management.
The feasibility is based on the information obtained from various agricultural sources as well as
discussions with businessmen. For financial model, since the forecast/projections relate to the
future periods, actual results are likely to differ because of the events and circumstances that
don’t occur frequently as expected.
Whilst due care and attention has been taken in performing the exercise, no liability can be
inferred for any in-accuracy or omissions reported from the results thereof. It is essential that our
report be read in its entirety with financial model in order to fully comprehend the impact of key
assumptions on the range of values determined.
The project is accessible and has the necessary infrastructure such as road, telephone, water and
electric power. The proposed project clearly identifies all the necessary equipment, inputs,
Management of the company and the required man power. The highest authority in the project
will be vested in the hand of the owner. He will control the overall activities of the proposed
project. Demand projection divulges that there is high demand for feed production in the country.
Accordingly, the planned project is set to provide quality products in the area.
The proposed project possesses wide range of economic and social benefits such as increasing
the level of investment, tax revenue and employment creation for both women and youths. It will
have also environmental concerns to protect it by planting trees around its working area and by
utilizing environmental friendly raw materials. Generally, the project is technically feasible,
financially and commercially viable as well as socially and economically acceptable. Hence the
project is worth implementing.
39 | P a g e
Recommendations
Financial sensitivity analysis shows that the project is highly sensitive to decrease in sales
revenue but relatively less sensitive to increase in raw material and investment costs. Therefore,
it is recommended that the company should give a great attention for the possible reasons for
sales reduction. In this case, different mechanisms should be selected and implemented to
increase sales. In addition to this, the company should decrease its cost that lowers profitability.
The project must utilize modern promotional styles to capture the planned market share. To do
so, it has to design effective strategy to achieve this plan.
Although, due care and diligence has been taken to compile this document, the contained
information may vary due to any change in any of the concerned factors, and the actual results
may differ substantially from the presented information. In this case, any delaying to implement
the project creates some problem on its profitability as there is always change like change in
price of services and goods, cost of raw materials, customers preference and purchasing power
etc.….So, it is recommended that investors should implement the project as soon as possible
before any change occurred.
40 | P a g e
References
Eyob Deraro (2013) Project Proposal for the construction of Mixed use Building.
Wikipedia: The Free Encyclopedia. Retrieved December 10, 2006 from the World Wide Web
www.wikipedia.org.
41 | P a g e