NTPC Limited Anta Gas Power Station: First Prize Thermal Power Stations
NTPC Limited Anta Gas Power Station: First Prize Thermal Power Stations
NTPC Limited Anta Gas Power Station: First Prize Thermal Power Stations
NTPC LIMITED
ANTA GAS POWER STATION
Anta (Rajasthan)
Unit Profile
NTPC Anta is a Gas-Based Combined Cycle Power Plant situated near Anta village in
Baran District of Rajasthan State. The power plant has capacity of 419.33 MW and
works on combine cycle principle. The project was installed to meet the power
demand of northern region states - Delhi, Haryana, Himachal Pradesh, Jammu &
Kashmir, Chandigarh, Punjab, Rajasthan, Utter Pradesh and Uttaranchal. Station has
completed 25 years of its commercial operation on 01/04/2014.
CONFIGURATION
There are three gas turbines At NTPC Anta with 88.71 MW capacities each. These
turbines work on Brayton Cycle principle. There is one steam turbine which works on
Rankine cycle and has a capacity of 153.2 MW. In Combined Cycle module, three gas
turbines, three heats Recovery Steam Generators (HRSG) and one Steam Turbine put
together. Thus station has a total installed capacity of 419.33 MW.
Fuel
The gas turbine is designed for firing multi-fuel such as Naphtha, HSD and Natural
gas. The primary fuel for the project is lean natural gas supplied from Western
offshore gas fields (Bombay high, South Basin, etc.). The gas is transported from the
gas fields to project site by GAIL through HBJ pipeline. These units are also capable of
408
firing Naphtha. The annual natural gas requirement is about 490 Million SCM for 60%
PLF.
Reduction in running hours of CW pump, CT pumps and ARCW pump when STG goes
under shutdown. By modification, in ARCW discharge line, fire hydrant line
connected to discharge of ARCW to supply cooling water during STG shutdown.
During Steam Turbine shutdown ACRW pump (30 KW) is required to run for min 72
hrs for cooling of STG rotor shaft and its auxiliaries like CEP, HP / LP BFPs etc. As
suction of this ARCW pump is from main CW line, hence one CW and one CT pump is
required to be in service during running of ARCW pump. A modification has been
carried out through which water has been taken from hydrant header line and
connected to discharge of ARCW pumps. It has resulted in stopping of one CW , one
CT two ARCW pumps, 2 No of lube water pumps for CW and CT Pump each, CW
Screen wash pump. One Jocky pump of 15 KW runs continuously. Total saving
achieved during the year was 257458 Kwh.
409
line of clarified water pump was connected with
the DM plant over head tank. By this
modification 24 hr running of clarified water
pump saved while Running of DM plant O/H
tank filling pump (15 KW) increased by 4
hrs/day.
During the closed cycle Cooling Water operation 10-11 CT fans run continuously.
When RMC (Right Main Canal) is charged, all CT fans are stopped. Also at the time
of closure of RMC, canal gates provided about 1.5 km away from the gates of plant
intake channel are closed to create the pondage for using the available water in the
canal, plant circulate this pondage water till it start losing on account of condenser
vacuum. As the water temperature rises, CT fans are put in service one by one to
maintain the condenser vacuum. Out of total 10 no. of CT Fans, only 5-7 No. of CT
Fans run during partial open cycle operation.
The temp of Electrical/C&I Panel room is maintained around 22° C for proper
functioning of the control panels. This temp. is maintained by running Air
Conditioning System. There are 2 Nos of Centralized AC Systems installed. One for
cooling CCR Building and One for cooling control panel room at Switchyard Control
Room. During the winter season when ambient temp goes down, requirement of
running AC System also decrease. Compressors are stopped during night hours and
only AHU (Air Handling Unit) is kept running for air circulation. Stopping of AC
compressor & its pumps in each system (2 Nos of Condensate Pump, 2 nos of
Chilled Water Pumps and One Cooling Tower Fan), Stopping of GT lube oil cooler
fan, generator CW fan and two roof extractor fan of GT and STG hall.
410
First Prize Thermal Power Stations
(Coal fired plants > 100 MW capacity)
Lanco Anpara Power Limited (LANPL) is an ISO 9001, 14001 & OHSAS 18001
certified company having a total capacity of 1200 MW (2 X 600 MW). Unit#1 started
its commercial operation on 10.12.2011 and Unit#2 commercial operations started
on 18.01.2012.
Sub critical units of 600MW comprising of Boiler Manufactured by M/s. Don fang
Boiler Group Co. Ltd., and Turbine designed and manufactured by Dongfang Steam
Turbine Works. The Boiler is a Single drum which adopts subcritical natural
circulation, opposed burning of front and rear wall, single reheating, single-furnace
balanced draft, all-steel framework and all-suspension structure, wherein, reheating
temperature is regulated by dampers and the rotating type air preheaters are set in
the main post of the boiler. Steam turbine used in this project is a subcritical, single
reheat, condensing, tandem, three-cylinder steam turbine.
411
TECHNICAL SPECIFICATION OF STEAM TURBINE
GENERATION MU 100
PLF & Availability %
8000 6918.2 83.9
80 65.81
6000 55.14
60
3979.17 37.85
4000 40
2000 20
0
0 FY 2012-13 FY 2013-14 FY PLF
2012-13 Availability
FY 2013-14
412
Specific Coal Consumption 2 Specific Oil
1.79 Consumption
0.8 kg/kWh
0.67 0.67 ml/kWh
1.5
SCC (Kg/kwh)
0.6
SOC (ml/kwh)
1
0.4
0.48
0.2 0.5
0 0
FY 2012-13 FY 2013-14 FY 2012-13 FY 2013-14
7.53
8
2444
6
2360.2
4
2344
2
0 2244
FY 2012-13 FY 2013-14 FY 2012-13 FY 2013-14
2. Induced Draft Fans’ eroded blade set change in Unit#2: It has been
identified that energy consumption of ID Fans increased in Unit#2. On
inspection it was found that its blades were eroded. To increase the fan
efficiency, Induced Draft Fans’ blade set replaced with new blade sets in Unit#2.
The saving is considered from Oct 13 to March 14 i.e. 6 months for one unit
413
only. Before it was 200 MWh per day, and after 193 MWh per day. Saving of
1260 MWH achieved in the year.
• Investment: 290 lacs
• Energy savings: 1260 MWh
• Financial savings: Rs.37.80 lacs
4. Stopping of Bottom Ash Low Pressure (BALP) pumps in AHP: There are
three Bottom Ash Low Pressure (BALP) Pumps out of which two are working and
one is standby. During bottom ash handling, these pumps were used to fill the
bottom ash hoppers. After one modification, economizer hopper slurry line
diverted to both bottom ash hoppers thus eliminating the use of BALP pumps.
Saving is considered from Oct.13 to Mar.14 i.e. six months. Saving of 2 pumps
of 35 KW each for 24 Hours, consumption 32 KW for each pump. Saving thus
achieved in one year is 276.48 MWh
• Investment: 0.5 lacs
414
• Energy savings: 276.48 MWh
• Financial savings: Rs.8.29 lacs
6. Fire Fighting system made in auto after modifying the water usage in
Coal handling Plant: In Coal handling Plant pre-wetting of coal and dust
suppression of track hopper was fulfilled by fire water line as per original design.
Efforts were made to change the pre-wetting and dust suppression line from fire
water to reject cooling water of crushers. Then Fire Fighting system then kept
on auto and now only jockey pump runs to maintain the pressure of fire fighting
pipe line in place of higher rated main fire hydrant pump, unless there is some
usage of fire water. Saving considered from June 13 to Mar 14, i.e. 10 months.
Before the consumption was 5.76 MWh per day for Fire Fighting & after it is 4.08
MWh per day. Saving thus achieved is 504 MWh in one year.
• Investment: Nil
• Energy savings: 504 MWh
• Financial savings: Rs.15.12 lacs
415
Before Modification After Modification
416
Before modification After modification
11. APH seal and sector plate repair to reduce APH leakage of Unit#1:
During energy audit it was found that APH leakage increased considerably. Thus
APH seal and sector plate repair work was taken in annual overhauling of
Unit#1. Saving considered for 45 days only. Draft system power consumption
was 367 MWh/day before AOH, and 308 MWh after AOH. Saving thus achieved
is 2655 MWh in the year.
• Investment: Rs.50 lacs
• Energy savings: 2655 MWh
• Financial savings: Rs.79.65 lacs
417
spray), but after modification loss is only 6 Kcal/KWh (140T/H superheater
spray & 9 T/H Reheater spray). Saving Considered for 45 days. Thus 1666 MT of
coal could be saved in the year.
• Investment: Rs.300 lacs
• Fuel savings: 1666 MT
• Financial savings: Rs.41.65 lacs
418
Second Prize Thermal Power Stations
(Coal fired plants > 100 MW capacity)
Anpara thermal power plant is one of the prestigious thermal power plant of Uttar
Pradesh Rajya Vidyut Utpadan Nigam
Limited Lucknow UP, which is located
near village Anpara on the bank of the
Rihand reservoir. It is called as the pit
head power plant. The coal to all these
units is fed from Kharia, Kakri and Beena
open coal mines of NCL, by means of a
marry-go-round system, maintained by
UPRVUNL and the required water is taken
from the Rihand Reservoir(Govind Vallabh
Pant) having two stages which are as
follows:
CONFIGURATION:
419
FUEL
Total consumption of coal per day is approximately 25000 MT/day, if all above units
running at full capacity, which carry out through MGR system from open coal mines
to track hopper of Anpara ‘A’ thermal power plants (10000MT/day) and track hopper
of Anpara ‘B’ thermal power plants (15000MT/day). Liquid fuel LDO is used during
initial light-up or during un stable flame conditions in the boiler. The normative value
of liquid fuel consumption allowed by UPERC is 02 ml/kWhr.
420
2. REPLCEMENT OF LINERS OF TUBE MILLS & HELIXES OF SCREW
CONVEYORS
421
4. REPLCEMENT OF COAL BURNER IN 2 X 500 MW ANPARA
Due to deformation of coal burner tips, there was improper mixing of air in coal. So
there was high unburnt carbon in bottom ash found and specific coal consumption was
high. After replacement of coal burner specific coal consumption and unburnt in
bottoms ash was reduced. By this action fuel consumption was reduced. The power
consumed by boiler side auxiliaries i.e. the Mill/PA/FD/ID fans was also reduced.
Make up water consumption was on higher side due to steam & water leakage from
boiler & turbine side valves/drains/flanges & instruments impulse lines. The same was
attended and make up water consumption was reduced.
Due to excessive damage of Flue gas duct, there was heavy loading on ID Fans.
Loading on ID Fans was up to 390A in 2X500MW machine which was 100A above the
design value. After repairing flue gas duct ID Fan current drop to 310A. In 3X210MW
unit margin in ID Fan was not available, so furnace draft frequently fluctuated towards
positive side. Same was improved after repairing of Flue gas ducts.
422
8. MODIFICATION IN THE DESIGN OF CEPs OF 2X210 MW UNITS
The condensate Extraction Pumps(CEPs) installed in Anpara ‘A’ TPS units were running
below their designed capacities since the commissioning of units due to which both
the CEPs had to be taken into service to achieve the full load capacity on the units. As
per the design, only one CEP is sufficient to have full load generation. The matter was
taken up with the OEM firm and as per their suggestion one no. CEP was sent to their
works for necessary modification in its design against work orders during the
overhauling of unit 1 & 3 in May 2012 & Oct./Dec., 2013 respectively . After the
necessary modifications, the installation and commissioning of the pumps were done
at site by the firm and it has been found that the modified CEPs are capable of
meeting out the full load requirements of the unit generation by itself without the
need to run the other CEP for this purpose. This has resulted into appreciable energy
saving and the efforts are being made to get the similar modifications done in other
CEPs also.
423
Total Thermal Energy Savings (435394.84 mKcl )
1. REPLACEMENT OF AIR PRE
HEATER SEALS
2. REPLCEMENT OF LINERS OF
TUBE MILLS
3. ATTENDING TUBE LEAKAGE OF
HPH 5B/6B
4. REPLCEMENT OF COAL
BURNER IN 2X500MW UNITS
5. ARRESTING STEAM LEAKAGES
424
First Prize Thermal Power Stations
(Coal & Gas fired plants < 100 MW capacity)
Meghalaya Power Ltd is a CPP for Star Cement with installed capacity of 43 MW.
Meghalaya Power Ltd is situated at Lumshnong, Dist.- East Jaintia Hills of Meghalaya
state.
The power project was installed to meet the power requirements of its sister concern
“Star Cement”, This is largest capacity CPP in the state of Meghalaya. The project
started its operation on 28 February, 2013.
CONFIGURATION
The Power plant has 2x90TPH CFBC Boiler – Thyssen Krupp India Ltd. make and a 43
MW BHEL turbine. To reduce water consumption Air Cooled Condenser have been
installed.
Fuel for Boiler: - CFBC Boiler is an environment friendly boiler and utilizes low GCV
coal.
2012-13 2013-14
GENRATION(MUs) 4.407 123.442
PLANT LOAD FACTOR (%) 21.35 38.71
Machine Availability Factor (%) hrs. 5658 3219
GROSS HEAT RATE(KCAL/KWH) 4275 2978
425
Major Energy Conservation Initiatives
Fly ash of ESP-1 field is being re-used by feeding it with coal & cyclone ash as a
homogeneous mixture. By mixing these ashes to the fuel plant is increasing the
combustion timing of coal, so that 100% combustion can take place. Also by using fly
ash of ESP-1st field & of cyclone ash, the un-burnt carbon in ash is taken again for
combustion. Thus the wastage of fuel energy is minimized. For this purpose a diverter
in ash conveying line has been introduced as well as an intermediate silo for ESP ash
has been installed on boiler, so that proper mixing of ESP fly ash with coal can take
place.
426
Bed ash cooler system is designed & installed to reduce the heat loss through bed
drain, as when we drain the bed ash it comes out with very high heat energy as
waste, but using bed ash cooler we are heating primary air from ambient temperature
to 280 °C, also unburned carbon which are lighter in weight are being returned to
boiler with hot air coming out from Bed Ash Cooler.
Variable Frequency Drives (VFDs) were installed in all main motors, pumps &
compressors to optimize the operation without wastage of power.
In control room, plant has PMS SCADA for Power system control. From this PMS plant
is able to operate (open/close) the breakers of switchyard at our 132 KV Substation.
Plant can also synchronize the TG Set with grid from remote i.e., from PMS SCADA
5. Equipment’s Interlocking
For 100% combustion excess air is required but excess air also leads to loss of ignition
as some amount of unburned carbon also migrates with excess air, for reducing that
loss plant interlocked ID fan’s RPM with furnace Draft, so that optimum operation can
take place and minimum migration of unburned carbon will take place. For reducing
excess air loss coal feeder’s RPM are interlocked with excess air & drum pressure so
that the drum pressure will be maintained with minimum excess air loss.
HP heaters are taken in line to improve the boiler feed water temperature, by
introducing HP Heaters around 70° C temperature rise takes place in boiler feed
water.
427