Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Up PJB Muara Karang: Laporan Progres Harian Pekerjaan

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 12

LAPORAN PROGRES HARIAN PEKERJAAN

UP PJB MUARA KARANG


JASA PERBAIKAN SILINCER & DINDING DALAM GAS DUCT M1 GT 1.1 MUARA KARANG 2020

PT. GUNUNG API MULIA


GENERAL TRADING & ENGINEERING COMPANY
BOILER, REFRACTORIES, INSULATION, MECHANICAL & ELECTRICAL
JL. GAYUNG SARI TIMUR BLOK MGJ NO. 9 SURABAYA
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Senin Monday, October 19, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Mobilisasi Material,Tools , dan Manpower 100 % 100 % FINISH >. Pemasangan akses Scafolding untuk pembongkaran
ke Lokasi Kerja roof silincer
>. Pemotongan Plat luar roof untuk akses pengangkatan
panel silincer sisi utara dan selatan

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 1 Peralatan Scafolding Skill 14 1 Site Manager 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 2 Mobile Crane Welder 6 2 Supervisor 4
03 .00 09 .00 15 .00 21 .00 3 3 Generator c/w Panel Listrik Helper 2 3 Engineering 1
04 .00 10 .00 16 .00 22 .00 4 4 Mesin Las GTAW 200 A 4 QC 1
05 .00 11 .00 17 .00 23 .00 5 5 Mesin Las SMAW 160 A 5 Safetyman 3
06 .00 12 .00 18 .00 24 .00 6 6 Plasma Cutting 200 A 6 Driver 2
Note : 7 7 Mesin Blander 7 Administrasi 1
H M C 8 8 Peralatan Isolasi 8
Hujan Cloudy / Mendung Clear / Cerah 9 9 Peralatan Pengecetan 9
10 10 Tool Box
TOTAL EQUIPMENT TOTAL 45 TOTAL 13 58

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Selasa Tuesday, October 20, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pemasangan akses Scafolding untuk pembongkaran 100 % 100 % Finish >. Pemotongan Plat luar roof untuk akses pengangkatan
roof silincer panel silincer sisi utara dan selatan
2 >. Pemotongan Plat luar roof untuk akses pengangkatan 65 % 65 % On Progress >. Pemasangan Scafolding di dalam area Gus Duct untuk
panel silincer sisi utara dan selatan penahan panel silincer
>. Pengangkatan roof gas duct silincer

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot Skill 14 1 Site Manager 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit Welder 6 2 Supervisor 4
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set Helper 2 3 Engineering 1
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4 QC 1
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5 Safetyman 3
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6 Driver 2
Note : 7 Mesin Blander 2 Set 7 Administrasi 1
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL 45 TOTAL 13 58

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Rabu Wednesday, October 21, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pemotongan Plat luar roof untuk akses pengangkatan 65 % 35 % 100 % Finish >. Pengangkatan Panel Silincer sisi depan ( 5 panel sebelah
panel silincer sisi utara dan selatan kiri dan 5 panel sebelah kanan)
2 >. Pemasangan Scafolding di dalam area Gus Duct untuk 100 % 100 % Finish >. Mobilisasi Panel Silincer ke Workshop PT.GAM
penahan panel silincer >. Pemasangan Scafolding area Inlet HRSG sisi timur,barat,
3 >. Pengangkatan roof gas duct silincer 100 % 100 % Finish dan roof
>. Pembongkaran Plat dan isolasi Area Gas Duct sisi timur
dan barat

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot Skill 14 1 Site Manager 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit Welder 6 2 Supervisor 4
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set Helper 2 3 Engineering 1
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4 QC 1
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5 Safetyman 3
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6 Driver 2
Note : 7 Mesin Blander 2 Set 7 Administrasi 1
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL 45 TOTAL 13 58

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Kamis Thursday, October 22, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pengangkatan Panel Silincer sisi depan ( 5 panel sebelah 100 % 100 % Finish >. Pengangkatan Panel Silincer sisi belakang ( 5 panel sebelah
kiri dan 5 panel sebelah kanan) kiri dan 5 panel sebelah kanan)
2 >. Mobilisasi Panel Silincer ke Workshop PT.GAM 100 % 100 % Finish >. Mobilisasi Panel ke Workshop
3 >. Pemasangan Scafolding area Inlet HRSG sisi timur,barat, 45 % 45 % On Progress >. Pemasangan Scafolding & inlet HRSG sisi timur,barat,dan
dan roof roof
4 >. Pembongkaran Plat dan isolasi Area Gas Duct sisi timur 25 % 25 % On Progress >. Pembongkaran Plat dan isolasi Area Gas Duct sisi timur
dan barat dan barat

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Jumat Friday, October 23, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 Pengangkatan Panel Silincer sisi belakang ( 5 panel sebelah 100 % 100 % Finish >. Pemasangan Scafolding & inlet HRSG sisi timur,barat,dan
kiri dan 5 panel sebelah kanan) roof
2 Mobilisasi Panel ke Workshop 100 % 100 % Finish >. Pembongkaran Plat dan isolasi Area Gas Duct sisi timur
3 Pemasangan Scafolding & inlet HRSG sisi timur,barat,dan 45 % 25 % 70 % On Progress dan barat
roof >. Pemasangan akses scafolding area dinding selatan gas
4 Pembongkaran Plat dan isolasi Area Gas Duct sisi timur 25 % 35 % 60 % On Progress duct silincer
dan barat >. Pembongkaran Proforated Plate Panel Silincer di Area
Workshop PT.GAM

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Sabtu Saturday, October 24, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 Pemasangan Scafolding & inlet HRSG sisi timur,barat,dan 70 % 30 % 100 % Finish >. Pemasangan akses scafolding area dinding utara gas duct
roof silincer
2 Pembongkaran Plat dan isolasi Area Gas Duct sisi timur 60 % 40 % 100 % Finish >. Pembongkaran perforated plate di area dinding sisi selatan
dan barat gas duct panel silincer, (pemotongan stut bolt dan as drat)
3 Pemasangan akses scafolding area dinding selatan gas 100 % 100 % Finish dilanjutkan dengan pelepasan canal c
duct silincer >. Pembongkaran Isolasi Gas Duct Silincer sisi Selatan
4 Pembongkaran Proforated Plate Panel Silincer di Area % - % On Progress >. Pembongkaran perforated plate dan isolasi dalam
Workshop PT.GAM panel silincer di workshop

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Minggu Sunday, October 25, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pemasangan akses scafolding area dinding utara gas duct 100 % 100 % Finish >. Pembongkaran Isolasi Gas Duct Silincer sisi Selatan
silincer >. Pembongkaran perforated plate di area dinding sisi utara
2 >. Pembongkaran perforated plate di area dinding sisi selatan 100 % 100 % Finish gas duct panel silincer, (pemotongan stut bolt dan as drat)
gas duct panel silincer, (pemotongan stut bolt dan as drat) dilanjutkan dengan pelepasan canal c
dilanjutkan dengan pelepasan canal c >. Pembongkaran perforated plate dan isolasi dalam
3 >. Pembongkaran Isolasi Gas Duct Silincer sisi Selatan 45 % 45 % On Progress panel silincer di workshop
4 >. Pembongkaran perforated plate dan isolasi dalam % - On Progress
panel silincer di workshop

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Senin Monday, October 26, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pembongkaran Isolasi Gas Duct Silincer sisi Selatan 45 % 55 % 100 % Finsih >. Pembongkaran perforated plate di area dinding sisi utara
2 >. Pembongkaran perforated plate di area dinding sisi utara % 45 % 45 % On Progress gas duct panel silincer, (pemotongan stut bolt dan as drat)
gas duct panel silincer, (pemotongan stut bolt dan as drat) dilanjutkan dengan pelepasan canal c
dilanjutkan dengan pelepasan canal c >. Moving Material Ceramic Fiber Blanket ke area Gas Ducting
3 >. Pembongkaran perforated plate dan isolasi dalam % % - % On Progress >. Pemasangan Scafolding untuk akses pembongkaran
panel silincer di workshop isolasi gas duct sisi utara silincer
>. Pembongkaran perforated plate dan isolasi dalam
panel silincer di workshop
>. Pembongkaran Isolasi area Discharge Seal Sisi air fan
sisi open cyle

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Selasa Tuesday, October 27, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pembongkaran perforated plate di area dinding sisi utara 45 % 25 % 70 % On Progress >. Pembongkaran perforated plate di area dinding sisi utara
gas duct panel silincer, (pemotongan stut bolt dan as drat) - gas duct panel silincer, (pemotongan stut bolt dan as drat)
dilanjutkan dengan pelepasan canal c - dilanjutkan dengan pelepasan canal c
2 >. Moving Material Ceramic Fiber Blanket ke area Gas Ducting 100 % 100 % Finish >. Pembongkaran Isolasi di area dinding sisi utara gas duct
3 >. Pemasangan Scafolding untuk akses pembongkaran 100 % 100 % Finish Silincer
isolasi gas duct sisi utara silincer - >. Pembongkaran perforated plate dan isolasi dalam
4 >. Pembongkaran perforated plate dan isolasi dalam - % - % On Progress panel silincer di workshop
panel silincer di workshop >. Pembongkaran Isolasi di area Inlet HRSG sisi Timur
5 >. Pembongkaran Isolasi area Discharge Seal Sisi air fan 100 % 100 % Finish
sisi open cyle

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
DAILY REPORT
JASA PERBAIKAN SILINCER & DINDING DALAM GUS DUCT
MI GT 1.1 MUARA KARANG 2020

Rabu Wednesday, October 28, 2020


Progress (%) Activities Next Day
No Description Previous Today Cumm.
Status

1 >. Pembongkaran perforated plate di area dinding sisi utara 70 % 30 % 100 % Finish >. Pembongkaran Plate Roof Gas Duct Silincer
gas duct panel silincer, (pemotongan stut bolt dan as drat) >. Pembongkaran Isolasi di area dinding sisi utara gas duct
dilanjutkan dengan pelepasan canal c Silincer
2 >. Pembongkaran Isolasi di area dinding sisi utara gas duct 40 % 40 % On Progrees
Silincer
3 >. Pembongkaran perforated plate dan isolasi dalam % - % On Progress
panel silincer di workshop
4 Pembongkaran Isolasi di area Inlet HRSG sisi Timur 100 % 100 % Finish

*) Note : Pembongkaran Isolasi Area dinding sisi utara gas


Duct Silincer tertunda karena ada Progress Cleaning dari
kontraktor lain

Equipment Direct Man Power Indirect Man Power Total Man Power
Weather Contractor Jam Kerja
No. Description Total No. Classification Total No. Classification Total
01 .00 07 .00 13 .00 19 .00 1 Peralatan Scafolding 1 lot 1
02 .00 08 .00 14 .00 20 .00 PT. GAM 10 2 Mobile Crane 1 unit 2
03 .00 09 .00 15 .00 21 .00 3 Generator c/w Panel Listrik 1 set 3
04 .00 10 .00 16 .00 22 .00 4 Mesin Las GTAW 200 A 2 Set 4
05 .00 11 .00 17 .00 23 .00 5 Mesin Las SMAW 160 A 4 Set 5
06 .00 12 .00 18 .00 24 .00 6 Plasma Cutting 200 A 1 Set 6
Note : 7 Mesin Blander 2 Set 7
H M C 8 Peralatan Isolasi 1 Lot 8
Hujan Cloudy / Mendung Clear / Cerah 9 Peralatan Pengecetan 1 Lot 9
10 Tool Box 3 Unit
TOTAL EQUIPMENT TOTAL TOTAL

Created by Acknowledge by, Approved by,


PT. GUNUNG API MULIA PT. GUNUNG API MULIA PT. PJB UP MUARA KARANG

( RIESKY FIRDYANO ) ( INDARTO)


QC Engineering Site Manager
Untuk hari ini 28 /10/20 kegiatan sbb
1.pembongkaran perforated plate dinding gas duct sisi utara dan selatan.
2.pembongkaran wire mesh dan isolasi yg rusak di area dinding gas duct sisi utara dan selatan.
3.pembongkaran isolasi ceramic fibre blanket isi panel silincer yg rusak.