GR 245617 - Contract
GR 245617 - Contract
GR 245617 - Contract
~upreme <!Court
;fflllanila
FIRST DIVISION
PERALTA, CJ
Chairperson,
- versus - CAGUIOA,
CARANDANG,
ZALAMEDA,
GAERLAN,JJ
DECISION
CARANDANG, J.:
Due to this, on July 13, 2016, El Dorado filed a Request for Arbitration
against PUIC before the CIAC and prayed that it be awarded the following:
t
Id. at 188-205 .
5
Id. at 58.
6
Id. at 59.
7
Id.
8
Id. at 60.
9
Id. at 60, 233.
10
Id.at 212.
II
Id. at 214.
12
Id. at 60-62.
13
Id. at 62.
Decision 3 G.R. Nos. 245617 & 245836
On March 6, 2017, the CIAC issued its Final Award. 17 The CIAC
discussed that is within its jurisdiction to take cognizance of the case because
the dispute between the parties arose from or is connected with the Owner-
Contractor Agreement entered into between El Dorado and ASPF
Construction. 18
On the other hand, the CIAC denied the prayer for exemplary damages
and attorney's fees submitted by PUIC. 23
14
Id. at 158.
15
Id. at 366-376.
16
Id. at 159,375.
17
Id. at 158- 176.
18
Id. at 166- 167.
19
Id. at 169- 170.
20
Id. at 170.
21
Id. at 173.
22
Id.
23
Id.
Decision 4 G.R. Nos. 245617 & 245836
Ruling of the CA
In its July 23, 2018 Consolidated Decision, 24 the CA agreed with the
CIAC that El Dorado is not entitled to its claim for unliquidated damages,
costs of retrofitting, and the interests and costs of arbitration. Further, the CA
deleted CIAC' s award of Pl ,700,000.00 liquidated damages in favor of El
Dorado. 25
Lastly, the CA denied PUIC's contention that the unpaid First Variation
/ Order Billing in the amount of P729,668. l 1 be offset against El Dorado's
claim because there is no proof to support the billings. 28
Since the CA deleted the only monetary claim awarded by CIAC in its
favor, El Dorado filed this Petition for Review on Certiorari3 1 reiterating its
demand to be reimbursed the amount of Pl 7,000,000.00 it paid as down
payment, P21,538,294.76 as liquidated damages, interest, costs of arbitration,
and attorney's fees. 32
24
25
26
27
28
29
Supra note 2.
Rollo, p. 80.
Id. at 71.
Id. at 72-75.
Id. at 79.
Id. at 82-101.
t
30
Supra note 3.
3I
Rollo, pp. 8-50.
32
Id. at 49.
33
Id. at 259-292.
34
Id. at 266.
Decision 5 G.R. Nos. 245617 & 245836
Issue
The question of whether the CIAC has jurisdiction over a surety, which
issued a performance bond to guarantee the performance by the contractor of
its obligation under the construction agreement, is not novel. In Prudential
Guarantee and Assurance, Inc. v. Anscor Land, Inc, 38 property owner Anscor
Land, Inc. (ALI) entered into a contract for the construction of an eight-unit
townhouse with Kraft Realty and Development Corporation (KRDC). KRDC
secured the completion of the construction project through a surety and
performance bond it obtained from Prudential Guarantee. The delay in the
construction project prompted ALI to terminate the contract and to file
arbitration proceedings against both KRDC and Prudential Guarantee.
Prudential Guarantee argued that CIAC did not have jurisdiction over it for
not being a signatory of the construction agreement between ALI and KRDC.
In ruling that the CIAC has jurisdiction over Prudential Guarantee, the
Supreme Court held that:
35 Id. at 10.
36 Bi fag v. Ay-ay, 809 Phil. 236, 248 (20 17), citing Mitsubishi Motors Philippines Corporation v.
Bureau ofCustoms, 760 Phil. 954, 960(2015).
n Id.
JS
644 Phil. 634 (20 10).
Decision 6 G.R. Nos. 245617 & 245836
xxxx
r
ARTICLE 8. ARBITRATION. -
Article 1
CONTRACT DOCUMENTS
a. Bid Proposal
xxxx
d. Notice to proceed
xxxx
Article 2
CONTRACT DOCUMENTS
q
2.01 The CONTRACT DOCUMENTS, which are
hereto incorporated and made integral part hereof, and which
40
Id. at 281-282.
Decision 9 G.R. Nos. 2456 17 & 245836
Since the CIAC has no jurisdiction over PUIC, the CIAC cannot rule
on the liability of PUIC over the Performance Bonds.
SO ORDERED.
,11
Rollo, p. 190.
42
C IVIL C ODE OF THE PHI LIPPINES, Al1. I 3 I I.
Decision 10 G.R. Nos. 245617 & 245836
WE CONCUR:
.PERALTA
tstice
S. CAGUIOA
==~
AER
SAMUEL~
Associate Justice
CERTIFICATION