AHU OQ & PQ Document
AHU OQ & PQ Document
AHU OQ & PQ Document
Date : xx/xx/xxxx
Report No: xx/xxxxx
AHU Operation and Performance Qualification Report Page 3 of 13
Table of Content
SN Details Page No.
2 Purpose 5
3 Scope 5
4 Responsibilities 5
5 Testing Instruments 5
6 Commissioning Checks 6
9 Annexure 12
9.1 Abbreviation 12
Project name
Project address
Project description
System details
Client details
Activity Details
Revision No
Revision Remark
2. Purpose:
Documented evidences that the equipment which has been successfully installed is operating according
to OEM’s specification and properly facilitate with the required utility.
3. Scope:
Operation Qualification of Fan comprising of the following main Equipment.
1. AHU
2. Electrical Panel
3. Ducting
4. Responsibilities:
1. Shall agree and follow the URS.
2. To prepare the detailed document on operation qualification
3. To submit the technical details of ventilation system/AHU as per the scope of supply
4. To ensure safe commissioning of equipment
5. To complete the commissioning of equipment and witness the same to client
5. Testing Instruments
Calibration Date
SN Instrument Name Purpose
Issue Expiry
1 Clamp on Meter To check current and voltage
2 Vane Anemometer To check air velocity
3 Micro Manometer To check air pressure
4 Tachometer To check rotational speed
5 Sound Meter To check noise level
6 Ultrasonic Flow meter To check water flow
7 Digital Pressure Gauge To check water pressure
8 Temperature Sensor To measure DBT
9 Hygrometer To measure DBT and RH
Instrument Calibration:
All testing and commissioning equipment shall be complete with valid calibration certificates.
All calibration certificates shall be submitted for client review at least one week prior to each
T&C exercise being undertaken.
AHU Operation and Performance Qualification Report Page 6 of 13
6. Commissioning Checks
The following criteria shall be satisfied before start of Testing & Commissioning
Inspection of the mechanical operation should be made to verify the equipment is correctly
operating.
6.1.1 Ensure equipment’s factory test certificate and warranty certificate is available
6.1.2 Confirm that equipment operation manual and technical data sheet available
6.1.3 Confirm all packing material removed from unit and air inlets/ discharges are free from
obstruction.
6.1.4 Confirm all major snags highlighted during installation qualification are rectified by
vendors and verified by respective owner
6.1.5 Confirm all necessary testing & commission instruments are available on site during
startup test; ensure all testing instruments are calibrated.
6.1.6 Confirm room is in good condition and fit for commissioning to commence.
6.1.7 Check power supply available at the incoming of Fan LCP and verify the voltage and
Phase sequence
Undertake all necessary checks and complete the Operation Testing and record the data
for Fan Checks.
5.1.1 Check all incoming voltage is normal 230V p-n or 415V p-p.
5.1.2 Check the control panel indication lamp functional properly.
5.1.3 Check the auto/stop/manual selector functional property.
5.1.4 Star delta starter timers are correctly set.
5.1.5 Turn the auto/stop/manual selector to manual position. Press the "start" button, so that
the motor will be running. Check the control panel indication correctly.
5.1.6 Record down the motor running current and the motor running current is within the full
load capacity of motor.
5.1.7 The direction of rotation is correct.
5.1.8 The drives are free from vibration and undue noise.
5.1.9 Motor and bearings are not overheating.
5.1.10 Emergency stop button functional properly.
AHU Operation and Performance Qualification Report Page 7 of 13
Witnessed By L&T
Accepted By Ikea
AHU Operation and Performance Qualification Report Page 10 of 13
Witnessed By L&T
Accepted By Ikea
AHU Operation and Performance Qualification Report Page 12 of 13
8. 9. Annexure:
8.1 9.1 Annexure: Abbreviations
GA General Arrangement
VFD Variable Frequency Driver
URS User Requirement Specification
CFM Cubic Feet Per Minute
FPM Feet per minute
IQ Installation Qualification
GI Galvanized Iron
GSS Galvanized Steel Sheet
HVAC Heating Ventilation and Air Conditioning
KW Kilowatt
Hz Hertz’s
mm Milli Meter
MOC Material of Construction
NA Not Applicable
WG Wire Gauge
Enclosed
Sr No Drawing Name
(Yes / No)
1 Technical Datasheet for fan 1-5
2 Technical Datasheet for fan 6-10
3 Technical Datasheet for fan 11-15
4 Factory test certificate 1-5
5 Factory test certificate 6-10
6 Factory test certificate 11-15
7 Warranty certificate 1-5
8 Warranty certificate 6-10
9 Warranty certificate 11-15
AHU Operation and Performance Qualification Report Page 13 of 13
Prepared by:
Department Name Designation Sign. / Date
Reviewed by:
Department Name Designation Sign/date
L&T
L&T
Approved by:
Ikea
Ikea