Valero Emerson Blending
Valero Emerson Blending
Valero Emerson Blending
Optimum
blending $$$$
Traditional gasoline blending methods. The original
blending system in the Pembroke refinery combined set volumes 1.1
of multiple gasoline component streams in a header to produce Crude mixing
penalty Suboptimum
each batch of finished gasoline, which was then routed into a set blending
of tanks. A sample was taken to the laboratory for analysis. After 1.0
the results were determined, the mixture would be “touched up”
to meet requirements, if necessary, and a certificate of quality/
Crude receiving Process units Blending Product shipping
analysis would be issued. Often, the touchup of an off-spec offsites
blend caused giveaway by adding a buffer to avoid carrying out
a second touchup. When the ship arrived, the blended gasoline FIG. 2. Capturing even a fraction of blend optimization opportunity
can present a strategic refining advantage.
would be pumped aboard from multiple tanks.
extra load/cost on the lab due to the retesting required; and, flows, etc., and calculates a recipe that is optimal for the blend
if there is a problem and the blend testing comes out off-spec, at any given moment to meet the optimization objectives. The
then shipments are delayed and incur potential demurrage optimized recipe from the BOSS is then fed to the regulatory
charges for holding up the ship. software package, which calculates the appropriate flow setpoints
In 2011, a study was undertaken to find ways to improve for the individual blend component control loops. For example,
the blending process: a project to replace the existing blending it takes a 41% alkylate recipe and translates that into a setpoint for
arrangement with one that would allow the blending of gasoline the alkylate flow control loop. It performs other regulatory level
directly to ship rather than solely to tankage. Such a system had functions as well, such as starting and stopping pumps, etc. FIG. 3
the potential to save millions of dollars each year by reducing shows schematically how the different parts fit together.
the number of tanks needed in gasoline service, as well as satisfy
the key performance indicators of lower average blend giveaway Consistent data helps obtain operator acceptance.
and the minimization of touchup blends. A critical success factor of the new system is the presentation of
consistent views to the operator. The design and implementation
Upgrading the blending system. The refinery was already of such a system must revolve around a single-screen integrated
scheduled for a control system update, which would ultimately approach to minimize the different operator system interactions.
include replacing the existing, and obsolete, distributed control All the blend regulatory controls—start/stop, routes, ramp,
system (DCS). The gasoline blending optimization project ratio and pacing—are handled in the DCS via commands from
was approved, and the project teams realized that it would the blend optimizer, akin to a master/slave control relationship.
integrate well with a new DCS system upgrade in the blending The operator displays are kept to a minimum and are integrated
and shipping areas. with the DCS graphic, which helps considerably in obtaining
Each batch of finished gasoline is made by simultaneously operator acceptance of the new system.
blending up to 21 different component streams in a header— The optimizer screen is the interface that the operators use to
typically 10 or fewer streams at a time, with mid-blend pump and start and monitor the blends. This screen is typically provided on
tank changes. Each component has a flowmeter, a proportional a separate interface screen, but using RDP from the DCS made it
integral derivative (PID) controller and a target ratio set by the possible to display this screen within the DCS system, simplifying it
control system. A set of online analyzers provide feedback for for the operators and demonstrating the “single-screen integrated”
optimization and certification using state-of-the-art redundant approach the project team and operators wanted.
sample compositors. The system can achieve up to 20 quality
limits simultaneously, although the number is usually closer to Challenges encountered. As expected, designing and
five. The output of the blending system (finished gasoline) can implementing the new system was not without its challenges,
go into tanks or directly onto a ship. many of which coincided with systems not always being
The blend optimization system used at Pembroke is available when needed. At the front-end engineering and design
comprised of a highly standardized mix of both hardware and (FEED) phase, there were gaps in the system knowledge, which
software components. The system is built of several layers: At is often the case in projects where very old systems are in place
the bottom (just above the field devices) is the DCS; on top and little or no good documentation still exists.
of the DCS is an advanced regulatory software package, which To in-line blend directly to a ship, a composite sampler that can
handles the ratio control functions. Above this layer is a blend take samples at required rates for the size of the blend and provide
optimization supervisory system (BOSS) software package. a composite of exactly what went onto the ship (it is very difficult
Sitting at the top of the pyramid, it processes data from analyzers, to test the separate tanks on a ship) is required. The sample
compositor takes a cross-section of the
Refinery blending unit DCS Blend optimizer final product exiting the blend header. This
SBO blend SBO blend
can be tested in the lab and a certificate of
FT
Tank AE M recipe ratio property M
quality/analysis can be produced.
component A
M control control These custom-built, redundant-
sample compositors, which are a proxy
Multi-blend
FT planning M for the blend tender going to the final
Tank AE
M
M software destination (i.e. ship), must be very
component B robust and very accurate. The reliability
M of such a system is critical, as any failure
Pipeline would result in uncertain specifications of
FT
M VGBOP the gasoline product loaded onto the ship.
Tank AE
M Redundant FTIR and M
component C vapor pressure online Note: Backup procedures are in place that
field analyzers allow for additional testing and sample
FT collection, should the compositors fail
M
Tank AE
M Multi-blend PT
M Finished to avoid any off-spec loading to the ship.
component D planning product tank
Coriolis software Establishing the reliability of this system
meter was a minor challenge, but in the end it
proved to be extraordinarily valuable to
FIG. 3. A schematic drawing of the various parts that comprise a blend optimization system.
the overall success of the project.